You are on page 1of 5

ANALISA HARGA SATUAN PEKERJAAN

Kegiatan : Rehabilitasi / Pemeliharaan Berkala Jalan


Pekerjaan : Pembangunan Jembatan
Nama Paket : Pembangunan Jembatan Pakuli - Bangga
Kabupaten : Sigi
Sumber Dana : (DAU)
Tahun Anggaran : 2011

3
1M Galian Tanah
0.400 Oh Pekerja @ Rp 30,000.00 = Rp 12,000.00
0.040 Oh Mandor @ Rp 60,000.00 = Rp 2,400.00
Rp 14,400.00

3
1M Urugan Kembali
0.192 Oh Pekerja @ Rp 30,000.00 = Rp 5,760.00
0.019 Oh Mandor @ Rp 60,000.00 = Rp 1,140.00
Rp 6,900.00

3
1M Urugan Pasir Dibawah Pondasi dan Lantai
3
1.200 M Pasir Urug @ Rp 60,000.00 = Rp 72,000.00
0.300 Oh Pekerja @ Rp 30,000.00 = Rp 9,000.00
0.010 Oh Mandor @ Rp 60,000.00 = Rp 600.00
Rp 81,600.00

3
1M Urugan Sirtu/Tanah Pilihan
3
1.200 M Sirtu/ Tanah Pilihan @ Rp 60,000.00 = Rp 72,000.00
0.250 Oh Pekerja @ Rp 30,000.00 = Rp 7,500.00
0.025 Oh Mandor @ Rp 60,000.00 = Rp 1,500.00

Rp 81,000.00
3
1M Pasangan Batu Kali 1 : 4
3
1.100 M Batu Kali / Batu Belah @ Rp 115,000.00 = Rp 126,500.00
163.000 Kg Semen @ Rp 1,100.00 = Rp 179,300.00
3
0.520 M Pasir Pasang @ Rp 90,000.00 = Rp 46,800.00
0.600 Oh Tukang @ Rp 50,000.00 = Rp 30,000.00
0.060 Oh Kepala Tukang @ Rp 55,000.00 = Rp 3,300.00
1.500 Oh Pekerja @ Rp 30,000.00 = Rp 45,000.00
0.075 Oh Mandor @ Rp 60,000.00 = Rp 4,500.00
Rp 435,400.00
3
1M Cor Beton Tumbuk 1 : 3 : 5
3
0.870 M Kerikil @ Rp 120,000.00 = Rp 104,400.00
218.000 Kg Semen @ Rp 1,100.00 = Rp 239,800.00
3
0.520 M Pasir Beton @ Rp 90,000.00 = Rp 46,800.00
3
0.044 M Koral Beton @ Rp 120,000.00 = Rp 5,280.00
0.250 Oh Tukang @ Rp 50,000.00 = Rp 12,500.00
0.025 Oh Kepala Tukang @ Rp 55,000.00 = Rp 1,375.00
1.650 Oh Pekerja @ Rp 30,000.00 = Rp 49,500.00
0.080 Oh Mandor @ Rp 60,000.00 = Rp 4,800.00
Rp 464,455.00
3
1M Cor Beton Tumbuk 1 : 2 : 3
3
0.780 M Kerikil @ Rp 120,000.00 = Rp 93,600.00
360.000 Kg Semen @ Rp 1,100.00 = Rp 396,000.00
0.480 m3 Pasir Beton @ Rp 90,000.00 = Rp 43,200.00
3
0.680 M Koral Beton @ Rp 120,000.00 = Rp 81,600.00
0.250 Oh Tukang @ Rp 50,000.00 = Rp 12,500.00
0.025 Oh Kepala Tukang @ Rp 55,000.00 = Rp 1,375.00
1.650 Oh Pekerja @ Rp 30,000.00 = Rp 49,500.00
0.080 Oh Mandor @ Rp 60,000.00 = Rp 4,800.00
Rp 682,575.00

