SUBCONTRACTOR:
Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 Areas being fed by AHU are clean.
2 Filters are clean.
3 Condense drain tray is clean and connected to
waste line.
4 Duct temperatures sensors and differential
pressure switches are installed.
5 All VCDs and splitters are open.
6 Fan impeller rotates freely.
7 Belt tension adjusted.
8 Alignment of pulleys and check bearings.
9 Overload setting and fuse rating.
10 Electrical connections and tight.
11 BMS wiring completed.
12 Heaters and connected if applicable.
13 DRV and GV are adjusted for design flow rate.
14 Check flow of condense drain and P trap.
THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH
CONTRACT SPECIFICATIONS.