Professional Documents
Culture Documents
Vdocuments - MX - Brazil CSP Ball Tank Erection Manual
Vdocuments - MX - Brazil CSP Ball Tank Erection Manual
CONTENTS
1. GENERAL
2. RELATED DOCUMENTS
3. OVERALL SEQUENCE
4. FOUNDATION
5. ASSEMBLING OF TANK
6. WELDING SEQUENCE
7. INSPECTION
http://slidepdf.com/reader/full/brazil-csp-ball-tank-erection-manual 1/18
8/20/2019 Brazil CSP-Ball Tank Erection Manual
1. GENERAL
1.1 This procedure is applied to the field erection of the spherical tank for the following
articles.
1.2 Supplied for: RCC Off Gas to Propylene Project UP-VI Balonqan of PT. PERTAMINA
(PERSERO)
1.3 Items to be supplied
2. RELATED DOCUMENTS
http://slidepdf.com/reader/full/brazil-csp-ball-tank-erection-manual 2/18
8/20/2019 Brazil CSP-Ball Tank Erection Manual
3. OVERALL SEQUENCE
The plannedwith
accordance sequence of construction
the construction and and
schedule completion involves
approved the erection of spheres in
drawings.
Deliveries of materials are scheduled to satisfy the erection sequence, mobilization of facilities &
equipment and mobilization of manpower.
http://slidepdf.com/reader/full/brazil-csp-ball-tank-erection-manual 3/18
8/20/2019 Brazil CSP-Ball Tank Erection Manual
http://slidepdf.com/reader/full/brazil-csp-ball-tank-erection-manual 4/18
8/20/2019 Brazil CSP-Ball Tank Erection Manual
4. FOUNDATION
The foundation shall be checked using an accurate instrument set on center of grade.
4.1 The following dimension typically marked A, B, C, D, E, F1 ~ Fn, and H as shown in Fig-1
shall be checked and adjusted as necessary prior to commencement of field erection.
4.2 Tank center point s hall be established on the ta nk foundation. The orientation of tank
foundation shall be subjected to the approved construction drawing.
0
F1
F2
F3
F4
270
D E 90
F5
C H
A B
G.L
180
4.3 Inspection
Before acceptance of foundation, inspection shall be made for the following items with
presence of Vendor/Subcontractor, Contractor's inspector. All dimensions shall be
checked against approved drawings and ensure that the standard tolerances are met. All
records shall be reported and reviewed by Contractor.
(1) On the foundation for supports, pipelines, and stairs, padding shall be made after
measuring
acceptance.the
Thelevel of foundation
foundation surfacessurface
shall bewith the presence
roughened, before of QC inspector
padding for
installation.
(2) Padding for support foundation shall be formed in such a way as shown in Fig-2 so as to
meet the tolerances.
(3) Grouting using non-shrinkage mortar between the foundation surface and base plate
http://slidepdf.com/reader/full/brazil-csp-ball-tank-erection-manual 5/18
8/20/2019 Brazil CSP-Ball Tank Erection Manual
shall be completed after PWHT and before the pressure test of tank.
(4) The difference in pad levels shall be within 2.0 mm.
SCALE
LEVEL
SCALE
ANCHOR BOLT
LINER PLATE
TANK
CENTER
LINE
PAD
4.5 Allowable tolerance of each dimension shall be in accordance with the specific Inspection
and Test Procedure with Plan at Field.
http://slidepdf.com/reader/full/brazil-csp-ball-tank-erection-manual 6/18
8/20/2019 Brazil CSP-Ball Tank Erection Manual
5. ASSEMBLING OF TANK
&
%
'
(
!
)
#
$
* "
*
Lower column
! Equator plate with upper column and equator without column
" Bracing (Note 2)
# Lower ring plate
$ Bottom crown plate and pole plate
% Upper ring plate
& Top crown plate and pole plate (Note 1)
' Stairway & platforms
( Internal pipes & ladder
) Water spray system
* Accessories (nameplate, earth lugs, etc.)
+ Others
Note:
(1) For ventilation of inside welding fume and heat, one of crown plate may
open until completion of production welding of all shell joints, and then the
plate will be installed and welded to the final weld joint.
(2) When PWHT is required for assembled tank, the column-bracing pipe
shall be welded after PWHT.
The plumb of each column shall be checked as shown in Fig-4 and adjusted after
assembling of equator plates in the presence of QC inspector for acceptance
Plumb
Check Points
0
0 A
2
Reference Mark
String with For Levelness Check
Plumb-Bob
B
0
0 0
0 5
4
G.L
(2) Allowable tolerances of plumb and levelness of each column shall be in accordance with
the Inspection & Test Procedure with Plan at Field.
1) After erection of each lower column, the top of lower column shall be level
within ! 3 mm in any one.
2) After erection of lower column and stress relieving the tank, the verticality of
each lower column shall not exceed 1/500 of the total length.
Before and during the Post Weld Heat Treatment (PWHT), following shall
be kept carefully.
- To provide sliding between base plates and sliding plate during PWHT,
grease shall be applied on the sliding plate before erection of lower column.
16
14 3
15 2
12 5
90
270 13 4
10 7
1 6
8 9
180
Wire Rope
Turn Buckle
Equator Plate
http://slidepdf.com/reader/full/brazil-csp-ball-tank-erection-manual 9/18
8/20/2019 Brazil CSP-Ball Tank Erection Manual
1) As shown in Fig-7, assemble each equator plate successively, and make surface aligned
tack welding shall be performed by qualified welder.
Wire Rope
G.L
2) The difference between maximum and minimum diameter "D" given as Fig-8 shall not
exceed 0.3% specified diameter in the approved construction drawing
D D"
G.L
http://slidepdf.com/reader/full/brazil-csp-ball-tank-erection-manual 10/18
8/20/2019 Brazil CSP-Ball Tank Erection Manual
BALL PIN
KEY PLATE
KEY NUT
500mm
EQUATOR PLATE
500mm
(4) In fitting the plate, put the scaffold blanks, key-plates, etc., on the ground as shown in
Fig-11, when possible, and lift them together with plates.
Hand Rail
Scaffold Plate
Bracket
5.4 The lower ring or bottom crowns as shown in Fig-12 are supported by temporary jigs (key-
plate, key-nut, etc as per Fig-9) with tack welding during erection and the inclination in
adjusted with them.
Lower Ring
http://slidepdf.com/reader/full/brazil-csp-ball-tank-erection-manual 12/18
8/20/2019 Brazil CSP-Ball Tank Erection Manual
CURVATURE GAUGE
" !
JACK
The upper ring or top crown as shown in Fig-14 are supported by temporary jigs (key-plate,
key-nut, etc as per Fig-9) with tack welding during erection and the inclination in adjusted
with them.
Upper Ring
http://slidepdf.com/reader/full/brazil-csp-ball-tank-erection-manual 13/18
8/20/2019 Brazil CSP-Ball Tank Erection Manual
(1) The top crown is erected after the roundness adjustment of the upper ring opening.
(2) The erection procedure is similar to the bottom crown.
(3) Mount the members after assembling the internal scaffold.
INSPECTION SCAFFOLD
INSIDE SCAFFOLD
BRACKETS
INSIDE OUTSIDE
http://slidepdf.com/reader/full/brazil-csp-ball-tank-erection-manual 14/18
8/20/2019 Brazil CSP-Ball Tank Erection Manual
(2) A plate joint is adjusted plainly with suitable device (plain-dog) if it is uneven.
The
(withplain-dog
regardlessshall be Numbers).
Group the same P-Number material as the base metal of the tank
Qualified welder shall perform the attachment of plain-dog to base metal,
which is to adjusted alignment.
Not allowed to remove the plain-dog with hammering and the reminder on the
plates shall be applied non-destructive examination.
Wedge
Plain dog
Wedge Plain dog
Welding
Strong backs with the same P-Number material with regardless Group Number as the
base metal shall be used to reinforce the shell plate and to prevent the welding
distortion; two pieces of them are set for a plate on the horizontal joint.
For each shell-to-shell joint, key-plates will substitute for strong-backs if those shall not
be taken off until completion of one side of the production welding.
Strong back
Strong back Top crown
To be set
400 Upper ring on outside
Center ring
C=150mm 120
To be set
Lower ring
on inside
Welding
Bottom crown
40R
The bracket shoe for scaffolding should be set on ground prior to starting erection
for eachshoe
Bracket plate.are set as given in below;
6. WELDING
Full welding shall be done with the approved welding procedure specification (WPS) and
qualified welder. Welding sequence shall be minimizes distortion and shrinkage. Welding repairs
shall be made using the same WPS that used for original production welding with approved
WPS.
http://slidepdf.com/reader/full/brazil-csp-ball-tank-erection-manual 16/18
8/20/2019 Brazil CSP-Ball Tank Erection Manual
NOTE:
1) Perform welding on equator course vertical joint as soon as they are fitted. The
columns splices may be welded after a minimum of one side of all equator
course plates are welded.
2) Welding of girth joint may be performed simultaneously with running of welding radial
joints which the welding of girth joints does not cross the unwelded or partially
welded radial joint.
3) Perform fit-up for the vertical or girth joint with key-plates and tack welding.
Finger bars should be used at all times on the fit-up side of welding courses
either distortion of the plate of the joint could be close. If the key-plate is
insufficient, the amount of finger bar shall be increased in alternate to the
amount
(6 mm), of key-plates.
weld Finger
the groove bar minimum
at 1500 thickness
mm interval shall
distances andnota be less than
minimum of 61/4 inch
inches
(150 mm) in length and the weld deposited shall be at least 6 mm thickness.
After the completion of the shell plate welding, the maximum permissible deviation
between
drawing. maximum and minimum diameter shall not exceed 0.5 % of specified diameter in
7. INSPECTION
All inspection shall be done in accordance with the specified Inspection and Test
Procedure with Plan at Field for the spherical tank.
All NDE inspection shall be carried out in accordance with the Inspection and Test
Procedure with Plan at Field, the approved NDE Procedures and approved
construction drawings.
When applicable at field, PWHT shall be done in accordance with the approved
PWHT Procedure.
9. ASSEMBLING OF ACCESSORIES
When specified in the contract, the items shall be done according to the following articles.
9.1 Accessories such as top stages instrument nozzle (stand pipe) and water spray
system
shall be installed successively after the non-destructive examination of the body.
9.2 Valves and instruments
9.3 The thermometers should be set before the hydrostatic test.
9.4 The pressure gauge should be set after completion of hydrostatic test.
9.5 Valves should be set with special care of the adequate tightening center ring gasket.
Water spray piping test shall be performed according to the drawing or the specified
specification.
http://slidepdf.com/reader/full/brazil-csp-ball-tank-erection-manual 18/18