You are on page 1of 2

Subject : Construction Schedule (bar chart,s-curve, manpower & equipment schedule)

Duration
: 120 days
(day)

Item Rel.Wt No. of


DURATION (Days)
ACTIVITIES QTY TOTAL AMOUNT Day(s)
No (%)

100

101

102

103

104

105

106

107

108

109

110

111

112

113

114

115

116

117

118

119

120
10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

36

37

38

39

40

41

42

43

44

45

46

47

48

49

50

51

52

53

54

55

56

57

58

59

60

61

62

63

64

65

66

67

68

69

70

71

72

73

74

75

76

77

78

79

80

81

82

83

84

85

86

87

88

89

90

91

92

93

94

95

96

97

98

99
1

9
A BUILDING 1
1.1 Layout & Excavation 10.15 cu.m. $ 226.60 0.07% 3 1 1 1

2.1 Footing 0.27 cu.m. $ 49.65 0.02% 4 1 1 1 1

2.2 Wall Footing 16.59 cu.m. $ 4,595.73 1.44% 6 1 1 1 1 1 1

2.3 Column (Outer) 0.37 cu.m. $ 622.06 0.19% 4 1 1 1 1

2.4 Columns 2.48 cu.m. $ 6,094.74 1.91% 11 1 1 1 1 1 1 1 1 1 1 1

2.5 Roof Beams 2.76 cu.m. $ 2,942.35 0.92% 19 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

2.6 Slab 100.52 cu.m. $ 14,922.64 4.68% 10 1 1 1 1 1 1 1 1 1 1

2.7 Lintels 0.54 cu.m. $ 379.91 0.12% 6 1 1 1 1 1 1

2.8 Walls 260.37 sq.m. $ 6,724.71 2.11% 20 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Installation of Trusses (2" x 6"), Purlins (2" x 4") and accessories. Use treated
3.1 220.15 sq.m. $ 3,298.67 1.03% 17 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
lumbers
3.2 Installation of Treated Wooden Fascia (1" x 6") 67.36 m. $ 112.06 0.04% 3 1 1 1

Installation of Pre-painted Roof Sheets (Ga. 26), pre-fabricated gutter, pre-painted


4.1 251.71 sq.m. $ 6,057.43 1.90% 8 1 1 1 1 1 1 1 1
(Ga. 26), pre-fabricated ridge cap, pre-painted (Ga. 26)
Installation of new ceiling (Exterior) on 2" x 2" treated wooden joists spaced at 0.6m
5.1 76.47 sq.m. $ 999.49 0.31% 8 1 1 1 1 1 1 1 1
on center both ways.Use Plywood, Reg Grade, ¼" ACX
Installation of new ceiling (Interior) on 2" x 2" treated wooden joists spaced at 0.6m
5.2 136.69 sq.m. $ 1,143.19 0.36% 13 1 1 1 1 1 1 1 1 1 1 1 1 1
on center both ways. Use Plywood, Reg Grade, ¼" ACX

5.3 0.40m x 0.90m Ceiling Vents (Use 1" x 2" treated lumber and provide Insect Screen ) 8.00 Nos. $ 354.55 0.11% 3 1 1 1

6.1 Prefab Door, Complete with Handle and Lock 6.00 Nos. $ 1,619.31 0.51% 2 1 1

6.2 Aluminum Sliding Window, 24" X 36", Complete with Glass 12.00 Nos. $ 968.11 0.30% 2 1 1

7.1 Masonry Surfaces Painting 530.17 sq.m. $ 1,210.14 0.38% 7 1 1 1 1 1 1 1

7.2 Wooden Surfaces Painting 213.15 sq.m. $ 875.89 0.27% 9 1 1 1 1 1 1 1 1 1

B BUILDING 2
1.1 Layout & Excavation 10.15 cu.m. $ 226.60 0.07% 3 1 1 1

2.1 Footing 0.27 cu.m. $ 49.65 0.02% 4 1 1 1 1

2.2 Wall Footing 16.59 cu.m. $ 4,595.73 1.44% 6 1 1 1 1 1 1

2.3 Column (Outer) 0.37 cu.m. $ 622.06 0.19% 4 1 1 1 1

2.4 Columns 2.48 cu.m. $ 6,094.74 1.91% 11 1 1 1 1 1 1 1 1 1 1 1

2.5 Roof Beams 2.76 cu.m. $ 2,942.35 0.92% 19 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

2.6 Slab 100.52 cu.m. $ 14,922.64 4.68% 10 1 1 1 1 1 1 1 1 1 1

2.7 Lintels 0.54 cu.m. $ 379.91 0.12% 6 1 1 1 1 1 1

2.8 Walls 260.37 sq.m. $ 6,724.71 2.11% 20 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Installation of Trusses (2" x 6"), Purlins (2" x 4") and accessories. Use treated
3.1 220.15 sq.m. $ 3,298.67 1.03% 17 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
lumbers
3.2 Installation of Treated Wooden Fascia (1" x 6") 67.36 m. $ 112.06 0.04% 3 1 1 1

Installation of Pre-painted Roof Sheets (Ga. 26), pre-fabricated gutter, pre-painted


4.1 251.71 sq.m. $ 6,057.43 1.90% 8 1 1 1 1 1 1 1 1
(Ga. 26), pre-fabricated ridge cap, pre-painted (Ga. 26)
Installation of new ceiling (Exterior) on 2" x 2" treated wooden joists spaced at 0.6m
5.1 76.47 sq.m. $ 999.49 0.31% 8 1 1 1 1 1 1 1 1
on center both ways.Use Plywood, Reg Grade, ¼" ACX
Installation of new ceiling (Interior) on 2" x 2" treated wooden joists spaced at 0.6m
5.2 136.69 sq.m. $ 1,143.19 0.36% 13 1 1 1 1 1 1 1 1 1 1 1 1 1
on center both ways. Use Plywood, Reg Grade, ¼" ACX

5.3 0.40m x 0.90m Ceiling Vents (Use 1" x 2" treated lumber and provide Insect Screen ) 8.00 Nos. $ 354.55 0.11% 3 1 1 1

6.1 Prefab Door, Complete with Handle and Lock 6.00 Nos. $ 1,619.31 0.51% 2 1 1

6.2 Aluminum Sliding Window, 24" X 36", Complete with Glass 12.00 Nos. $ 968.11 0.30% 2 1 1

7.1 Masonry Surfaces Painting 530.17 sq.m. $ 1,210.14 0.38% 7 1 1 1 1 1 1 1

7.2 Wooden Surfaces Painting 213.15 sq.m. $ 875.89 0.27% 9 1 1 1 1 1 1 1 1 1

C BUILDING 3
1.1 Layout & Excavation 10.15 cu.m. $ 226.60 0.07% 3 1 1 1

2.1 Footing 0.27 cu.m. $ 49.65 0.02% 4 1 1 1 1

2.2 Wall Footing 16.59 cu.m. $ 4,595.73 1.44% 6 1 1 1 1 1 1

2.3 Column (Outer) 0.37 cu.m. $ 622.06 0.19% 4 1 1 1 1

2.4 Columns 2.48 cu.m. $ 6,094.74 1.91% 11 1 1 1 1 1 1 1 1 1 1 1

2.5 Roof Beams 2.76 cu.m. $ 2,942.35 0.92% 19 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

2.6 Slab 100.52 cu.m. $ 14,922.64 4.68% 10 1 1 1 1 1 1 1 1 1 1

2.7 Lintels 0.54 cu.m. $ 379.91 0.12% 6 1 1 1 1 1 1

2.8 Walls 260.37 sq.m. $ 6,724.71 2.11% 20 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Installation of Trusses (2" x 6"), Purlins (2" x 4") and accessories. Use treated
3.1 220.15 sq.m. $ 3,298.67 1.03% 17 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
lumbers
3.2 Installation of Treated Wooden Fascia (1" x 6") 67.36 m. $ 112.06 0.04% 3 1 1 1

Installation of Pre-painted Roof Sheets (Ga. 26), pre-fabricated gutter, pre-painted


4.1 251.71 sq.m. $ 6,057.43 1.90% 8 1 1 1 1 1 1 1 1
(Ga. 26), pre-fabricated ridge cap, pre-painted (Ga. 26)
Installation of new ceiling (Exterior) on 2" x 2" treated wooden joists spaced at 0.6m
5.1 76.47 sq.m. $ 999.49 0.31% 8 1 1 1 1 1 1 1 1
on center both ways.Use Plywood, Reg Grade, ¼" ACX
Installation of new ceiling (Interior) on 2" x 2" treated wooden joists spaced at 0.6m
5.2 136.69 sq.m. $ 1,143.19 0.36% 13 1 1 1 1 1 1 1 1 1 1 1 1 1
on center both ways. Use Plywood, Reg Grade, ¼" ACX

5.3 0.40m x 0.90m Ceiling Vents (Use 1" x 2" treated lumber and provide Insect Screen ) 8.00 Nos. $ 354.55 0.11% 3 1 1 1

6.1 Prefab Door, Complete with Handle and Lock 6.00 Nos. $ 1,619.31 0.51% 2 1 1

6.2 Aluminum Sliding Window, 24" X 36", Complete with Glass 12.00 Nos. $ 968.11 0.30% 2 1 1

7.1 Masonry Surfaces Painting 530.17 sq.m. $ 1,210.14 0.38% 7 1 1 1 1 1 1 1

7.2 Wooden Surfaces Painting 213.15 sq.m. $ 875.89 0.27% 9 1 1 1 1 1 1 1 1 1

D BUILDING 4
1.1 Layout & Excavation 10.15 cu.m. $ 226.60 0.07% 3 1 1 1

2.1 Footing 0.27 cu.m. $ 49.65 0.02% 4 1 1 1 1

2.2 Wall Footing 16.59 cu.m. $ 4,595.73 1.44% 6 1 1 1 1 1 1

2.3 Column (Outer) 0.37 cu.m. $ 622.06 0.19% 4 1 1 1 1

2.4 Columns 2.48 cu.m. $ 6,094.74 1.91% 11 1 1 1 1 1 1 1 1 1 1 1

2.5 Roof Beams 2.76 cu.m. $ 2,942.35 0.92% 19 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

2.6 Slab 100.52 cu.m. $ 14,922.64 4.68% 10 1 1 1 1 1 1 1 1 1 1

2.7 Lintels 0.54 cu.m. $ 379.91 0.12% 6 1 1 1 1 1 1

2.8 Walls 260.37 sq.m. $ 6,724.71 2.11% 20 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Installation of Trusses (2" x 6"), Purlins (2" x 4") and accessories. Use treated
3.1 220.15 sq.m. $ 3,298.67 1.03% 17 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
lumbers
3.2 Installation of Treated Wooden Fascia (1" x 6") 67.36 m. $ 112.06 0.04% 3 1 1 1

Installation of Pre-painted Roof Sheets (Ga. 26), pre-fabricated gutter, pre-painted


4.1 251.71 sq.m. $ 6,057.43 1.90% 8 1 1 1 1 1 1 1 1
(Ga. 26), pre-fabricated ridge cap, pre-painted (Ga. 26)
Installation of new ceiling (Exterior) on 2" x 2" treated wooden joists spaced at 0.6m
5.1 76.47 sq.m. $ 999.49 0.31% 8 1 1 1 1 1 1 1 1
on center both ways.Use Plywood, Reg Grade, ¼" ACX
Installation of new ceiling (Interior) on 2" x 2" treated wooden joists spaced at 0.6m
5.2 136.69 sq.m. $ 1,143.19 0.36% 13 1 1 1 1 1 1 1 1 1 1 1 1 1
on center both ways. Use Plywood, Reg Grade, ¼" ACX

5.3 0.40m x 0.90m Ceiling Vents (Use 1" x 2" treated lumber and provide Insect Screen ) 8.00 Nos. $ 354.55 0.11% 3 1 1 1

