Professional Documents
Culture Documents
SPECIFICATION
10. Fuel Oil Storage Tanks, Piping & Accessories . . . . . . . . . . . . . . . . . . . . Section 15191
SECTION 01815
ACMV COMMISSIONING REQUIREMENTS
PART 1 - GENERAL
A. Comply with the Agreement between the Construction Manager and Trade
Sub-Contractor and all other documents referred to therein.
B. Provide all services, materials and labour required to fully commission the
mechanical systems in accordance with this Section of the Specification.
1.2 COORDINATION
B. Coordinate the work of this Section with all other Divisions to ensure complete
and operational mechanical systems at completion of this work.
D. Review the design intent of the project and the intended operation of systems
with the Consultant before proceeding with commissioning.
. Page 1 of 7
DIVISION 15 – MECHANICAL ACMV Commissioning Requirements SECTION 01815
. Page 2 of 7
DIVISION 15 – MECHANICAL ACMV Commissioning Requirements SECTION 01815
E. The Consultant may, at his discretion, attend and advise in the commissioning
process. Meet Consultant requirements.
F. Hold and attend regular meetings during the commissioning process. Prepare
detailed progress reports to coincide with regular commissioning meetings.
Coordinate with the Commissioning Manager, the preparation and issue of
minutes for each meeting to be circulated to each involved trade, the
Consultant and the Construction Manager representative(s). Minutes shall
highlight action items.
PART 2 - PRODUCTS
4. Air balancing
. Page 3 of 7
DIVISION 15 – MECHANICAL ACMV Commissioning Requirements SECTION 01815
11. Troubleshooting
C. List all specialist personnel and equipment required for the test and ensure
that these are available by the test date.
. Page 4 of 7
DIVISION 15 – MECHANICAL ACMV Commissioning Requirements SECTION 01815
2.3 STARTUP
A. Coordinate and supervise the start-up of the various pieces of equipment and
systems. Utilize the start-up services of the manufacturer's representative.
Ensure that the equipment is operating in a satisfactory manner. Including,
but not necessary limited to the following:
1. Direction of rotation
4. Seals
2.4 TROUBLESHOOTING
. Page 5 of 7
DIVISION 15 – MECHANICAL ACMV Commissioning Requirements SECTION 01815
D. Carry out operational tests for the current season and simulate operation of
summer, winter and intermediate seasons.
2.6 DEMONSTRATION
2.9 COMPLETION
A. Provide a list of spare parts, special tools, lubricants, etc. for each item of
equipment which has been purchased as part of the Contract.
B. Provide a listing of recommended spare parts for all equipment installed under
Division 15, to cover a period from Substantial Completion to Warranty end.
2. Manufacturer's part name, part number, unit price, lead time, shelf life
3. Quantity recommended for 1 year
. Page 6 of 7
DIVISION 15 – MECHANICAL ACMV Commissioning Requirements SECTION 01815
D. Submit preliminary list of spare parts and tools to Contractor at least 30 days
prior to intended system handover to Contractor. The Contractor reserves the
right to add to, reduce or omit entirely, the recommendations contained on
these lists.
PART 3 - EXECUTION
1. Temperature sensors
3. Status switches
. Page 7 of 7
DIVISION 15 – MECHANICAL ACMV Commissioning Requirements SECTION 01815
6. Alarm contacts
B. Verify correct sensors are reporting accurately to the distributed field panels
and operator workstation.
C. Operate each major equipment. Verify and correct the following if required:
F. Verify that all cooling coil drain pans and condensate piping operate.
B. Coordinate with Division 16, a power failure test with emergency generator
start-up.
D. Verify that interfacing to the work of other Divisions results in complete and
operational systems.
A. Visit the site and the Contractor's representative each month after Substantial
. Page 8 of 7
DIVISION 15 – MECHANICAL ACMV Commissioning Requirements SECTION 01815
Performance for a minimum period of two days until the end of the project
warranty period.
D. Prepare a report for the Consultant and Construction Manager for inclusion in
the Operating Manuals of the problems and issues that have arisen and the
corrective action(s) recommended and implement.
END OF SECTION
. Page 9 of 7
DIVISION 15 – MECHANICAL Through Penetration Firestopping Systems SECTION 07841
SECTION 07841
THROUGH PENETRATION FIRESTOPPING SYSTEMS
PART 1- GENERAL
1.1 DESCRIPTION
A. Closures of openings in walls, floors, and roof decks against penetration of flame,
heat, and smoke or gases in fire resistant rated construction.
1.2 SUBMITTALS
D. Certified laboratory test reports for ASTM E 814 tests for systems not listed by FM,
UL, or WH proposed for use.
A. Deliver materials in their original unopened containers with manufacturer’s name and
product identification.
B. Store in a location providing protection from damage and exposure to the elements.
1.4 GUARANTEE
Firestopping work subject to the terms of the Article GUARANTY except extend the guaranty
period to five years.
The Publications listed below form a part of this specification to the extent referenced.
Publications are referenced in the text by the basic designation only.
Page 1 of 4
DIVISION 15 – MECHANICAL Through Penetration Firestopping Systems SECTION 07841
PART 2 – PRODUCTS
D. Firestop sealants used for firestopping or smoke sealing shall have following
properties:
4. When used in exposed areas, shall be capable of being sanded and finished
with similar surface treatments as used on the surrounding wall or floor
surface.
E. Firestopping system or devices used for penetrations by glass pipe, plastic pipe or
conduits, unenclosed cables, or other non-metallic materials shall have following
properties:
1. Classified for used with the particular type of penetrating material used.
Page 2 of 4
DIVISION 15 – MECHANICAL Through Penetration Firestopping Systems SECTION 07841
3. Intumescent products which would expand to seal the opening and act as
fire, smoke, toxic fumes, and, water sealant.
C. Sealants shall have a maximum flame spread of 25 and smoke developed of 50 when
tested in accordance with E84.
D. When used in exposed areas capable of being sanded and finished with similar
surface treatments as used on the surrounding wall or floor surface.
PART 3 – EXECUTION
3.1 EXAMINATION
Submit product data and installation instructions, as required by article, submittals, after an on
site examination of areas to receive firestopping.
3.2 PREPARATION
A. Remove dirt, grease, oil, loose materials, or other substances that prevent adherence
and bonding or application of the firestopping or smoke stopping materials.
B. Remove insulation on insulated pipe for a distance of 150 mm (six inches) on either
side of the fire rated assembly prior to applying the firestopping materials unless the
firestopping materials are tested and approved for use on insulated pipes.
3.3 INSTALLATION
A. Do not begin work until the specified material data and installation instructions of the
proposed firestopping systems have been submitted and approved.
B. Install firestopping systems with smoke stopping in accordance with FM, UL, WH, or
other approved system details and installation instructions.
B. Do not move materials and equipment to the next-scheduled work area until
completed work is inspected and accepted by the Resident Engineer.
Page 3 of 4
DIVISION 15 – MECHANICAL Through Penetration Firestopping Systems SECTION 07841
END OF SECTION
Page 4 of 4
DIVISION 15 – MECHANICAL Basic Mechanical Materials and Methods SECTION 15050
SECTION 15050
BASIC MECHANICAL MATERIALS AND METHODS
PART 1 - GENERAL
A. Comply with Division 1, General Requirements and all documents referred to therein.
B. Provide all labour, materials, products, equipment and services to supply and install
the basic mechanical materials indicated on the Drawings and specified in Division 15
of these Specifications.
C. Identify lay-in type acoustic ceilings used for access to equipment and components by
a method acceptable to Consultant.
E. Provide typewritten master lists for each Equipment Room. Frame under glass.
Insert copies in Operating and Maintenance Instruction Manuals.
A. Provide SMS Wrap-Mark on all pipe coverings, using Wrap-Mark pipe markers with
flow arrow and alternating wording. For outside diameters up to 150 mm, allow
marker to completely wrap pipe. For larger outside diameters, secure markers with
stainless steel springs. Secure markers on vertical piping and elsewhere where
markers could be inadvertently moved.
B. Use stencils and stencil paint on ductwork or ductwork insulation. Apply solid black
capitalized lettering 50 mm high and solid black flow arrows 150 mm long x 50 mm
wide.
C. Locate identification and flow arrows so they can be seen clearly from floor and
service platforms:
. Page 1 of 18
DIVISION 15 – MECHANICAL Basic Mechanical Materials and Methods SECTION 15050
5. at entry and leaving point to pipe and duct chases, or other concealed spaces
6. both sides where piping and ductwork passes through walls, partitions and
floors
D. Colour code pipes meeting code International Standards and Owner’s requirements.
At minimum, colour code pipes with 50 mm wide bands in accordance with the detail
shown on the drawings. The Contractor is to submit the proposed colour coding of
pipes for approval.