1 Kg Pembesian dengan Besi Polos atau Besi Ulir


1.050 Kg Besi beton (polos/ulir) @ Rp 16,000.00 = Rp 16,800.00
0.015 Kg Kawat beton @ Rp 14,000.00 = Rp 210.00
0.007 Org Pekerja @ Rp 30,000.00 = Rp 210.00
0.007 Org Tukang besi @ Rp 50,000.00 = Rp 350.00
0.0007 Org Kepala tukang @ Rp 55,000.00 = Rp 38.50
0.0003 Org Mandor @ Rp 60,000.00 = Rp 18.00
Rp 17,626.50
2
1M Pasang Bekesting
3
0.040 M Kayu Klas III @ Rp 1,700,000.00 = Rp 68,000.00
0.300 Kg Paku Biasa @ Rp 22,500.00 = Rp 6,750.00
0.260 Oh Tukang @ Rp 50,000.00 = Rp 13,000.00
0.026 Oh Kepala Tukang @ Rp 55,000.00 = Rp 1,430.00
0.300 Oh Pekerja @ Rp 30,000.00 = Rp 9,000.00
0.005 Oh Mandor @ Rp 60,000.00 = Rp 300.00
Rp 98,480.00
3
1M Cor Beton Tumbuk 1 : 2 : 3 Untuk Kanstin + Bekesting
3
1M Cor Beton Tumbuk 1 : 2 : 3 Rp 682,575.00
2
1M Pasang Bekesting Rp 98,480.00
Rp 781,055.00
3
1M Cor Beton Bertulang 1 : 2 : 3 Untuk Plat/Block Beton
3
1M Cor Beton Bertulang 1 : 2 : 3 @ Rp 682,575.00 Rp 682,575.00
110 Besi Beton @ Rp 17,626.50 Rp1,938,915.00
2
1M Pasang Bekesting @ Rp 98,480.00 Rp 98,480.00
Rp2,719,970.00

3
1M Cor Beton Bertulang 1 : 2 : 3 Untuk Kolom
3
1M Cor Beton Bertulang 1 : 2 : 3 @ Rp 682,575.00 Rp 682,575.00
110 Besi Beton @ Rp 17,626.50 Rp1,938,915.00
2
1M Pasang Bekesting @ Rp 98,480.00 Rp 98,480.00
Rp2,719,970.00

3
1M Cor Beton Bertulang 1 : 2 : 3 Untuk Ring Balk dan Sloff
3
1M Cor Beton Bertulang 1 : 2 : 3 @ Rp 682,575.00 Rp 682,575.00
110 Besi Beton @ Rp 17,626.50 Rp1,938,915.00
2
1M Pasang Bekesting @ Rp 98,480.00 Rp 98,480.00
Rp2,719,970.00
2
1M Plesteran Dinding Camp. 1 : 4
3
0.020 M Pasir Pasang @ Rp 90,000.00 = Rp 1,800.00
5.200 Kg Semen @ Rp 1,100.00 = Rp 5,720.00
0.150 Oh Tukang @ Rp 50,000.00 = Rp 7,500.00
0.015 Oh Kepala Tukang @ Rp 55,000.00 = Rp 825.00
0.200 Oh Pekerja @ Rp 30,000.00 = Rp 6,000.00
0.010 Oh Mandor @ Rp 60,000.00 = Rp 600.00
Rp 22,445.00
3
1M Pekerjaan Gelagar Kayu

4.0000 Oh Pekerja @ Rp 30,000.00 = Rp 120,000.00


0.2000 Oh Mandor @ Rp 60,000.00 = Rp 12,000.00
12.0000 Oh Tukang Kayu @ Rp 50,000.00 = Rp 600,000.00
1.2000 Oh Kepala Tukang Kayu Rp 55,000.00 = Rp 66,000.00
1.1000 M3 Kayu Kelas I @ Rp 1,700,000.00 = Rp 1,870,000.00
0.8000 Kg Paku Biasa @ Rp 22,500.00 = Rp 18,000.00
Rp2,686,000.00
2
1M Pekerjaan Lantai Kayu