6.1 Prefab Door, Complete with Handle and Lock 6.00 Nos. $ 1,619.31 0.51% 2 1 1

6.2 Aluminum Sliding Window, 24" X 36", Complete with Glass 12.00 Nos. $ 968.11 0.30% 2 1 1

7.1 Masonry Surfaces Painting 530.17 sq.m. $ 1,210.14 0.38% 7 1 1 1 1 1 1 1

7.2 Wooden Surfaces Painting 213.15 sq.m. $ 875.89 0.27% 9 1 1 1 1 1 1 1 1 1

E BUILDING 5
1.1 Layout & Excavation 10.15 cu.m. $ 226.60 0.07% 3 1 1 1

2.1 Footing 0.27 cu.m. $ 49.65 0.02% 4 1 1 1 1

2.2 Wall Footing 16.59 cu.m. $ 4,595.73 1.44% 6 1 1 1 1 1 1

2.3 Column (Outer) 0.37 cu.m. $ 622.06 0.19% 4 1 1 1 1

2.4 Columns 2.48 cu.m. $ 6,094.74 1.91% 11 1 1 1 1 1 1 1 1 1 1 1


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120

0.02%

0.02%

0.03%

0.03%

0.27%

0.27%

0.27%

0.73%

0.73%

0.71%

0.93%

0.88%

0.88%

0.86%

0.86%

0.86%

0.62%

0.62%

0.44%

0.44%

0.49%

0.32%

0.32%

0.32%

0.15%

0.15%

0.21%

0.21%

0.31%

0.84%

0.84%

0.95%

1.47%

1.43%

1.53%

2.00%

1.95%

1.97%

1.97%

1.45%

1.47%

1.47%

1.01%

1.19%

1.19%

0.73%

0.88%

0.88%

0.83%

0.99%

0.99%

0.67%

0.90%

1.40%

1.09%

1.18%

1.68%

1.45%

1.27%

1.72%

1.69%

1.20%

1.20%

1.17%

0.83%

0.83%

0.57%

0.51%

0.55%

0.35%

0.35%

0.35%

0.15%

0.15%

0.21%

0.21%

0.31%

0.84%

0.84%

0.95%

1.47%

1.43%

1.53%

2.00%

1.95%

1.97%

1.97%

1.45%

1.47%

1.47%

1.01%

1.19%

1.19%

0.73%

0.88%

0.88%

0.81%

0.96%

0.96%

0.65%

0.63%

1.13%

0.82%

0.45%

0.95%

0.74%

0.34%

0.84%

0.81%

0.34%

0.34%

0.32%

0.21%

0.21%

0.13%

0.06%

0.06%

0.03%

0.03%

100.00% 0.03%
Relative % of Accomplishment

10.02%

10.46%

10.95%

11.27%

11.59%

11.91%

12.06%

12.20%

12.41%

12.61%

12.93%

13.77%

14.61%

15.55%

17.03%

18.45%

19.98%

21.98%

23.93%

25.90%

27.87%

29.32%

30.79%

32.27%

33.27%

34.47%

35.66%

36.39%

37.27%

38.15%

38.98%

39.97%

40.96%

41.63%

42.53%

43.94%

45.02%

46.20%

47.89%

49.33%

50.60%

52.31%

54.00%

55.20%

56.40%

57.57%

58.40%

59.23%

59.80%

60.31%

60.86%

61.21%

61.56%

61.91%

62.06%

62.20%

62.41%

62.62%

62.93%

63.77%

64.61%

65.55%

67.03%

68.45%

69.98%

71.98%

73.93%

75.90%

77.87%

79.32%

80.79%

82.27%

83.27%

84.47%

85.66%

86.39%

87.27%

88.15%

88.96%

89.92%

90.88%

91.53%

92.16%

93.30%

94.11%

94.56%

95.51%

96.26%

96.59%

97.43%

98.24%

98.58%

98.92%

99.23%

99.45%

99.66%

99.79%

99.85%

99.91%

99.94%

99.97%
0.02%

0.05%

0.07%

0.10%

0.37%

0.64%

0.91%

1.64%

2.37%

3.08%

4.01%

4.89%

5.76%

6.62%

7.48%

8.34%

8.95%

9.57%
Commulative % of Accomplishment 0%

100

101

102

103

104

105

106

107

108

109

110

111

112

113

114

115

116

117

118

119

120
10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

36

37

38

39

40

41

42

43

44

45

46

47

48

49

50

51

52

53

54

55

56

57

58

59

60

61

62

63

64

65

66

67

68

69

70

71

72

73

74

75

76

77

78

79

80

81

82

83

84

85

86

87

88

89

90

91

92

93

94

95

96

97

98

99
MANPOWER SCHEDULE

9
1 Construction Manager/Project Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 Site Engineer/Inspector 1 1 1 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
3 Foreman 1 1 1 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
4 Leadman Steel Fixer 1 1 1 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 2 1 1 1
5 Leadman Carpenter 2 2 2 4 4 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 8 8 10 8 10 10 12 12 12 12 12 12 12 10 10 10 8 8 8 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4 4 2 2 2