A. Provide 40 mm dia., 1 mm thick brass tags with 10mm high die-stamped black letters.
C. Tag all valves except for small valves isolating a single piece of equipment such as a
air handling units, fan coil unit, primary air units and VRV/split ac units.
A. Identify equipment, starters, and, remote control devices in a manner consistent with
the Drawings.
C. Where equipment size does not permit stencil identification, use lamacoid labels,
engraved white on black, mechanically fastened to the equipment. Minimum lettering
size 10 mm.
B. Insert legible page size copies into each Operating and Maintenance Manual.
C. Install diagrams, framed under glass, on Equipment Room walls where directed by
Owner.
. Page 2 of 18
DIVISION 15 – MECHANICAL Basic Mechanical Materials and Methods SECTION 15050
PART 2 - PRODUCTS
2.1 INSERTS
B. Where inserts must be placed after concrete is poured, use Phillips Red Head
Multiset II Anchor system or equivalent Hilti System.
B. In lieu of the paragraph which follow, suspended equipment support and restraints
may be designed and installed in accordance with the National Uniform Seismic
Installation Guidelines (NUSIG), most current edition. Submittals based on either the
NUSIG guidelines or the following paragraphs of this Section shall be stamped and
signed by a professional. Support of suspended equipment over 227kg (500 pounds)
shall be submitted for approval of the Consultant in all cases. See paragraph 2.2.M for
lateral force design requirements.
D. Type Numbers Specified: MSS SP-58. For selection and application refer to MSS
SP-69. Refer to Section 19 Part 4,for miscellaneous metal support materials and
prime coat painting.
2. Beam clamps: Types 20, 21, 28 or 29. Type 23 C-clamp may be used for
individual copper tubing up to 23mm (7/8-inch) outside diameter.
. Page 3 of 18
DIVISION 15 – MECHANICAL Basic Mechanical Materials and Methods SECTION 15050
I. Hanger Rods: Hot-rolled steel, ASTM A36 or A575 for allowable load listed in MSS
SP-58. For piping, provide adjustment means for controlling level or slope. Types 13
or 15 turn-buckles shall provide 38 mm (1-1/2 inches) minimum of adjustment and
incorporate locknuts. All-thread rods are acceptable.
J. Multiple (Trapeze) Hangers: Galvanized, cold formed, lipped steel channel horizontal
member, not less than 41mm by 41mm (1-5/8 inches by 1-5/8 inches), 2.7 mm (No.
12 gage), designed to accept special spring held, hardened steel nuts. Not permitted
for steam supply and condensate piping.
K. Pipe Hangers and Supports: (MSS SP-58), use hangers sized to encircle insulation on
insulated piping. Refer to Section 15080, for insulation thickness. To protect
insulation, provide Type 39 saddles for roller type supports or preinsulated calcium
silicate shields. Provide Type 40 insulation shield or preinsulated calcium silicate
shield at all other types of supports and hangers including those for preinsulated
piping.
h. Copper Tube:
. Page 4 of 18
DIVISION 15 – MECHANICAL Basic Mechanical Materials and Methods SECTION 15050
1. Provide 360 degree water resistant high density 965 kPa (140 psi)
compressive strength calcium silicate shields encased in galvanized metal.
4. The type of shield is selected by the temperature of the pipe, the load it must
carry, and the type of support it will be used with.
a. Shields for supporting chilled or cold water shall have insulation that
extends a minimum of one (1 inch) 25 mm, past the sheet metal.
Provide for an adequate vapor barrier in chilled lines.
5. Shields may be used on steel clevis hanger type supports, roller supports or
flat surfaces.
. Page 5 of 18
DIVISION 15 – MECHANICAL Basic Mechanical Materials and Methods SECTION 15050
a. Design and installation to meet the criteria listed above, and meet
requirements of the latest Sheet Metal and Air Conditioning
Contractors National Association (SMACNA), Seismic Restraint
Manual Guidelines for Mechanical Systems for the prescribed
Seismic Hazard Level (SHL).
b. Design and installation to meet the criteria listed above, and meet the
most current requirements of the National Uniform Seismic
Installation Guidelines (NUSIG). Contractor shall submit all design
tables and information for the design force levels, stamped and
signed by a professional engineer registered in the place where
project is located.
A. GENERAL:
1. All chilled water, condenser water, flue gas, and other piping within
mechanical rooms or within 50 feet total pipe length (whichever is longer) of
connected vibration-isolated equipment (chillers, pumps, air handling units,
etc.) and all of the above piping that is 12 inches or larger shall be isolated
from the building structure by means of vibration-isolation mounts, resilient
pipe guides, and resilient penetration sleeve/seals.
2. Spring isolators shall be selected for a static deflection, under load of not less
than I inch Unit SLRS or 30N isolators (whichever is applicable to the
mounting condition) shall be used.
3. Where lateral support of pipe risers is required within the specified limits, this
shall be accomplished by use of resilient lateral supports.
4. Pipes within the specified limits that penetrate the building construction shall
be isolated from the building structure by use of resilient penetrating
sleeve/seals.
. Page 6 of 18
DIVISION 15 – MECHANICAL Basic Mechanical Materials and Methods SECTION 15050
A. Provide eyebolts suitable for block and tackle connection, adequately supported by
the structure above for:
1. Pumps
2. Large Fans
3. Motors
4. Fan Coil Units
5. Air Handlers
6. Cooling Towers
5. Other equipment which will require block and tackle handling
2.5 SLEEVES, WALL AND FLOOR PLATES
A. Use machine cut and reamed standard weight steel piping. Pipe sleeves 200 mm and
larger shall have minimum 6 mm wall thickness.
B. Concealed perimeter risers and runouts may have sleeves of 1.31 mm galvanized
steel set around section of insulation to provide freedom of movement of piping.
Extend 50 mm above finished floor level.
C. For piping through exterior walls, cooperate with the waterproofing trade at all times,
and do not break any waterproofing seal without consent of the waterproofing trade.
Provide waterproof link seals as detailed on Drawings.
D. Provide leak plates where pipe sleeves pass through exterior building walls. Each
leak plate shall be a 3.42 mm steel plate, welded to the sleeve, 100 mm diameter
greater than sleeve outside diameter.
E. Provide 1.31 mm galvanized steel duct sleeves. Provide adequate bracing for support
of sleeves during concrete and masonry work. For fire rated floors and walls, build
fire damper assemblies into structure to attain fire rated construction, in a manner
acceptable to the governing authorities.
F. Cover pipe sleeves in walls and ceilings of finished areas, other than Equipment
Rooms, with satin finish stainless steel, or satin finish chrome or nickel plated brass
escutcheons, with non-ferrous set screws. Do not use stamped steel split plates.
Split cast plates with screw locks, however, may be used.
G. Cover exposed duct sleeves in finished areas with 1.31 mm galvanized steel plates in
the form of duct collars. Fix in position with non-ferrous metal screws.
2.6 PROVISION FOR PIPE EXPANSION, CONTRACTION AND BUILDING SHRINKAGE
A. Where space limitations do not permit the use of expansion loops or offsets, provide
expansion joint equal Mason or Honeywell Expansion Joints properly selected for
system operating pressures according to the following:
1. For piping up to and including 65 mm, select ends to suit specified pipe
fittings. Pressure shall be external to the bellows. Pressure ratings for Model
H and HB expansion compensated as 1400 kPa and 1050 kPa.
2. Steel Piping – Honeywell expansion compensator with two ply stainless steel
bellows.
. Page 7 of 18
DIVISION 15 – MECHANICAL Basic Mechanical Materials and Methods SECTION 15050
3. Copper Piping – Honeywell expansion compensator with two ply below, all
bronze construction.
5. Steel Piping - Honeywell controlled, flexing expansion joint with stainless steel
pressure carrier, flanged ends.
B. Submit for Consultant review prior to installation, drawings showing the location of
expansion joints, anchors and guides. Show details of proposed connection to
structure and loads to be imposed.
C. Recognize that the concrete structure will shrink. Design risers with sufficient
flexibility. Consult with structural engineer to determine the degree of flexibility.
2.7 DRAINS
A. Provide minimum 20 mm ball valve with hose end adapter, metal cap and chain at all
low points of all systems. Locate to allow easy connection of hose.
B. Provide 40 mm minimum size drains from ductwork connected to intake hoods and
wall louvers. Equip drains with deep seal traps. Locate traps in heated areas.
C. Provide 20 mm valves with metal caps and chains at the base of all pipe risers. Install
hose end ball valve in conjunction with 450 mm minimum length full line size dirt leg.
B. Supply for installation by other Contractors, doors, panels and frames. Ensure that
access doors and panels are properly located.
C. Coordinate requirements for all access doors and panels to suit Architectural finishes
and large enough to provide adequate access to equipment and components.
D. Check and coordinate Architect’s provision of access doors and panels with a fire
rating required by the code governing the fire rating of the structure.
E. In tile walls, and washroom walls, supply minimum 2.78 mm Type 304 stainless steel
with #4 finish, with recessed frame secured with stainless steel countersunk flush
head screws.
F. For all other surfaces, supply minimum 2.66 mm welded steel, flush type with
concealed hinges, lock and anchor strap, and factory prime coat finish.
2.9 FLASHING
A. Flashing will be carried out under each trade for roof curbs shown on their drawings.
. Page 8 of 18
DIVISION 15 – MECHANICAL Basic Mechanical Materials and Methods SECTION 15050
C. Carry out all counterflashing for roof mounted mechanical equipment and for pipes
and ducts passing through roof. Fit counterflashing over flashing or curb. Pitch
pockets are not acceptable.
2.10 CURBS
A. Curbs required for Division 15 work will be carried out under each trade.
B. Arrange and pay for Division 3 or Division 5 to provide other curbs and reinforcing
steel required for Division 15.
E. Provide roof curbs at least 300 mm above finished roof, unless exceeded by
Architectural considerations.
F. Provide concrete curbs around holes in Equipment Room floors, extending at least
150 mm above finished floor. Make watertight connection between curb and floor.
G. Fill spaces between curbs and pipes and ducts with firestopping material similar to
“Rectorseal” or equal. Caulk watertight with manufacturer’s recommended fire
resistant waterproof compound.
2.11 CONCRETE
A. Coordinate with Division 3 provision of 100 mm concrete housekeeping pads under all
floor mounted mechanical equipment and supports. Extend pads over the full
equipment base and isolator area.
B. Concrete work, including housekeeping pads, required for Division 15 work and
shown on the Structural or Architectural Drawings will be provided by Division 3.
2.13 STEEL
A. Provide steel required for Division 15 work including supports, framing of openings
and lintels over openings that is not shown on Structural or Architectural Drawings.
B. Provide steel of adequate strength to support equipment and materials during all
operating and test conditions.
. Page 9 of 18
DIVISION 15 – MECHANICAL Basic Mechanical Materials and Methods SECTION 15050
D. Provide base supports for all pipe risers. Design to distribute operating and static
loads to meet Consultant requirements.
E. Fabricate steel supports in contact with water or humidity conditions from materials
having approved corrosion resistance or galvanize after fabrication or brush welds
clean and apply a prime coat of rust inhibiting paint.
A. Type: ANSI/RMA standard V-belts with proper motor pulley and driven sheave. Belts
shall be constructed of reinforced cord and rubber.
F. Drives may utilize a single V-Belt (any cross section) when it is the manufacturer's
standard.
4. Groove spacing for driving and driven pulleys shall be the same.
E 554 (21.80)
. Page 10 of 18
DIVISION 15 – MECHANICAL Basic Mechanical Materials and Methods SECTION 15050
2. Provide fixed-pitch drives for drives larger than those listed above.
3. The final fan speeds required to just meet the system CFM and pressure
requirements, without throttling, shall be determined by adjustment of a
temporary adjustable-pitch motor sheave or by fan law calculation if a
fixed-pitch drive is used initially.
A. For machinery and equipment, provide guards as shown in AMCA 410 for belts,
chains, couplings, pulleys, sheaves, shafts, gears and other moving parts regardless
of height above the floor. Drive guards may be excluded where motors and drives are
inside factory fabricated air handling unit casings.
B. Materials: Sheet steel, cast iron, expanded metal or wire mesh rigidly secured so as to
be removable without disassembling pipe, duct, or electrical connections to
equipment.
C. Access for Speed Measurement: 25 mm (one inch) diameter hole at each shaft
center.
2. 16 FIRESTOPPING
Section 07841 specifies an effective barrier against the spread of fire, smoke and gases
where penetrations occur for piping and ductwork. Refer to Section 15080, for firestop pipe
and duct insulation.
A. Furnish, and turn over to the Consultant, special tools not readily available
commercially, that are required for disassembly or adjustment of equipment and
machinery furnished.
B. Grease Guns with Attachments for Applicable Fittings: One for each type of grease
required for each motor or other equipment.
C. Tool Containers: Hardwood or metal, permanently identified for intended service and
mounted, or located, where directed by the Consultant.
D. Lubricants: A minimum of 0.95 L (one quart) of oil, and 0.45 kg (one pound) of
grease, of equipment manufacturer's recommended grade and type, in unopened
containers and properly identified as to use for each different application.
