10 - Analisa Jembatan Gantung Pakuli Bangga
10 - Analisa Jembatan Gantung Pakuli Bangga
3
1M Galian Tanah
0.400 Oh Pekerja @ Rp 30,000.00 = Rp 12,000.00
0.040 Oh Mandor @ Rp 60,000.00 = Rp 2,400.00
Rp 14,400.00
3
1M Urugan Kembali
0.192 Oh Pekerja @ Rp 30,000.00 = Rp 5,760.00
0.019 Oh Mandor @ Rp 60,000.00 = Rp 1,140.00
Rp 6,900.00
3
1M Urugan Pasir Dibawah Pondasi dan Lantai
3
1.200 M Pasir Urug @ Rp 60,000.00 = Rp 72,000.00
0.300 Oh Pekerja @ Rp 30,000.00 = Rp 9,000.00
0.010 Oh Mandor @ Rp 60,000.00 = Rp 600.00
Rp 81,600.00
3
1M Urugan Sirtu/Tanah Pilihan
3
1.200 M Sirtu/ Tanah Pilihan @ Rp 60,000.00 = Rp 72,000.00
0.250 Oh Pekerja @ Rp 30,000.00 = Rp 7,500.00
0.025 Oh Mandor @ Rp 60,000.00 = Rp 1,500.00
Rp 81,000.00
3
1M Pasangan Batu Kali 1 : 4
3
1.100 M Batu Kali / Batu Belah @ Rp 115,000.00 = Rp 126,500.00
163.000 Kg Semen @ Rp 1,100.00 = Rp 179,300.00
3
0.520 M Pasir Pasang @ Rp 90,000.00 = Rp 46,800.00
0.600 Oh Tukang @ Rp 50,000.00 = Rp 30,000.00
0.060 Oh Kepala Tukang @ Rp 55,000.00 = Rp 3,300.00
1.500 Oh Pekerja @ Rp 30,000.00 = Rp 45,000.00
0.075 Oh Mandor @ Rp 60,000.00 = Rp 4,500.00
Rp 435,400.00
3
1M Cor Beton Tumbuk 1 : 3 : 5
3
0.870 M Kerikil @ Rp 120,000.00 = Rp 104,400.00
218.000 Kg Semen @ Rp 1,100.00 = Rp 239,800.00
3
0.520 M Pasir Beton @ Rp 90,000.00 = Rp 46,800.00
3
0.044 M Koral Beton @ Rp 120,000.00 = Rp 5,280.00
0.250 Oh Tukang @ Rp 50,000.00 = Rp 12,500.00
0.025 Oh Kepala Tukang @ Rp 55,000.00 = Rp 1,375.00
1.650 Oh Pekerja @ Rp 30,000.00 = Rp 49,500.00
0.080 Oh Mandor @ Rp 60,000.00 = Rp 4,800.00
Rp 464,455.00
3
1M Cor Beton Tumbuk 1 : 2 : 3
3
0.780 M Kerikil @ Rp 120,000.00 = Rp 93,600.00
360.000 Kg Semen @ Rp 1,100.00 = Rp 396,000.00
0.480 m3 Pasir Beton @ Rp 90,000.00 = Rp 43,200.00
3
0.680 M Koral Beton @ Rp 120,000.00 = Rp 81,600.00
0.250 Oh Tukang @ Rp 50,000.00 = Rp 12,500.00
0.025 Oh Kepala Tukang @ Rp 55,000.00 = Rp 1,375.00
1.650 Oh Pekerja @ Rp 30,000.00 = Rp 49,500.00
0.080 Oh Mandor @ Rp 60,000.00 = Rp 4,800.00
Rp 682,575.00
3
1M Cor Beton Bertulang 1 : 2 : 3 Untuk Kolom
3
1M Cor Beton Bertulang 1 : 2 : 3 @ Rp 682,575.00 Rp 682,575.00
110 Besi Beton @ Rp 17,626.50 Rp1,938,915.00
2
1M Pasang Bekesting @ Rp 98,480.00 Rp 98,480.00
Rp2,719,970.00
