Professional Documents
Culture Documents
New Completion Solution for Multi Layer Gas Fields: A Case History
M.A. Arianto, SPE, Y. Susatyo, SPE, B. Srisantoso, SPE, and Sumaryanto, SPE, VICO Indonesia
the surface was recommended. This type of completion reservoir target with the first well (well X) reaching total
resulted in drilling and completion cost savings of around depth (TD) at 10,571’ TVD (targeted on the deep reservoir)
$200,000 per well down to the deepest zone at 14,000 ft. It and the second well (well Y) at 6,311’ TVD (targeted on the
was mechanically simpler because there was no completion shallow reservoir). The Nilam well (well Z) was drilled
jewellery required. Perforation could be done without slightly directionally, with the kick off point at 8,500 ft and
requiring a rig and it was quicker to add and isolate zones. If maximum angle 15.63 degrees. The well was drilled to TD at
additional deliverability was required, more zones could be 13,668 ft
perforated to provide extra gas rate.
Initially for deeper low permeability sands VICO adopted a Well Drilling & Completion
modular gun system for safe underbalanced perforation. The wells were drilled early in 2005, and electrical logging
Subsequent zones would be perforated using e-line with and sampling was performed for well evaluation.
limited underbalance. Well X (FIG.3) experienced wellbore stability problems
The 4-1/2” monobore delivered a similar rate to that of which resulted in a drill string being left in the hole and an
two strings of 3-1/2” tubing. However in the lower abandoned lower section. The well was completed as a dual 3-
permeability and/or depleted reservoirs, this 4-1/2” monobore 1/2” monobore cemented inside 9-5/8” casing.
was susceptible to liquid loading problems thus reducing Well Y (FIG.4) and well Z were completed as a dual 3-
reserves recovery. Adding new perforation zones helped to 1/2” monobores cemented in open hole.
solve this loading problem but later on some wells were In all cases dual pipe - surface handling equipment was
shown to suffer from cross flow. The problem became more required to allow pipe reciprocation during the cementing job.
complicated if one of the commingled zones produced water
early and killed the other open zones. Centralizer & Cement Bond
In 2003, a combination of monobore on the bottom and A Dual string centralizer was installed in both open hole
packer type completion on top was introduced, called and cased hole applications as a stand-off mechanism between
‘monobore hybrid completion’. Even though this completion the two strings (FIG.5). This was required to enable both
helped in optimizing reserves recovery from the marginal strings to be run into the hole simultaneously instead of
zones at the bottom of the well and reduced the cost compared individually as was the previous VICO practice. Additional
to conventional completions, the risk of leaks and surface equipment on the rig, such as dual ram BOP, dual pipe
communication due to the sealing mechanism still remained. handling tools was also required. The cementing process was
carried out by pumping cement thru the Long String. A
Proposed Completion through tubing cement bond evaluation was run on the Long
A new completion type was required that met the String for both Well Y and Z to evaluate cement bonding. In
following requirements: it should be packerless to reduce the the deeper single monobore section, the log indicated excellent
cost and complexity of rig operation; it should allow flexibility bonding on both tubing to cement and cement to formation
on production strategy within a multilayer gas reservoir; it with average amplitude of less than 5mV. In the dual
should allow individual zones to be added or isolated; and it monobore section, good bond was also recorded, despite
should be of a smaller tubing size to avoid liquid load-up concern about how the tool would respond in this type of
problems. completion.
The solution that was developed is referred to as a “Dual
Monobore” completion. This followed the monobore concept Wellhead
but used dual 3-1/2” tubing cemented from TD to surface. This Dual Monobore completion required a different set up
Some risks in implementing this experimental completion for the wellhead compared to previous VICO completions
were: (FIG.6). A dual slip mechanism complete with pack-off was
- it had never been applied in VICO Indonesia set in the tubing head since both strings were run
- a stand-off mechanism between two strings to simultaneously instead of the tubing hanger system that was
overcome the cement isolation issue was required. required previously on dual conventional completions. A tree
- running dual strings simultaneously and dual string adapter was also required to accommodate the need for back
cementing practices were seen as challenging pressure valves. The rating of the tree was to the same VICO
- gun orientation could be an issue standard as that in previous dual completion systems.
measured when the tool faced the adjacent casing (in the
opposite direction to the other tubing string). This was because Nomenclature
the casing has more steel when compared to the tubing. The TCP: Tubing Convey Perforation
perforating gun phasing was configured to shoot in the POT: Perforation Orienting Tool
opposite direction to the magnetic sensor which aligned with BOP: Blow Out Preventer
the MINIMUM flux. In the open hole condition, the results mD: milli Darcy (permeability)
were the opposite, and perforation was in the direction BHP: Bottom Hole Pressure
opposite to the MAXIMUM flux (FIG.7). ID: Inner Diameter
TD: TotalDepth
Results TVD: True Vertical Depth
All wells were completed as Dual 3-1/2” Monobores
successfully without experiencing any operational issues.
Cement bond logs were run after and confirmed good cement
bond quality on both single and dual monobore sections. The References
POT was used to orient the guns according to the 1. Ismanto, B., Mike Hass, John Dyer: “New Well Architecture
recommendations of the surface simulations, and this resulted Successfully Optimizes the development of fluvio-deltaic
in perforation being carried out without impacting the adjacent Multi-layered Gas Field” paper SPE 64394
string. 2. Gunawan, R., and Dyer, G.R:”Tubing Size Optimization in Gas
Depletion Drive Reservoirs”, paper SPE 37001 presented in
The change of completion design from either dual 1996 SPE Asia Pacific Oil and Gas Conference, Adelaide,
conventional or 4-1/2” monobore to dual 3-1/2” monobore in October 28-31.
VICO does not impact the drilling of the well significantly 3. Brown, K. E., and Lea. F.:”Nodal System Analysis of Oil and
since the hole size does not change. It also allows the Gas Wells”, JPT (Oct.1985) 1751.
flexibility to change the completion to a single monobore 4. Ikoku, Chi U., Natural Gas Reservoir Engineering, John Willey &
completion if required based on the electric logging evaluation Sons (1984) 141.
results if required.
The 3-1/2” completion additionally favours the current
mature field conditions since critical flow rate is important to
overcome the liquid loading issue.
This completion design has allowed us to optimize the
policy of bottoms-up perforation in both the deep tighter sands
in the long string and the shallower more prolific water drive
sands perforated in the short string.
Cost Effective
In term of drilling and completion cost, this completion is
more economic compared with dual conventional packer type
completions since the total rig-time is reduced by 5 to 7 days.
Rig-time is similar to that of a 4-1/2” monobore completion
well, but the economics are more attractive since it is possible
to produce from both strings simultaneously.
Conclusions
1. The 3-1/2” Dual Monobore completion has been
demonstrated to be a feasible alternative for future VICO
completions in multilayer reservoirs.
2. It is economically more attractive than dual conventional
selective completion types and 4-1/2 monobores.
3. It allows the flexibility of producing from two different
strings simultaneously, reducing any requirement to
commingle production from different zones.
4. Reserves recovery is improved by allowing production to a
lower critical rate when compared with 4-1/2”
monobores.
Acknowledgements
The author would like to thank the management of VICO
Indonesia and BP Migas to publish this paper. We also would
like to thanks to Ronald Gunawan, Bill Turnbull, Robert
Nikijuluw, Roberto De Mitri (Asset Team) and Drilling
Department for support and discussion.
4 SPE 100991
TOC ~ 1,800'
9-5/8" 2,315'
FIG.6. Wellhead
GUN
GUN
Direction
Direction
2 x 3.5 in the
2 x 3.5 inside
open hole
Min 9-5/8 casing Max