PROJECT: PROJECT NAME SITE NO.

COMMISSIONING CHECK SHEET FOR AIR HANDLING UNIT Sheet No.

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 Areas being fed by AHU are clean.
2 Filters are clean.
3 Condense drain tray is clean and connected to
waste line.
4 Duct temperatures sensors and differential
pressure switches are installed.
5 All VCDs and splitters are open.
6 Fan impeller rotates freely.
7 Belt tension adjusted.
8 Alignment of pulleys and check bearings.
9 Overload setting and fuse rating.
10 Electrical connections and tight.
11 BMS wiring completed.
12 Heaters and connected if applicable.
13 DRV and GV are adjusted for design flow rate.
14 Check flow of condense drain and P trap.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH
CONTRACT SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY CLIENT: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature