Professional Documents
Culture Documents
contracting: Contractual
issues I wish I knew then
Samuel Cho
Senior Associate
31 August 2015
1. Outline
Why sub-contract?
Case law
2. Why Sub-Contract?
Resources
Required by law
Flexibility
Domestic sub-contracting
Main contractor is fully responsible to the employer for the sub-contractor’s work
Nominated sub-contracting
Main contracts commonly provide that the employer may choose certain sub-
contractors to carry out ‘prime cost’ work
Named sub-contracting
Employer’s liability
Employer can choose its associated with NSC
own specialist does not arise
Employer is not
responsible for sub- contractor and bargain
Pros for the best price, terms
contractor’s default Gives the employer
of its contract, reduced some element of
procurement time
involvement in the
selection process
No implied obligation of
fitness for purpose of
the NSC work for the
main contractor Employer has limited
Employer has no control control over choice of
Cons over the choice of sub- Employer’s liability may sub-contractors
contractors be greater compared to compared to NSC
domestic sub-contract
(depends on contract
terms)
5. Relationship between Main Contractor and
Nominated Sub-Contractor
General rule: main contractor is liable to the employer for any
default by the NSC - may be modified by a construction of the
main contract and the sub-contract
Incorporation of terms
Renomination of NSC
If the original NSC dropped out, there was an implied duty on the
employer to make a further nomination (Bickerton v NW Metropolitan
Regional Hospital Board [1970] 1 WLR 607)
Termination
Check Main Contract terms for any employer/ engineer approval and
procedure for proper termination
6. Relationship between Employer and Nominated
Sub-Contractor
No privity of contract
But may have a remedy against the engineer (Vigers, Sons & Co Ltd v
Swindell [1939] 3 All ER 590)
6. Relationship between Employer and Nominated
Sub-Contractor (cont.)
(3) Collateral warranty - where NSC warrants the quality of its work
(Shanklin Pier Co Ltd v Detel Products [1951] 2 KB 854)
6. Relationship between Employer and Nominated
Sub-Contractor (cont.)
Direct payment clause
Does not give rise to an implied contract for payment as between the
employer and sub-contractor (Yew Sang Hong Ltd v Hong Kong HA
[2008] BLR 563)
(1) Period of time lost by the withdrawal of the first NSC: A delay caused
by the original NSC's withdrawal at the main contractor's risk
Tripartite arbitration
Joinder / consolidation
Same arbitrator(s)
8. Dispute Resolution under Nominated Sub-Contract
(cont.)
Statutory adjudication
Application to seek leave to appeal on two questions of law arising out of an arbitrator’s
award
Second question concerns liability for defective specialist design - if a main contractor
subcontracts works to a NSC who then carries out design work as well, is the main
contractor, without more, liable to the employer for that design work?
Held:
Extent to which the main contractor is liable for defects in the workmanship of the
NSC will depend on the precise terms of the various contracts. Not liable in this
case.
The main contract documents did not include any obligation on the part of the
Defendants to perform any design work at all - main contractor cannot acquire
design liability merely because he is instructed to enter into a subcontract with a
NSC who is going to do some design work on behalf of the employer.
10. Great Eastern Hotel v John Laing Construction
[2005] 99 Con LR 45
Consortium of Conran Hotel Group and Arcadian was awarded £10 million in
damages for loss of profit and additional costs
Held:
John Laing was not responsible for the performance of the sub-contractors
as though they were a traditional main contractor
However, the primary obligation under the contract was to exercise all
reasonable skill, care and diligence of a properly qualified and competent
construction manager
10. Great Eastern Hotel v John Laing Construction
[2005] 99 Con LR 45 (cont.)
Potential problem
Questions?
Minter Ellison
Samuel Cho
Senior Associate
T +852 2841 6891
M +852 9722 8616
EMAIL samuel.cho@minterellison.com