Sia, Jason Joseph F.

J.O.C. D.O.R. P.D.N. D.O.D.


ADO 110 20 180
BATU 122 10 175
CUTA 130 18 210
DINO 120 30 200
ENTRO 125 16 230

FCFS
Job Seq. Date Order Received Production days Flow Time Date Order Due Staring from day 130 Job Lateness
ADO 110 20 20 180 50 0
DINO 120 30 50 175 45 0
BATU 122 10 60 210 80 15
ENTRO 125 16 76 200 70 0
CUTA 130 18 94 230 100 14
94 300 29
Ave. Completion time 60
Utilization 31.33%
Ave. no. of Jobs in the system 3.19
Ave. Job lateness 5.8

SPT
Job Seq. Date Order Received Production days Flow Time Date Order Due Staring from day 130 Job Lateness
BATU 122 10 10 175 45 0
ENTRO 125 16 26 230 100 0
CUTA 130 18 44 210 80 0
ADO 110 20 64 180 50 14
DINO 120 30 94 200 70 24
94 238 38
Ave. Completion time 47.6
Utilization 39.50%
Ave. no. of Jobs in the system 2.53
Ave. Job lateness 7.6

EDD
Job Seq. Date Order Received Production days Flow Time Date Order Due Staring from day 130 Job Lateness
BATU 122 10 10 175 45 0
ADO 110 20 30 180 50 0
DINO 120 30 60 200 70 0
CUTA 130 18 78 210 80 0
ENTRO 125 16 94 230 100 0
94 272 0
Ave. Completion time 54.4
Utilization 34.56%
Ave. no. of Jobs in the system 2.89
Ave. Job lateness 0

LPT
Job Seq. Date Order Received Production days Flow Time Date Order Due Staring from day 130 Job Lateness
DINO 120 30 30 200 70 0
ADO 110 20 50 180 50 0
CUTA 130 18 68 210 80 0
ENTRO 125 16 84 230 100 0
BATU 122 10 94 175 45 49
94 326 49
Ave. Completion time 65.2
Utilization 28.83%
Ave. no. of Jobs in the system 3.47
Ave. Job lateness 9.8

Job ORDER CUSTOMER PROJECT COST ‘000 Penalty


Cost / Day Project Cost * Penalty Cost

ADO 4250 5% 212.5


BATU 1350 2% 27
CUTA 250 10% 25
DINO 7780 7% 544.6
ENTRO 100 20% 20

RESULTS
Rule Ave. Completion (Days) Utilization Ave. No. of jobs in the system Ave. Lateness Cost for Lateness
FCFS 60 31.33% 3.19 5.8 $755.00
SPT 47.6 39.50% 2.53 7.6 $16,045.40
EDD 54.4 34.56% 2.89 0 $0.00
LPT 65.2 28.83% 3.47 9.8 $1,323.00

a. Which priority rule give the company the least cost of penalty?
- EDD
b. Which priority rule give the company the highest utilization?
-SPT
c. Which priority rule give the company the maximum average jobs?
-LPT
d. Which priority rule give the company the maximum average completion time?
-LPT
To finally decide on its schedule, the company has the following weighted factors for decision making as stated below:
(1- Lowest Score, 4-Highest Score)
Decision Criteria Percentage EDD SPT LPT FCFS
Average Completion Time 20% 3 4 1 2
Company Utilization 30% 3 4 1 2
Average number of Job 15% 3 4 1 2
Cost 35% 4 1 2 3
Total Rating 100% 3.35 2.95 1.35 2.35

What is the final Sequence and explain your answer?


- My final sequence is EDD, SPT, FCFS, LPT. Based on the calculations above, the highest total rating is EDD, followed by SPT and so on.