PT.

WALSIN LIPPO INDUSTRIES


JADWAL KERJA
OPERATOR DRAWING 9 S/D 10
SEN SEL RAB KAM JUM SAB MINGG
Machine Nama KETERANGAN
22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb
EKO PRASETIO 1 1 OFF 3 3 3 OFF
DRAWING CATUR 2 OFF 1 1 1 OFF 3
9/10 FATKHURI OFF 2 2 2 OFF 1 1
AGUS G 3 3 3 OFF 2 2 OFF
SUWARNO 1 1 OFF 3 3 3 OFF
DRAWING IBRAHIM 2 1 1 1 OFF 3
11/12 IWAN R OFF 2 2 2 OFF 1 1
ABD AZIZ 3 3 3 OFF 2 2 OFF
KHUSNI A 1 1 OFF 3 3 3 OFF
DRAWING KHOLIK 2 OFF 1 CUTI 1 OFF 3
13/14 KUSNI ALU OFF 2 2 2 OFF 1 1
DIFKA N 3 3 3 OFF 2 2 OFF
ARZIN 1 1 OFF 3 3 3 OFF
EKO MULIANTO 2 1 1 1 3
DRAWING
ROMANSYAH OFF 2 2 2 OFF 1 1
15/16
ROHMAT 3 3 3 OFF 2 2 OFF
ATNANTO 1 1 1 1 1 OFF OFF
GUSTRI W 1 1 OFF 3 3 3 OFF
DRAWING AAN A 2 OFF 1 1 1 OFF 3
17/18 RUSLAN OFF 2 2 2 OFF 1 1
DEDI A 3 3 3 OFF 2 2 OFF
MUSLIM 1 1 OFF 3 1 3 OFF
DRAWING AHMAD T 2 OFF 1 1 1 OFF 3
19/20 MULYANA OFF 2 2 2 OFF 1 1
WAHYU A 3 3 3 OFF 2 CUTI OFF
SURAHMIN 1 1 1 1 1 OFF OFF
CEK PROD
M.MAHA 1 1 1 1 1 OFF OFF
Dibuat Oleh :
CATATAN : SETIAP OVER SHIFT DAN BUNYI MUSIK MEMBERSIHKAN DAN MARAPIKAN MESIN AREA KERJANYA Nurdin / M Maha