Professional Documents
Culture Documents
In preparation for the Centennial Celebration in 2021, the St. Joan of Arc
Sanctuary Restoration Project was focused on restoration of the historic
sanctuary space, improved user comfort, ADA accessibility, and increased
functionality resulting in an enhanced worship experience.
St. Joan of Arc is an historic structure built in the Roman Basilica style and
completed in 1929. Minimal restoration work had happened over the last
87 years. The Parish completed a scoping document outlining the proposed
scope of work and anticipated priorities. This study took that initial scoping
information and evaluated phasing strategies to most efficiently implement
the work, build excitement through the process, and minimize overall cost.
The result was a proposed three phased project starting in 2017. The total
project cost for the overall project was estimated at $4.2M.
• Phase 1 - focused on HVAC upgrades (specifically adding air conditioning to the
sanctuary), ADA accessibility, and key functional upgrades with an estimated
cost of $1.6M completed.
• Phase 2 - addresses painting, lighting, and clerestory window restoration
estimated at $900K.
• Phase 3 - will complete terrazzo flooring installation, pew cleaning/restoration,
and organ restoration estimated at $1.7M.
Phases 2 and 3 may be combined depending on fundraising. The focus of this
study was on the Phase 1 scope of work that was recently completed.
Option 1
Phase 1 Phase 2 Phase 3
Year: 2017 Year: 2019-2020 Year: 2020-2021
Scope: Paint Restoration, Lighting, and
Scope: HVAC & Accessibility Scope: Pews and Flooring
Windows
Cost: $1.6M Cost: $900K Cost: $1.7M
Duration: Feb-June Duration 2.5 Months Duration: 2.5 Months
Pros: Cons:
- More even distribution of cost over 3 years - Have to vacate sanctuary twice (‘18 & ‘19)
- Able to use school gym in summer - Increased cost
Option 2
Phase 1 Phase 2
Year: 2017 Year: 2020
Scope: HVAC & Accessibility Scope: Paint Restoration, Lighting, Windows, Pews, and Flooring
Cost: $1.56M Cost: $2.55M
Duration: Feb-May Duration: 5 Months
Pros: Cons:
- Only have to vacate the sanctuary one time - Will be out of sanctuary for 5 months
- Significant cost savings
PROCESS/SCHEDULE
Schmidt Associates was retained in August of 2016 to restore the St. Joan of
Arc sanctuary space and upgrade the HVAC and electrical systems. Working
with the Parish Building Committee Task Force and the Office of Management
Services (OMS) for the Archdiocese of Indianapolis a project schedule was
created for the project.
Schedule Objectives:
• Key approval dates were developed to align with OMS committee meetings
• Phase 1 schedule created around having HVAC installed by summer of 2017
• Consideration for already scheduled weddings
• Overall schedule established to be complete by centennial celebration (2021).
• Focus on scheduling work that will impact sanctuary space during summer
months when school gym can be used for worship space
Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Scoping
Design
Bidding
Construction
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun July Aug Sep Oct Nov Dec
Design
Bidding*
Procurement/
Submittals *
Construction*
* If the project is completed in two phases, work can be complete in 2020. With three
phases the work will be complete in 2021.
• Demo of Existing System & Boilers • Repair bottom of door to prevent dragging.
Reconciliation $27,350
Mechanical/Electrical $907,200
Structural $40,500
Site $6,750
Total $1,067,200
Estimated Actual
Construction Cost $1,067,200 $981,600
Scaffolding $130,000
Total $925,000
Total $1,710,000
Loving God,
At this time in the life of our parish,
we turn to You with grateful hearts,
for what we have,
and with grateful anticipation
for what is yet to be.