- Under which of the folloginw processes does Analogous Estimating appear as an input?
i) Estimate Cost
ii) Estimate Activity Durations
iii) All of the above
iv) None of the above
- In which of the following knowledge areas does Perform Integrated Chance Control
Appear?
i) Change Control Managemente
ii) Project Integration Management
iii) Project Scope Management
iv) Project Change Management
- Your are the proyect manager for a highway construction Project. You have analysed the
work that needs to be done and have come up with a list of activities. You consulted with
the Project sponsor to find out any important milestone that you need to meet. What is
the next thing that you shoudl do ideally?
i) Create the Project Schedule
ii) Perform the define activities process
iii) Consult your Project management plan to figure out how to handle any Schedule
changes
iv) Figure out the dependencias between activities and create a diagramo f the activity
network
- A Project manager has just finished the risk response plan for $387,000 engineering
Project. Which of the following should he probably do next?
i) Determine the overall risk rating of the Project
ii) Begin to analyse the risks that show up in the Project drawings
iii) Add work packages to the Project WBS
iv) Hold Project risk review.