. Page 11 of 18
DIVISION 15 – MECHANICAL Basic Mechanical Materials and Methods SECTION 15050
PART 3 - EXECUTION
C. Excavation and backfill required for Division 15 work inside the building and to a point
1.5 m outside building shall be carried out by the Division listed in the following
schedule:
1. Excavation:
Initial excavation to 150 mm above pipe inverts Division 2
D. Ensure that excavation work is executed to attain required inverts and grades.
E. Remove material excavated by Division 15 and not to be reused, from the site.
F. Carefully prepare the bottom of pipe trench. Use one of the following bedding
methods:
1. In firm undisturbed soil, lay pipe directly on the soil and shape soil to fit the
lower 1/3 segment of pipe and fittings.
2. In rock, shale and where noted, excavate to 150 mm below and minimum 200
mm on each side of pipe. Form a 150 mm thick bedding using 10 mm
crushed stone. Provide continuous support over at least the lower 1/3
segment of pipe.
3. In unstable soil, in fill and where soil has been disturbed during previous
excavation work, excavate to at least 150 mm below bottom of pipe and form
a reinforced concrete cradle supporting full length between firm support, or
install piers down to undisturbed solid soil. Piers shall be at a maximum
spacing of 2400 mm. Provide at least one pier for each pipe length. Support
over at least the lower 1/3 segment of pipe.
G. Where excavation is necessary close to and below the level of any footing, backfill
with 14,000 kPa concrete to the level of the highest adjacent footing. Do not proceed
with the work prior to receiving written approval from Consultant.
A. Locate distribution systems, equipment and materials for maximum usable space,
optimum service clearances and to accommodate current requirements and identified
future expansion.
. Page 12 of 18
DIVISION 15 – MECHANICAL Basic Mechanical Materials and Methods SECTION 15050
C. Include all pipe and duct offsets required to eliminate interference with the work of
other Divisions.
D. Install equipment and materials to present a neat appearance. Run piping, ducts and
conduit parallel to or perpendicular to building planes. Conceal piping, ducts and
conduit in finished areas. Install so as to require a minimum amount of furring.
E. Install pipe, duct and conduit straight, parallel and close to walls and slab or deck
underside, with specified pitch.
F. Use standard fittings for all direction changes. Do not use drilled tees and other field
fabricated fittings.
G. Install eccentric reducers in horizontal piping to permit drainage and eliminate air
pockets.
H. Where pipe sizes differ from connection sizes of equipment, provide reducing fittings
between inline components such as valves, strainers and fittings, and equipment.
Reducing bushings are not permitted.
J. Lay copper tubing so that it is not in contact with dissimilar metal and will not kink or
collapse.
K. Use non-corrosive lubricant or teflon tape equal to Dow Corning and apply on male
thread.
L. Provide brass adaptors or dielectric couplings wherever dissimilar metals are joined.
N. Ensure that pipe installation does not transmit vibration to the walls and floors through
which they pass.
O. Make provisions for neat insulation finish around equipment and materials. Do not
mount equipment within insulation depth.
P. Provide, in electrical rooms and elevator machine rooms, drip trays under the entire
length of pipe within the confines of the room. Pipe drip tray to nearest floor drain.
B. Install unions in piping up to and including 50 mm pipe size. Install flanges in piping
65 mm pipe size and larger.
. Page 13 of 18
DIVISION 15 – MECHANICAL Basic Mechanical Materials and Methods SECTION 15050
C. Prevent galvanic corrosion by isolating copper and steel. Use red brass adapters, or
completely isolate flanges using full face gaskets with bolts installed through phenolic
sleeves with insulating fibre washers. Where the Plumbing Code prohibits the use of
red brass adapters, use insulating couplings. Where system valves are required,
solid brass isolating valves may be used in lieu of adapters or couplings.
D. Provide metallic code rated continuity link between flanges or unions, where pipe
mains carry flammable fluids or gases.
E. Make all plumbing and sheet metal connections to equipment provided by the Owner.
3.4 INSERTS
B. Properly locate and firmly secure inserts to forms before concrete is poured.
C. Place inserts only within main structure and not in any finishing materials.
D. When inserts are required in precast concrete, supply inserts and location drawings to
the precast concrete supplier for casting into material. Otherwise, include the cost of
having the precast concrete supplier install inserts at the site.
3.5 HANGERS
A. Suspend piping, ductwork and equipment with all necessary hangers and supports
required for a safe and neat installation. Ensure that pipes are free to expand and
contract and are graded properly. Adjust each hanger to take its full share of the
weight.
B. Suspend hanger rods directly from the structure. Do not suspend pipes, ducts or
equipment from other pipes, ducts, equipment, metal work or ceilings.
C. Provide auxiliary structural steel angles, channels and beams where ductwork, piping
and equipment must be suspended between joists or beams.
D. Use galvanized rods, steel support angles, channels and beams where exposed to
direct contact with water or to possible high humidity conditions where condensation
can occur.
E. Space hangers to ensure that structural steel members are not over stressed. In no
case shall pipe hangers be further apart than indicated in the tables. When
requested, submit detailed drawings showing locations and magnitude of ductwork,
piping and equipment loads on the structure. Provide calculations when requested by
Consultant.
F. Do not use trapeze type hangers for support of piping, without prior review by
Consultant. Where permitted, fabricate from angle or channel frames, and space
hangers to suit the smallest pipe size.
H. For precast concrete work, if inserts cannot be cast into members, pass hanger rods
between the members and weld to steel plates resting on the upper surface of the
precast material. To prevent raising of the hanger rod, apply a lock nut and 50 mm
minimum dia. flat washer tight against the under surface of the precast material.
. Page 14 of 18
DIVISION 15 – MECHANICAL Basic Mechanical Materials and Methods SECTION 15050
I. Ensure that copper materials are completely isolated from ferrous materials. Use
plastic or epoxy coated hangers and clamps, or use lead inserts between copper
piping and ferrous materials, and between copper piping and copper coated ferrous
materials.
K. The following table establishes minimum standards of rod sizes and hanger spacing
for steel and copper piping.
Maximum Horizontal
Spacing of Supports
12 10 1.5 1.5
20 10 1.8 1.8
25 10 1.8 1.8
32 10 2.4 2.1
40 10 2.7 2.4
50 10 2.7 2.7
65 12 3.0 3.0
75 12 3.0 3.0
90 12 3.0 3.3
100 16 3.0 3.7
125 16 3.7 3.7
150 20 3.7 3.7
200 22 3.7
250 22 3.7
300 22 3.7
350 25 3.7
400 25 3.7
450 29 3.7
500 32 3.7
600 32 3.7
1. to eliminate vibration
N. Support horizontal cast iron soil pipe at each hub. Where groups of fittings occur, not
more than three joints shall be between hangers.
. Page 15 of 18
DIVISION 15 – MECHANICAL Basic Mechanical Materials and Methods SECTION 15050
Q. Support vertical duct risers at each floor with rolled angle collars bearing on building
structure.
A. Set sleeves for piping and ductwork in conjunction with erection of floors and walls.
Locate sleeves accurately in accordance with submittal drawings, and as follows:
1. Through interior walls, set sleeves flush with finished surfaces on both sides.
2. Through exterior walls above grade, set sleeves flush with finished surfaces
on inside and to suit flashing on outside.
D. Provide continuous insulation runs through fire separations. Ensure that piping and
ductwork do not touch sleeves.
E. Pack clearance spaces with Rectorseal Metacaulk Firestopping materials strictly as
recommended by the manufacturer.
F. Install leak tight seals to meet the manufacturer's requirements. Select the inside
diameter of each wall sleeve opening to fit the pipe and leak tight seal, all to ensure
watertight joint.
1. Provide sleeves for systems not part of Contract, but identified to be required
on Drawings.
. Page 16 of 18
DIVISION 15 – MECHANICAL Basic Mechanical Materials and Methods SECTION 15050
A. Make provision for pipe expansion, contraction and building shrinkage with suitable
anchors and offsets or expansion loops.
B. Install piping to allow freedom of movement in all planes without imposing undue
stress on any section of main piping, branch piping, equipment and structure.
C. Use offsets at takeoffs to fans, fan coil units, pipe risers and other branch lines.
D. Select expansion joints for the calculated movement according to the following
temperature ranges.
1. For cold pipes, from minimum operating temperature to 38 deg C, plus 25%
safety factor.
2. For warm and hot pipes, from minimum ambient, but not lower than -5 deg C,
to maximum operating temperature plus 25% safety factor.
H. During the construction and warranty periods, regularly review provisions for building
shrinkage and make necessary adjustments to piping to ensure freedom from binding
and stress.
A. Install pipe guides for expansion joints according to expansion joint manufacturer's
published recommendations. Use at least two guides on each side of expansion joint.
