You are on page 1of 4

CON Title - [CON Title] COIN Numbers - [Case]

Duty Holder – [Company Name] IMT Topic Assessor – [Name]

MANAGEMENT SYSTEMS SCHEDULE 10 - COMBINED OPERATIONS - INSPECTION TEMPLATE

Note on Purpose of Template

This document is to be used by inspectors to record the inspection of a combined operations notification submitted under SCR2015 against the requirements
of Schedule 10, which outlines the ‘Particulars to be included in a notification of combined operations’. It has been decided that this will be conducted by the
focal point inspector for the production installation and the non-production installation, and by exception the inspector may refer the notification to a topic
specialist inspector to comment where he/she feels it is necessary to explore the details of the submission further.

The document is drafted to complement the guidance being produced to support the regulations, as well as existing topic sector guidance. Requirements
identified by green text are new to SCR2015, those in black text were present in SCR05.

Relevant Pre-Existing Guidance

 APOSC Principles:
Combined Operations

 Principle 28
The management system should address the additional risks associated with combined operations
 Principle 29
A systematic approach should be taken to assessing the impact of combined operations on the conclusions of the operational safety case for each
installation
 Principle 30
A systematic approach should be taken to identifying and assessing any additional major accident hazards arising from combined operations. These
can be new hazards or changes to existing hazards
 Principle 31
The measures for emergency response should be appropriate to the particular combined operation
 Principle 32
Elements that become safety critical elements (SCEs) as a result of combined operations should be identified and made subject to verification. They
may be parts of the individual installations, or additional plant or equipment provided for the combined operations

TRIM: 2016/111388 Revised: 4/5/2016 Page 1 of 4


Owner: ED7
CON Title - [CON Title] COIN Numbers - [Case]
Duty Holder – [Company Name] IMT Topic Assessor – [Name]

 GASCET Chapters:
3 Safety Management Systems

 The SMS should encompass the marine, helicopter and diving activities of the installation, and relevant aspects of combined
operations. The areas of interface between the SMS of these operations, and the SMS of the installation, need to be identified and
assessed for clarity, to ensure potential hazard have been identified due to duplication, commission or omission.

TRIM: 2016/111388 Revised: 4/5/2016 Page 2 of 4


Owner: ED7
CON Title - [CON Title] COIN Numbers - [Case]
Duty Holder – [Company Name] IMT Topic Assessor – [Name]

Clarification

Objection Raised
SCR2015 Regulatory Requirement

Schedule 10 - Particulars to be included in a notification of combined operations


1.  The name and address of the duty holder submitting the notification.
2. The name and address of each duty holder preparing the notification and a confirmation that every such duty holder has agreed to the
contents of the notification.
3. A description of the combined operation and a programme of work, which must include the dates on which the combined operation is
expected to commence and finish.
4. Particulars of any plant to be used in connection with the combined operation but which is not described in the current safety case for any of
the installations involved in the combined operation.
5.  A summary of the joint review referred to in paragraph 23(b) of Schedule 6 or paragraph 19(b) of Schedule 7, which must include
(a) a description of any activities during the combined operation which may involve hazards with the potential to cause a major
accident on or in connection with an installation; and
(b) a description of any risk control measures introduced as a result of that review.
6. A description, by reference to a bridging document authorised by all parties to the document, of how the management systems for the
installations involved in the combined operation will be co-ordinated so as to reduce the risks from a major accident to comply with the relevant
statutory provisions.
Inspection Guidance / Minimum Information Doc Ref Inspector’s Inspection Comments
Is the name and address of each duty holder preparing the IMT Inspector to comment on the detail and adequacy. IMT
notification stated and a confirmation that every such duty Inspector shall check that each installation has a current, accepted
holder has agreed to the contents of the notification? Who safety case.
are the duty holders?
Is there a description of the combined operation and a IMT Inspector to comment on the detail and adequacy, refer to
programme of work, which must include the dates on which Wells or Pipelines Topic Specialists for support as required. Is the
the combined operation is expected to commence and programme of work consistent with any well notification or pipeline
finish? notifications that may also have been received?
 Are the particulars of any plant to be used in connection Where additional plant is identified refer to relevant topic specialists
with the combined operation but which is not described in to comment on the detail and adequacy.
the current safety case for any of the installations involved
in the combined operation given?
Is there a summary of a joint review that identified the IMT Inspector to comment on the detail and adequacy or refer to
hazards and assessed the risks of the combined operation? Topic Specialists for support as required. It is recommended that
Does it include: for MODUs or flotels in a combined operation next to a production
installation, that the CON is inspected in more detail, using the
expertise of other relevant topic specialists
(a) a description of any activities during the combined
operation which may involve hazards with the
potential to cause a major accident on or in

TRIM: 2016/111388 Revised: 4/5/2016 Page 3 of 4


Owner: ED7
CON Title - [CON Title] COIN Numbers - [Case]
Duty Holder – [Company Name] IMT Topic Assessor – [Name]

connection with an installation; and


(b) a description of any risk control measures
introduced as a result of that review?
Is there a description, by reference to a bridging document IMT Inspector to comment on the detail and adequacy
authorised by all parties to the document, of how the
management systems for the installations involved in the
combined operation will be co-ordinated so as to reduce the
risks from a major accident to comply with the relevant
statutory provisions?

TRIM: 2016/111388 Revised: 4/5/2016 Page 4 of 4


Owner: ED7

You might also like