Name of the Project : COCHIN UNIVERSITY

Type of Structure - RCC Rooftop

Tilt Angle - 10 degree

Tilt type - Fixed


Table orienttion - potrait
Size of table - 2 X 6

Minimum Ground Clearance - 700 mm

Module make Adani

Module watt peak 335

Module type Monofacial

Matrial Specification

Column hot dip


Purlin Galvalume
Rafter Galvalume
Bracing Galvalume

Fastener SS 304

Foundation
Any constarint from customer yes

Chipping/Anchor yes

Foundation type Ballast


Dimension of Foundation Ø300mm
Depth of Foundation 1500mm

Special Requirement one bird repellent spike at a level higher than the panel
edge

Structure Weight:-

Approximate weight 45.5 MT/MWp


RCC Rooftop
Industrial Shed
Ground Mount

Fixed
Seasonal
potrait
Landscape

Trina 330
Adani 335
Renesola 340
Vikram 345
JA solar 350
Jinko 355
Waree 360
365
380
Hot dip 385
Galvalume 390
Black 395
400
HDG 5.6 405
HDG 6.6 410
SS 304 415
420
425
430
435
No 445
450
Ballast 455
Anchoring 460
Pile Found 465

470
485
490
495
500
Name of the Project : DCM TEXTILES, HISAR

Wind Speed - 170kmph


Type of Structure - Ground Mount
Tilt Angle - 19°
Tilt type - Fixed
Table orienttion - Potrait
Size of table - 2 X 14
Minimum Ground Clearance - 500 mm
Module make - Trina As per layout
Module watt peak - 410
Module type - Mono Crystaline

Matrial Specification

Thcikness
Member Section Type Material Type Grade
(in mm)
Column C with Lip 2 - hot dip 350 Mpa
Purlin Hat Section 0.9 - Galvalume 350 Mpa
Rafter C with lip 1.6 - Galvalume 350 Mpa
Bracing C with lip 1.6 - Galvalume 350 Mpa
Fastener - SS 304

Foundation
Any constarint from customer - No
Chipping/Anchor - No
Foundation type - Pile +
Dimension of Foundation - Ø300mm
Pile Capping Height 100mm
Depth of Foundation - 2000mm
Foundation Quantity: - 6/Table

Structure Weight:-

Approximate weight - 28.635 MT/MWp

General Requirement Column will be HDGI and all other members will be
Glavalume.
Note:-
1 Any change in module will lead to change in design.
2 No soil data is available. Pile depth to be finalised after soil data and pullout test.