You are on page 1of 1

PROJECT: PROJECT NAME SITE NO.

CHECK SHEET FOR TESTING AND COMMISSIONING OF Sheet No.


POWER AND CONTROL CABLES

SUBCONTRACTOR:

EQUIPMENT NO. : SEQUENCE NO. :


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 PHYSICAL CHECKS
The cable installation has to checked for:
a. Proper laying and dressing.
b. Cable tying.
c. Cable tray supports.
d. Cable identification and labelling.
e. Termination.
f. Damage.
2 INSULATION RESISTANCE TEST
a. Measure insulation resistance between cores of
all cable with 500V meggar and tabulate readings
b. Measure insulation resistance between cores and
ECC and earth terminal with a 500V meggar and
tabulate readings

Once the valves are found to be satisfactory, the


breakers may be switched on and the following
tests may be carried out.
3 PHASE ROTATION TEST
a. Check phase rotation at all points.
b. Phase rotation at all points should be same or
rectify.
THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH
CONTRACT SPECIFICATIONS.

CHECKED BY SUBCONTRACTOR: _____________________


Signature

WITNESSED BY CLIENT: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature