KUIS Manajemen Konstruksi Kelas C

MANAJEMEN KONSTRUKSI Nama : Minzorus Sunan


Senin, 16 November 2020 NIM : F1A018064

Nama Waktu WAKTU PELAKSANAAN


Nomor Kegiatan HARGA PERSENTASE
Kegiatan (Minggu) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1 A 5 Rp 5.000.000,00 3,846 0,769231 0,769231 0,769231 0,769231 0,769231 100
2 B 4 Rp 3.000.000,00 2,308 0,576923 0,576923 0,576923 0,576923
3 C 3 Rp 3.000.000,00 2,308 0,77 0,77 0,77
4 D 4 Rp 5.000.000,00 3,846 0,961538 0,961538 0,961538 0,961538
5 E 3 Rp 10.000.000,00 7,692 2,564103 2,564103 2,564103
6 F 4 Rp 15.000.000,00 11,538 2,884615 2,884615 2,884615 2,884615
7 G 4 Rp 10.000.000,00 7,692 1,923077 1,923077 1,923077 1,923077
8 H 3 Rp 10.000.000,00 7,692 2,564103 2,564103 2,564103
9 I 2 Rp 5.000.000,00 3,846 1,923077 1,923077 50
10 J 5 Rp 10.000.000,00 7,692 1,538462 1,538462 1,538462 1,538462 1,538462
11 K 5 Rp 7.000.000,00 5,385 1,076923 1,076923 1,076923 1,076923 1,076923
12 L 3 Rp 5.000.000,00 3,846 1,282051 1,282051 1,282051
13 M 4 Rp 10.000.000,00 7,692 1,923077 1,923077 1,923077 1,923077
14 N 4 Rp 7.000.000,00 5,385 1,346154 1,346154 1,346154 1,346154
15 O 4 Rp 10.000.000,00 7,692 1,923077 1,923077 1,923077 1,923077
16 P 3 Rp 15.000.000,00 11,538 3,846154 3,846154 3,846154 0
2,115385 2,115385 2,115385 3,269231 8,141 8,333 8,333 7,308 5,500 5,179 5,179 5,179 4,282 4,551 4,551 5,192 3,269 5,769 5,769 3,846
∑ Rp 130.000.000,00 100,00
2,115385 4,230769 6,346154 9,615385 17,756 26,090 34,423 41,731 47,231 52,410 57,590 62,769 67,051 71,603 76,154 81,346 84,615 90,385 96,154 100