Professional Documents
Culture Documents
There are a dozen major problems which may occur during primary
cementations. The following is a list of those problems.
1
in which the cement slurry and the mud being displaced is flowing
during displacement is dominant.
SOLUTION: The recognized flow regimes are (1) plug, (2) laminar
and, (3) turbulent. The dominant solution to poor mud displacement is
cement hydraulics. Other aids are pipe rotation and reciprocation.
Mobil Oil showed rotation speeds of 35 rpm are sufficient. Exxon
showed 80% standoff with centralizers is sufficient with proper cement
and hydraulics.
2
usually thinned (PV and YP are reduced) all into turbulent flow. Fully
developed turbulent flow calls for Reynold's number of 3000 or more.
In all cases the Reynold's number should be calculated with the power law
equation.
Turbulent flow cementations are primarily chosen because they require the
shortest of all cementation times; and not chosen because of high circulating
bottom hole pressures.
The laminar flow technique has the smallest displacement efficiencies (75%
and less) of the three flow regimes and often gives inadequate cementations.
It should be avoided when possible.
However, because of equipment limitations and poor planning, the technique
is often inadvertently used.
SOLUTION: Reduce the density of the cement column and the circulating
friction pressure loss. See the ECD calculation for the turbulent flow
cementation section.
3
PROBLEM.4: SWAPPING OUT OF MUD AND CEMENT BELOW PIPE
MECHANISM: Casing or a plug back pipe is not run to the total depth of
the well and the mud below the pipe buoyantly rises into the annulus where
the cement was circulated.
While the mud is rising, the cement must be falling along side it; thus, mud
and cement are "swapping out."
SOLUTION: If pipe is close to the bottom of the hole (50 feet or so; as is
the usual case of floaters), a pill of a density equal or slightly greater than
that of the cement may be circulated to the bottom of the hole prior to the
cementation of the pipe.
If an up hole cement plug is to be set, the pipe is run one stand below the
desired location of the bottom of the plug and a very viscous bentonite pill is
circulated. Thereafter, the pipe is raised one stand and the cement is
circulated into place. Of course, the viscous bentonite pill can be used if the
casing is close to the bottom of the hole.
SOLUTION: Check the mix water and retard the cement as needed.
4
PROBLEM.7: PERMEABILITY OF CEMENT MAY CAUSE AN INTERZONAL
FLOW.
SOLUTION: The gas migration resulting from the first mechanism has not
been totally solved; however right angle setting cements and appropriate
additives have been helpful. Sometimes successful additives are latex flakes
and alumina particles. The second mechanism requires careful planning of
cementation setting times and circulating times to eliminate long periods of
quiescent unset cement in the drill hole.
SOLUTION: One solution is to reduce the pressures within casing while the
cement is setting. This may be done by bumping the cement plugs with a
light fluid and not holding a surface pressure while the cement sets. Another
is plan not to lower the pressure in the pipe at critical times.
5
PROBLEM.10: TEMPERATURE RETROGRADE OF CEMENT.
SOLUTION: It has been found in the laboratory that cements with higher
moduli of elasticity give less shattering (neat cement).
6
CEMENTATION TEMPERATURES
The three axes of the chart are sensor temperatures in °F, geothermal
temperatures at each sensor in °F, sensor pressures in 1000's of psi, and time
in minutes. Each line in the chart represents temperatures and pressures
detected by a sensor whose number is at the end of that line. Corresponding
geothermal temperatures are shown as black dots. Cement mixing and
pumping began at the left axis at a time of 750 minutes. Displacement ended
at 860 minutes.
Prior pumping had lowered the temperatures at each sensor to the values
shown on the left axis. The lines show that heating at the sensors was
gradual until the time of 1010 minutes (4.3 hours). For example at sensor #1,
located near the bottom of the hole where the geothermal temperature is
218°F, the gradual increase raised the temperature from 155°F to 190°F in
4.3 hours. Thereafter, heat of hydration of the setting cement combined with
conduction from the formations to quickly raise the temperature of the
cement above the geothermal temperature at that sensor.
The study shows that large bodies of cold fluid heats slowly in the annulus
between formation and casing and that pressures within set cement drop
substantially below the pressures developed by the unset cement slurry.
7
EXAMPLE 1
The cement bond log which was taken from a plug flow cementation
indicates an excellent cement pipe bond. Other points are that the cement to
mud transition is sharp, free pipe is clearly shown, and bonded pipe to free
pipe signal strength is excellent. The following analysis points out that the
cement was in plug flow.
Data is taken from the well log and the power law sheet. The cement
properties are those for the class "G" cement.
K an
1.125
K
Kan = 0.0713
1 42
V= 2 0.339 ft / sec
2.45 6.752 4.52
The Reynold’s number is
0.436
6.75 4.5
2.79 .339 2 0.43615.9
NR = 144 18
0.0713
F = 0.0889
0.889 15.9 0.339 2
P 6000 167 psid
25.8 6.75 4.5
Because the Reynold's number is about 1/5 of the upper value of 100 for
plug flow, an excellent plug should form in the annulus and a satisfactory
cementation should result.
8
EXAMPLE 2
The cement bond log shown in the turbulent flow cementation figure
illustrates better bonding where the smaller hole diameters exists. At depths
of 5720 - 5750 the hole diameter is 24 or greater and less bonding has
taken place than at the depth of 5695 where the hole is 13 1/4 diameter.
The data for the calculations of the Reynold's numbers were taken from the
figure. Casing TD is 6482.
922
V= 0.779 ft / sec
2.45 242 9.6252
9
922
V= 4.54 ft / sec
2.4513.252 9.6252
If the cement had been circulated to the surface as was planned, then the
circulating bottom hole pressure would have been as calculated below.
Note : that this ECD must be less than the fracture extension gradient if
circulation is not be lost.
10