JADWAL PELAKSANAAN PEKERJAAN

TAHUN ANGGARAN 2020 - 2021


NAMA PROYEK : PEMBANGUNAN RUMAH SUSUN PEMKAB TAMBRAUW
KONTRAKTOR : PT. SURYA EKA CIPTA
NOMOR KONTRAK : 07/HK.02.03/KONTR/RUSUN PEMKAB-TAMBRAUW/VIII/2020
TANGGAL KONTRAK : 14 AGUSTUS 2020
NOMOR KONTRAK ADENDUM 1 : 07/ADD.1/HK.02.03/KONTR/RUSUN.PEMKAB-TAMBRAUW/II/2021
TANGGAL KONTRAK ADENDUM 1 : 18 FEBRUARI 2021
MASA PELAKSANAAN : 300 HK

BOBOT BOBOT BOBOT SEPTEMBER OKTOBER NOPEMBER DESEMBER JANUARI PEBRUARI MARET APRIL MEI JUNI
SISA 24 AUG 31 AUG 07 SEP 14 SEP 21 SEP 28 SEP 05 OKT 12 OKT 19 OKT 26 OKT 02 NOP 09 NOP 16 NOP 23 NOP 30 NOP 07 DES 14 DES 21 DES 28 DES 04 JAN 11 JAN 18 JAN 25 JAN 01 PEB 08 PEB 15 PEB 22 PEB 01 MRT 08 MRT 15 MRT 22 MRT 29 MRT 05 APR 12 APR 19 APR 26 APR 3 MEI 10 MEI 17 MEI 31 MEI 25 MEI 7 JUNI 14 JUNI
KONTRAK KONTRAK MINGGU KE
NO URAIAN PEKERJAAN JUMLAH BOBOT KET.
AWAL ADD 1 25 s/d s/d s/d s/d s/d s/d s/d s/d
(%)
(%) (%) (%) 30 AUG 06 SEP 13 SEP 20 SEP 27 SEP 04 OKT 11 OKT 18 OKT 25 OKT 01 NOP 08 NOP 15 NOP 22 NOP 29 NOP 06 DES 13 DES 20 DES 27 DES 03 JAN 10 JAN 17 JAN 24 JAN 31 JAN 07 PEB 14 PEB 21 PEB 28 PEB 07 MRT 14 MRT 21 MRT 28 MRT 04 APR 11 APR 18 APR 25 APR 2 MEI 9 MEI 16 MEI 23 MEI 30 MEI 6 JUNI 13 JUNI 19 JUNI
MG.1 MG.2 MG.3 MG.4 MG.5 MG.6 MG.7 MG.8 MG.9 MG.10 MG.11 MG.12 MG.13 MG.14 MG.15 MG.16 MG.17 MG.18 MG.19 MG.20 MG.21 MG.22 MG.23 MG.24 MG.25 MG.26 MG.27 MG.28 MG.29 MG.30 MG.31 MG.32 MG.33 MG.34 MG.35 MG.36 MG.37 MG.38 MG.39 MG.40 MG.41 MG.42 MG.43
I PEKERJAAN PERSIAPAN STANDART #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
I.A PEKERJAAN PERSIAPAN #REF!
Pengukuran dan Pemasangan Bouwplank 15.549.100,00 0,0664 0,0664 0,0664 - 0,0022 0,0022 0,0022 0,0022 0,0022 0,0022 0,0022 0,0022 0,0022 0,0022 0,0022 0,0022 0,0022 0,0022 0,0022 0,0022 0,0022 0,0022 0,0022 0,0022 0,0022 0,0022 0,0022 0,0022 0,0022
Direksi Keet 53.239.200,00 0,2272 0,2272 0,2272 - 0,1136 0,1136 - - - - - - - - - - - - - - - - - - - - - - -
Papan Nama Proyek 1.363.862,50 0,0058 0,0058 0,0058 - - 0,0058 - - - - - - - - - - - - - - - - - - - - - - -
Foto Proyek 4.815.000,00 0,0205 0,0205 0,0191 0,0014 0,0008 0,0008 0,0008 0,0008 0,0008 0,0008 0,0008 0,0008 0,0008 0,0008 0,0008 0,0008 0,0008 0,0008 0,0008 0,0008 0,0008 0,0008 0,0008 0,0008 0,0008 0,0008 0,0008 0,0008 0,0008 0,0001 0,0001 0,0001 0,0001 0,0001 0,0001 0,0001 0,0001 0,0001 0,0001 0,0001 0,0001 0,0001 0,0001 0,0001 0,0001 0,0001 0,0001
Pagar Seng Keliling Proyek 68.035.740,00 0,2904 0,2904 0,2904 - 0,0726 0,1452 0,0726 - - - - - - - - - - - - - - - - - - - - - -
I.B PEKERJAAN RK3K KONSTRUKSI
I.B.1 PENYIAPAN RKK 4.800.000,00 0,0205 0,0205 0,0150 0,0055 0,0205 0,0003 0,0003 0,0003 0,0003 0,0003 0,0003 0,0003 0,0003 0,0003 0,0003 0,0003 0,0003 0,0003 0,0003 0,0003 0,0003 0,0003 0,0003
I.B.2 SOSIALISASI, PROMOSI DAN PELATIHAN 3.290.000,00 0,0140 0,0140 0,0140 - - 0,0140
I.B.3 ALAT PELINDUNG KERJA DAN ALAT PELINDUNG DIRI 115.668.000,00 0,4937 0,4937 0,2885 0,2051 0,0688 0,1638 0,0093 0,0093 0,0093 0,0093 0,0093 0,0093 0,0093 0,0093 0,0093 0,0093 0,0093 0,0093 0,0093 0,0093 0,0093 0,0093 0,0093 0,0093 0,0093 0,0093 0,0093 0,0093 0,0093 0,0114 0,0114 0,0114 0,0114 0,0114 0,0114 0,0114 0,0114 0,0114 0,0114 0,0114 0,0114 0,0114 0,0114 0,0114 0,0114 0,0114 0,0114
II PEKERJAAN STRUKTUR, ARSITEKTUR DAN ME
II.A.1 PEKERJAAN STRUKTUR STANDARD
A.1.1 LANTAI DASAR 1.836.852.185,60 7,8394 7,8394 6,3421 1,4973 - - - - - - - 0,9635 0,9934 0,8565 0,8019 0,8019 1,1794 1,1089 - - - 0,9892 0,1443 - - - - - - 0,2496 0,2496 0,2496 0,2496 0,2496 0,2496
A.1.2 LANTAI 2 2.228.381.326,29 9,5104 9,5104 8,2102 1,3001 - - - - - - - - - 0,6154 1,7246 1,7700 - 0,8732 2,4212 - - 0,8362 0,9892 0,1402 0,1402 - - - - 0,2167 0,2167 0,2167 0,2167 0,2167 0,2167
A.1.3 LANTAI 3 1.618.237.452,30 6,9064 6,9064 6,0916 0,8148 - - - - - - - - - - - - - - - 2,4123 2,6860 - 0,5926 0,4862 0,4486 0,1402 0,1402 - - 0,1358 0,1358 0,1358 0,1358 0,1358 0,1358
A.1.4 LANTAI DAK 473.425.169,35 2,0205 2,0205 1,6053 0,4152 - - - - - - - - - - - - - - - - - - - - 1,2528 - 0,7676 0,1038 0,1038 0,1038 0,1038
PROGRESS RENCANA ADENDUM I
A.1.5 LANTAI ATAP 404.211.827,92 1,7251 1,7251 1,6995 0,0256 - - - - - - - - - - - - - - - - - - - - - - 0,8463 0,8787 - 0,0085 0,0085 0,0085
A.1.6 RANGKA ATAP BAJA 414.054.665,00 1,7671 1,7671 1,7577 0,0094 - - - - - - - - - - - - - - - - - - - - - - - 0,9750 0,7921 0,0031 0,0031 0,0031

ADDENDUM I, TANGGAL 18 FEBRUARI 2021


II.A.2 PEKERJAAN ARSITEKTUR STANDART
A.2.1 PEKERJAAN LANTAI 1 2.889.840.627,60 12,3334 12,3334 7,6483 4,6850 - - - - - - - - - - - - - - - - - 1,0113 1,1377 1,2641 1,1377 1,7822 2,5167 2,3975 0,6410 0,6693 0,6693 0,6693 0,6693 0,6693 0,6693 0,6693
A.2.2 PEKERJAAN LANTAI 2 2.907.979.437,20 12,4108 12,4108 6,5964 5,8144 - - - - - - - - - - - - - - - - - - - 1,0683 0,8012 1,3354 2,1366 1,9710 2,0854 0,8306 0,8306 0,8306 0,8306 0,8306 0,8306 0,8306
A.2.3 PEKERJAAN LANTAI 3 2.949.183.751,20 12,5866 12,5866 1,4811 11,1055 - - - - - - - - - - - - - - - - - - - - - 1,0945 1,0945 1,0945 2,1889 1,5865 1,5865 1,5865 1,5865 1,5865 1,5865 1,5865
A.2.4 PEKERJAAN LANTAI DAK DAN ATAP 458.943.539,58 1,9587 1,9587 0,6868 1,2719 - - - - - - - - - - - - - - - - - - - - - - - - 1,2462 0,3180 0,3180 0,3180 0,3180
II.B.1 PEKERJAAN STRUKTUR NON STANDARD
B.1.1 Pondasi Bore Pile dan Tie Beam (Sloof) 3.344.172.529,67 14,2724 14,2724 12,7561 1,5163 0,4481 1,6713 1,9787 2,0980 2,1195 2,0533 0,9759 0,4965745 - - 0,9173964 0,1528 0,4632 0,4632 0,2417 - - - - - - - - 0,2527 0,2527 0,2527 0,2527 0,2527 0,2527
B.1.2 PEKERJAAN STRUKTUR GWT , RUANG POMPA DAN PONDASI STP
I PEKERJAAN STRUKTUR GWT 785.315.234,37 3,3516 3,3516 0,2739 3,0777 0,0110 0,0110 0,3977 0,2839 0,2839 0,3452 0,8998 0,8998 - 0,2192 - - - - - - - - - - - - 1,0259 1,0259 1,0259
II PEKERJAAN STRUKTUR RUANG POMPA 191.361.832,36 0,8167 0,8167 0,1808 0,6359 - - - - - - - - - - - - - - - - - - 0,0003 0,2020 0,2000 0,0008 0,1762 0,0900 0,1474 0,2120 0,2120 0,2120
PROGRESS RENCANA
III PEKERJAAN STRUKTUR PONDASI STP 13.409.856,32 0,0572 0,0572 - 0,0572 - - - - - - - - - - - - - - - - - - - - - - - - 0,0227 0,0572
KONTRAK AWAL
II.B.2 PEKERJAAN ARSITEKTUR NON STANDARD
B.2.1 PEK. KELILING BAGIAN LUAR BANGUNAN 443.716.177,16 1,8937 1,8937 - 1,8937 - - - - - - - - - - - - - - - - - - - - - - - - 0,4712 0,3156 0,3156 0,3156 0,3156 0,3156 0,3156
B.2.2 PEKERJAAN DRAINASE KELILING BAGIAN LUAR BANG. 214.709.588,96 0,9163 0,9163 - 0,9163 - - - - - - - - - - - - - - - - - - - - - - - - - 0,1527 0,1527 0,1527 0,1527 0,1527 0,1527
B.2.3 PEKERJAAN GROUND TANK DAN R. POMPA DI LUAR BANGUNAN 113.465.945,00 0,4843 0,4843 - 0,4843 - - - - - - - - - 0,0889 0,0278 - 0,0193 - - - - - - - - 0,0831 - 0,0647 0,0502 0,0807 0,0807 0,0807 0,0807 0,0807 0,0807
B.2.4 PEKERJAAN LAIN-LAIN 42.207.790,00 0,1801 0,1801 - 0,1801 - - - - - - - - - - - - - - - - - - - - - - - - - 0,0300 0,0300 0,0300 0,0300 0,0300 0,0300
II.B.3 PEKERJAAN MEKANIKAL & ELEKTRIKAL STANDART
B.3.1 LANTAI 1 390.938.790,43 1,6685 1,6685 1,2377 0,4308 - - - - - - - 0,1146 0,1146 - - - 0,1746 0,3493 - - - - - - - - - - - 0,1077 0,1077 0,1077 0,1077
B.3.2 LANTAI 2 306.225.139,84 1,3069 1,3069 0,6866 0,6203 - - - - - - - - - - - - - 0,0358 0,0358 - - - - - - - - - - 0,1551 0,1551 0,1551 0,1551
B.3.3 LANTAI 3 306.214.887,68 1,3069 1,3069 0,5289 0,7780 - - - - - - - - - - - - - - - - - - 0,0345 0,0345 - - - - - 0,1945 0,1945 0,1945 0,1945
B.3.4 LANTAI ATAP 15.730.120,69 0,0671 0,0671 0,0545 0,0126 - - - - - - - - - - - - - - - - - - - - - - 0,0347 - - 0,0031 0,0031 0,0031 0,0031
B.3.5 PEKERJAAN UTILITAS 134.595.320,10 0,5744 0,5744 - 0,5744 - - - - - - - - - - - - - - - - - - - - - - - - - 0,1436 0,1436 0,1436 0,1436
B.3.6 PEKERJAAN SISTEM PENTANAHAN 6.407.917,85 0,0273 0,0273 - 0,0273 - - - - - - - - - - - - - - - - - - - - - - - - - 0,0068 0,0068 0,0068 0,0068
B.3.7 PEKERJAAN PENANGKAL PETIR 28.453.407,49 0,1214 0,1214 - 0,1214 - - - - - - - - - - - - - - - - - - - - - - - - - 0,0607 0,0607
C PEKERJAAN MEKANIKAL & ELEKTRIKAL NON STANDART - -
C.1 PEKERJAAN PEMADAM KEBAKARAN - - PROGRESS REALISASI
I INSTALASI APAR 5.129.342,00 0,0219 0,0219 - 0,0219 - - - - - - - - - - - - - - - - - - -
KONTRAK -
AWAL - - - - - 0,0055 0,0055 0,0055 0,0055
II PEKERJAAN VENTILASI UDARA 44.542.671,80 0,1901 0,1901 - 0,1901 - - - - - - - - - - - - - - - - - - - - - - - - - 0,0475 0,0475 0,0475 0,0475
III PEKERJAAN INSTALASI ELEKTRONIK 156.295.056,38 0,6670 0,6670 - 0,6670 - - - - - - - - - - - - - - - - - - - - - - - - - 0,1668 0,1668 0,1668 0,1668
I PEKERJAAN SYSTEM TV
C.2 PEKERJAAN SARANA DAN PRASARANA LINGKUNGAN (LUAR BANGUNAN) 216.958.661,91 0,9259 0,9259 - 0,9259 - - - - - - - - - - - - - - - - - - - - - - - - - 0,1852 0,1852 0,1852 0,1852 0,1852
I PEKERJAAN INSTALASI PLAMBING
C.2.1 INSTALASI AIR KOTOR & AIR BEKAS 108.906.107,10 0,4648 0,4648 - 0,4648 - - - - - - - - - - - - - - - - - - - - - - - - - 0,1549 0,1549 0,1549
C.2.2 PENYAMBUNGAN DAYA PLN 106.600.000,00 0,4550 0,4550 - 0,4550 - - - - - - - - - - - - - - - - - - - - - - - - - 0,4550
C.2.3 PEKERJAAN INSTALASI KABEL FEEDER 7.837.388,36 0,0334 0,0334 - 0,0334 - - - - - - - - - - - - - - - - - - - - - - - - - 0,0111 0,0111 0,0111