3
1M Cor Beton Bertulang 1 : 2 : 3 Untuk Ring Balk dan Sloff
3
1M Cor Beton Bertulang 1 : 2 : 3 @ Rp 682,575.00 Rp 682,575.00
110 Besi Beton @ Rp 17,626.50 Rp1,938,915.00
2
1M Pasang Bekesting @ Rp 98,480.00 Rp 98,480.00
Rp2,719,970.00
2
1M Plesteran Dinding Camp. 1 : 4
3
0.020 M Pasir Pasang @ Rp 90,000.00 = Rp 1,800.00
5.200 Kg Semen @ Rp 1,100.00 = Rp 5,720.00
0.150 Oh Tukang @ Rp 50,000.00 = Rp 7,500.00
0.015 Oh Kepala Tukang @ Rp 55,000.00 = Rp 825.00
0.200 Oh Pekerja @ Rp 30,000.00 = Rp 6,000.00
0.010 Oh Mandor @ Rp 60,000.00 = Rp 600.00
Rp 22,445.00
3
1M Pekerjaan Gelagar Kayu
3
0.0440 M Papan Kayu Klas I Rp 1,700,000.00 = Rp 74,800.00
0.100 Kg Paku biasa 2" - 5" @ Rp 22,500.00 = Rp 2,250.00
0.150 Oh Pekerja @ Rp 30,000.00 = Rp 4,500.00
0.450 Oh Tukang kayu @ Rp 50,000.00 = Rp 22,500.00
0.045 Oh Kepala tukang Rp 55,000.00 = Rp 2,475.00
0.075 Oh Mandor @ Rp 60,000.00 = Rp 4,500.00
Rp 111,025.00
3
1M Pekerjaan Gapit, Tiang dan Balok Sandaran
2.0000 Oh Pekerja @ Rp 30,000.00 = Rp 60,000.00
0.1000 Oh Mandor @ Rp 60,000.00 = Rp 6,000.00
3.0000 Oh Tukang Kayu @ Rp 50,000.00 = Rp 150,000.00
1.1000 Oh Kepala Tukang Kayu @ Rp 55,000.00 = Rp 60,500.00
1.1000 M3 Kayu Kelas I @ Rp 1,700,000.00 = Rp 1,870,000.00
0.8000 Kg Paku Biasa @ Rp 22,500.00 = Rp 18,000.00
Rp2,164,500.00
Rp 41,575.00
1
1M Pekerjaan Besi Kabel/Sling Utama 1 1/2"
1.000 M1 Besi Kabel/Sling 1 1/2" @ Rp 115,000.00 = Rp 115,000.00
0.250 Oh Tukang @ Rp 60,000.00 = Rp 15,000.00
0.070 Oh Kepala Tukang @ Rp 55,000.00 = Rp 3,850.00
0.500 Oh Pekerja @ Rp 30,000.00 = Rp 15,000.00
0.070 Oh Mandor @ Rp 60,000.00 = Rp 4,200.00
Rp 153,050.00
1
1M Pekerjaan Besi Kabel/Sling Angin 1"
1.000 M1 Besi Kabel/Sling 1" @ Rp 90,000.00 = Rp 90,000.00
0.250 Oh Tukang @ Rp 60,000.00 = Rp 15,000.00
0.070 Oh Kepala Tukang @ Rp 55,000.00 = Rp 3,850.00
0.500 Oh Pekerja @ Rp 30,000.00 = Rp 15,000.00
0.070 Oh Mandor @ Rp 60,000.00 = Rp 4,200.00
Rp 128,050.00
1
1M Pekerjaan Besi Penggantung Dia 14 mm
1.000 M1 Besi Beton Dia 14 mm @ Rp 8,000.00 = Rp 8,000.00
0.050 Oh Tukang @ Rp 60,000.00 = Rp 3,000.00
0.025 Oh Kepala Tukang @ Rp 55,000.00 = Rp 1,375.00
0.100 Oh Pekerja @ Rp 30,000.00 = Rp 3,000.00
0.013 Oh Mandor @ Rp 60,000.00 = Rp 750.00
Rp 16,125.00