You are on page 1of 2

April 17, 2017

Attention : Arch. Giselle V. Eala

Project : MIASCOR – Substation

Subject : Proposal for Substation Inspection, As-Built Drawings,


Design and Consultation

-----------------------------------------------------------------------------------------------------------
Dear Ma’am,:

I am pleased to submit my proposal to provide the Consultation, Inspection and As-built


Drawing

A. SCOPE OF WORK

1. To Conduct inspection of actual site condition.


2. To Trace and Tag existing Substation System
3. To Provide As-built plan
4. To Provide New Substation Design duly signed and Sealed

B. CONTRACT PRICE

The total contract price is


ONE HUNDRED TWENTY THOUSAND PESOS ONLY, (Php. 120,000.00)

Actual Site Works


Site As-built (7days)
3-Electrician PhP. 16,000.00
1-Electrical Engineer PhP. 14,000.00
Miscellaneous PhP. 20,000.00
As-built Plan duly Sign and Sealed PhP. 15,000.00
PhP. 65,000.00

Design and Upgrade


Design and Consultation (New Design) PhP. 30,000.00
Site Visit and Coordination PhP. 10,000.00
Sign and Sealed (New Design) Php. 15,000.00

Php. 55,000.00
C. CONTRACT SCHEDULE

As-built Plans will be ready 3days after actual plotting of data at site

D. TERMS OF PAYMENT

50% Down Payment


50% Full Payment upon submission of plans

E. OTHER CONDITIONS

1. Plotting and Blueprint not included on this Proposal.


2. Installation and implementation not included on this proposal
3. All Coordination shall be via Principal Architect.

Very truly yours,

Engr. Gemmar E. Bon

You might also like