side and fuel tank another side that make the imbalance weight container. So, step unloading
Generator might have 2 options:
2. Two crane 25T will lift container up and put on the floor.
3. One forklift 6T will pull off Generator from container to the floor (must be strong floor for
Generator 14T).
4. Finally lift up generator by crane to the permanent area in supply building3.
Option2: Using 1 crane 50T + one forklift + one Trailer.
1. we need to find a clear area close to supply building 3 for Trailer with container park and one
empty trailer park at the back side.
2. Lift up forklift 6T to empty trailer and forklift will pull off generator from container to put on
trailer.
3. Finally lift up generator by crane from trailer to the permanent area in supply building3
- The previous unloading in Vietnam, they choose option2 but using 2 cranes 25T
As I checked the area at supply building3, I think we should go with option2 to have one empty
trailer that we can unloading in convenience area and move to supply building3 due to the actual
area in supply building3 is quite poor condition at the moment.