6 Leadman Mason 2 2 2 4 4 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4 4 4 4 4 4 4 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4 4 2 2 2
7 Skilled Workers (Steel Fixer) 2 2 2 4 4 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4 4 2 2 2 2 2 4 2 4 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4 4 2 2 2
8 Skilled Workers (Carpenter) 5 5 5 10 10 10 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 20 20 25 20 25 25 30 30 30 30 30 30 30 25 25 25 20 20 20 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 10 10 10 5 5 5
9 Skilled Workers (Mason) 5 5 5 10 10 10 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 10 10 10 10 10 10 10 10 10 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 10 10 10 5 5 5
10 Skilled Workers (Painter) 3 3 3 6 9 9 12 12 12 12 12 12 12 6 6 6 3 3 3 3 3 3 6 9 9 12 12 12 12 12 12 12 6 6 6 3 3 3
11 Unskilled Workers 13 13 18 41 41 46 69 69 74 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 74 74 74 64 64 74 64 69 89 89 98 118 118 127 141 141 145 145 145 145 145 145 145 122 122 122 103 103 103 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 84 74 74 74 64 64 61 51 51 48 48 52 49 49 53 57 57 61 61 61 61 61 61 61 38 38 38 19 19 19
TOTAL MANPOWER = 26 26 31 73 73 78 120 120 125 142 142 142 142 142 142 142 142 142 142 142 142 142 142 142 142 142 142 142 142 142 142 142 142 142 142 142 140 140 140 138 138 138 136 126 126 125 115 115 127 117 122 151 151 163 193 193 205 229 229 236 236 229 229 229 222 222 193 186 186 164 164 164 142 142 142 142 142 142 142 142 142 142 142 142 140 140 140 138 138 138 136 126 126 125 115 115 104 94 94 83 83 90 80 80 87 94 94 101 101 94 94 94 87 87 58 51 51 29 29 29

100

101

102

103

104

105

106

107

108

109

110

111

112

113

114

115

116

117

118

119

120
10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

36

37

38

39

40

41

42

43

44

45

46

47

48

49

50

51

52

53

54

55

56

57

58

59

60

61

62

63

64

65

66

67

68

69

70

71

72

73

74

75

76

77

78

79

80

81

82

83

84

85

86

87

88

89

90

91

92

93

94

95

96

97

98

99
EQUIPMENT SCHEDULE

9
1 Mini Excavator/Backhoe 1 1 1 1 1 1 1 1 1 1 1 1 2 1 1 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 1 1 2 1 1 1
2 Pick-up Truck 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
3 Compactor 1 1 1 2 2 2 3 3 2 2 2 1 1 1 1 1 1 2 2 2 2 2 2 1 1 1 1 1 1 2 2 2 3 3 2 2 2 1 1 1 1 1 1 2 2 2 2 2 2 1 1 1
4 Concrete Mixer 2 2 2 4 4 4 6 6 6 6 6 6 6 6 6 4 4 4 2 2 4 2 2 4 4 4 6 6 6 6 6 6 6 6 6 4 4 4 2 2 2 2 2 2 4 4 4 4 4 6 6 6 6 6 6 6 4 4 4 2 2 4 4 4 4 4 4 4 4 6 6 6 6 6 6 6 4 4 4 2 2 2 2 2
5 Concrete Vibrator 2 2 2 4 4 4 6 6 6 6 6 6 6 6 6 4 4 4 2 2 4 2 2 4 4 4 6 6 6 6 6 6 6 6 6 4 4 4 2 2 2 2 2 2 4 4 4 6 6 6 6 6 6 6 6 6 4 4 4 2 2 4 2 2 4 4 4 6 6 6 6 6 6 6 6 6 4 4 4 2 2 2
6 Power Generator (Portable) 3 3 3 6 6 6 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 12 12 12 15 15 15 18 18 18 18 18 18 18 18 18 18 18 18 15 15 15 12 12 12 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 6 6 6 3 3 3

7 Power Tools (Chopsaw, Circular Saw, Drill, Angle Grinder, Heavy duty extension wire with outlet & Power Outlet) lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot

Misc. Hand Tools (Hammer, Saw, Measuring Tape, Carpenter Square, Level Hose, Level Bar, Bar Cutter,10mm Rebar Bender w/ pipe,
8 Concrete Trowel, Shovel, Crow Bar, Hack Saw, Aluminum Telescopic Stairs/foldable ladder, Layout String, Pick Axe, Plumb Bob, Riveter, lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot
Snipping tools/tin snips,Wheel Borrow & Water Tank)

You might also like