Q8. Provide the cost estimation of your project using COCOMO Model.

For the purpose,

1. Select the category of your project out of three defined categories (organic, semidetached
and embedded) for the values of coefficients and constants.
2. Select at least two modules of the project for estimation.

Lines of code = 1600

KLOC lines of code (in the thousands) = 1.6

Category: ORGANIC

Modules selected: Admin, Customer

b
Effort = a*(KLOC) , in person/months

d
Duration = c*(Effort) , in months

Staffing = Effort/Duration

Effort Duration
Mode a b c d KLOC Staffing
(person/months) (months)

Organic 2.4 1.05 2.5 0.38 1.6 3.93 4.26 0.93 ≈ 1