3
0.0440 M Papan Kayu Klas I Rp 1,700,000.00 = Rp 74,800.00
0.100 Kg Paku biasa 2" - 5" @ Rp 22,500.00 = Rp 2,250.00
0.150 Oh Pekerja @ Rp 30,000.00 = Rp 4,500.00
0.450 Oh Tukang kayu @ Rp 50,000.00 = Rp 22,500.00
0.045 Oh Kepala tukang Rp 55,000.00 = Rp 2,475.00
0.075 Oh Mandor @ Rp 60,000.00 = Rp 4,500.00
Rp 111,025.00
3
1M Pekerjaan Gapit, Tiang dan Balok Sandaran
2.0000 Oh Pekerja @ Rp 30,000.00 = Rp 60,000.00
0.1000 Oh Mandor @ Rp 60,000.00 = Rp 6,000.00
3.0000 Oh Tukang Kayu @ Rp 50,000.00 = Rp 150,000.00
1.1000 Oh Kepala Tukang Kayu @ Rp 55,000.00 = Rp 60,500.00
1.1000 M3 Kayu Kelas I @ Rp 1,700,000.00 = Rp 1,870,000.00
0.8000 Kg Paku Biasa @ Rp 22,500.00 = Rp 18,000.00
Rp2,164,500.00

1 Buah Pasang Klem Penggantung Atas


1.000 Buah Klem Besi 3 mm @ Rp 15,000.00 = Rp 15,000.00
3.000 Buah Baut 12 @ Rp 2,000.00 = Rp 6,000.00
0.150 Oh Tukang @ Rp 60,000.00 = Rp 9,000.00
0.015 Oh Kepala Tukang @ Rp 55,000.00 = Rp 825.00
0.015 Oh Pekerja @ Rp 30,000.00 = Rp 450.00
0.005 Oh Mandor @ Rp 60,000.00 = Rp 300.00
Rp 31,575.00
1 Buah Pasang Klem Penggantung Bawah
1.000 Buah Klem Besi 3 mm @ Rp 25,000.00 = Rp 25,000.00
3.000 Buah Baut 12 @ Rp 2,000.00 = Rp 6,000.00
0.150 Oh Tukang @ Rp 60,000.00 = Rp 9,000.00
0.015 Oh Kepala Tukang @ Rp 55,000.00 = Rp 825.00
0.015 Oh Pekerja @ Rp 30,000.00 = Rp 450.00
0.005 Oh Mandor @ Rp 60,000.00 = Rp 300.00

Rp 41,575.00

1
1M Pekerjaan Besi Kabel/Sling Utama 1 1/2"
1.000 M1 Besi Kabel/Sling 1 1/2" @ Rp 115,000.00 = Rp 115,000.00
0.250 Oh Tukang @ Rp 60,000.00 = Rp 15,000.00
0.070 Oh Kepala Tukang @ Rp 55,000.00 = Rp 3,850.00
0.500 Oh Pekerja @ Rp 30,000.00 = Rp 15,000.00
0.070 Oh Mandor @ Rp 60,000.00 = Rp 4,200.00

Rp 153,050.00

1
1M Pekerjaan Besi Kabel/Sling Angin 1"
1.000 M1 Besi Kabel/Sling 1" @ Rp 90,000.00 = Rp 90,000.00
0.250 Oh Tukang @ Rp 60,000.00 = Rp 15,000.00
0.070 Oh Kepala Tukang @ Rp 55,000.00 = Rp 3,850.00
0.500 Oh Pekerja @ Rp 30,000.00 = Rp 15,000.00
0.070 Oh Mandor @ Rp 60,000.00 = Rp 4,200.00

Rp 128,050.00

1
1M Pekerjaan Besi Penggantung Dia 14 mm
1.000 M1 Besi Beton Dia 14 mm @ Rp 8,000.00 = Rp 8,000.00
0.050 Oh Tukang @ Rp 60,000.00 = Rp 3,000.00
0.025 Oh Kepala Tukang @ Rp 55,000.00 = Rp 1,375.00
0.100 Oh Pekerja @ Rp 30,000.00 = Rp 3,000.00
0.013 Oh Mandor @ Rp 60,000.00 = Rp 750.00

Rp 16,125.00