JUMLAH NILAI PEKERJAAN 23.431.064.649,99 100,000 100,000 58,764 41,236

MINGGUAN 0,278 0,894 1,767 2,002 2,508 2,416 2,350 2,412 2,517 2,473 2,567 2,584 2,522 2,532 2,933 2,888 2,940 2,849 2,911 3,208 3,993 4,448 7,725 7,484 7,657 6,634 5,345 4,461 2,666 2,038
RENCANA
KOMULATIF - 0,278 1,172 2,939 4,941 7,449 9,865 12,215 14,626 17,143 19,616 22,183 24,767 27,289 29,822 32,754 35,642 38,582 41,431 44,342 47,550 51,543 55,991 63,716 71,200 78,857 78,857 85,491 90,836 95,296 97,962 100,000

MINGGUAN 0,002 0,002 0,002 1,197 2,098 0,812 0,738 3,659 6,597 0,687 0,652 0,511 0,434 5,570 0,091 1,238 1,816 4,196 2,602 6,745 2,907 6,522 8,048 0,709 0,932
REALISASI
KOMULATIF - - 0,002 0,004 0,006 1,203 3,301 4,113 4,850 8,509 15,106 15,794 16,445 16,956 17,389 22,960 23,051 24,289 26,105 30,301 32,903 39,648 42,555 49,076 57,124 57,833 58,764

KOMULATIF (0,277) (1,168) (2,934) (3,739) (4,148) (5,752) (7,364) (6,117) (2,037) (3,822) (5,738) (7,811) (9,900) (6,862) (9,703) (11,353) (12,477) (11,130) (11,439) (7,902) (8,988) (6,915) (6,592) (13,367) (20,093)

MINGGUAN 0,514 0,731 0,867 1,747 2,733 4,526 4,488 4,067 3,764 3,575 2,489 2,489 2,264 2,383 2,249 0,787 0,787 0,776
RENCANA ADDENDUM KE - 1
KOMULATIF - 0,004 0,006 1,203 3,301 4,113 4,850 8,509 15,106 15,794 16,445 16,956 17,389 22,960 23,051 24,289 26,105 30,301 32,903 39,648 42,555 49,076 57,124 57,833 58,764 58,764 59,278 60,009 60,876 62,623 65,356 69,882 74,370 78,436 82,201 85,776 88,265 90,753 93,017 95,401 97,650 98,437 99,224 100,000

Manokwari, 18 Februari 2021

PEJABAT PEMBUAT KOMITMEN ( PPK )


RUMAH SUSUN DAN RUMAH KHUSUS

ISSA AGUNG C. WIBAWA,ST


Nip. 19821012 201412 1 001