No Task Name Start Finish Duration


Nov Des Jan Feb Mar Apr Mei Jun
1 Kick Off 11/11/2020 11/12/2020 1
2 Collect as is data 11/11/2020 1/11/2021 60
3 Design to be 1/11/2021 2/11/2021 30
4 Master Data 2/11/2021 2/13/2021 2
5 Budgeting 2/13/2021 2/15/2021 2
6 Unit testing 2/15/2021 3/15/2021 30
7 Integration testing 3/15/2021 4/15/2021 30
8 Expert user training 4/15/2021 4/18/2021 3
9 Master Data 4/18/2021 4/20/2021 2
10 Transction Data 4/20/2021 4/22/2021 2
11 Form and reporting 4/22/2022 4/25/2021 2
12 Trial implementation 4/25/2021 5/25/2021 30
13 End user training 5/25/2021 6/8/2021 14
14 Master Data 6/8/2021 6/10/2021 2
15 Transction Data 6/10/2021 6/12/2021 2
16 Form and reporting 6/12/2021 6/14/2021 2
17 conversion 6/14/2021 6/19/2021 5
18 Go live 6/19/2021 7/19/2021 30
19 Change management 30
20 Closing 2