C. Install vertical risers properly anchored and guided to maintain accurate vertical
position of piping. At time of startup, clean and lubricate guides, and adjust to allow
free sliding at operating conditions.
D. For piping up to and including 75 mm, guide pipes at every floor or every 3900 mm.
Guide larger pipes at every second floor or every 7500 mm.
F. Secure anchors to the structure. Avoid introduction of excessive reactive forces and
operating weights into the structure and onto equipment and piping.
G. Where guides are provided on cold piping, provide thermal break to prevent sweating.
3.9 PAINTING
A. Supply ferrous metal work except piping and galvanized and stainless steel ductwork,
with at least one factory prime coat, or paint one prime coat on job.
. Page 17 of 18
DIVISION 15 – MECHANICAL Basic Mechanical Materials and Methods SECTION 15050
B. Clean and steel brush surfaces with welds. Then prime coat all steel supports and
brackets.
D. Touchup or repaint all surfaces damaged during shipment or installation and leave
ready for finish painting.
A. Belt Drive: Set driving and driven shafts parallel and align so that the corresponding
grooves are in the same plane.
B. Direct-connect Drive: Securely mount motor in accurate alignment so that shafts are
free from both angular and parallel misalignment when both motor and driven
machine are operating at normal temperatures.
3.11 LUBRICATION
Field check and lubricate equipment requiring lubrication prior to initial operation.
A. Prior to the final inspection, perform required tests as specified in Section 15010,
Article, Tests and submit the test reports and records to the Consultant.
C. When completion of certain work or system occurs at a time when final control
settings and adjustments cannot be properly made to make performance tests, then
make performance tests for heating systems and for cooling systems respectively
during first actual seasonal use of respective systems following completion of work.
END OF SECTION
. Page 18 of 18
DIVISION 15 – MECHANICAL Motors, Starters, Control Centers and Wiring SECTION 15055
SECTION 15055
MOTORS, STARTERS, CONTROL CENTERS AND WIRING
PART 1 - GENERAL
B. Provide all labour, materials, products, equipment and services to supply and
install the motors, starters, control centres and wiring indicated on the
Drawings and specified in this Section of the Specification.
The Publications listed below form a part of this specification to the extent referenced.
Publications are referenced in the text by basic designation only.
A. IEEE 112 B - Test procedure for Polyphase Induction Motors and Generators
C. UL-B45
D. NEMA 1652-322
1.4 SUBMITTALS
A. Submit shop drawings and manufactures’ data for the following items in
accordance with the conditions of the contract.
4. Include full load heat rejection in BTU per hour for total components by
control center.
Page 1 of 9
DIVISION 15 – MECHANICAL Motors, Starters, Control Centers and Wiring SECTION 15055
PART 2 - PRODUCTS
2.1 MOTORS
A. Provide Westinghouse,
Provide approved by theGE
Architect/Engineer,
or U.S. Electric, 60 cycle, 1800 rpm for 4P motors,
except where noted, with the following characteristics:
B. High efficiency motors (per NEMA Standard) shall be provided and shall be
compatible with standard motor frames.
C. All motors 1.0 kW and over, unless specified differently, shall be T-frame, A.C.
Three Phase and equal to Motor Efficiency Level as tested to the most recent
issue of IEEE 112B.
E. The minimum requirement for 3 phase motors shall be NEMA Design B, Class
B insulated for maximum 40 deg C ambient.
Page 2 of 9
DIVISION 15 – MECHANICAL Motors, Starters, Control Centers and Wiring SECTION 15055
1. Open dripproof, 1.15 service factor for motors protected from the
weather and moisture entertainment to operate satisfactorily at
maximum temperature and moisture levels of surrounding air for
motors located in air streams.
2. Totally enclosed fan cooled 1.15 service factor for motors in all other
locations, including cooling towers.
H. Equip motors 18 kW and larger, as well as those smaller but with longer than
10 second starting time, with inherent overheat protection, consisting of
thermistors, one for each phase, embedded in the stator windings. Extend
wires out to motor terminal box, ready for field wiring into the starter holding
coil circuit. Provide manual reset tripping device compatible with starter.
5. Must be capable of running at 10% full rated speed with the VSD
output provided by the drives supplied under Section 15075.
J. Two speed motors shall be, single winding, variable torque high and low
speed. Provide starter to suit motor requirements.
A. Starters and contactors factory built into the control panel of packaged
equipment will be considered as an integral part of the package and may be
from a different manufacturer.
1. Magnetic Motor Starters shall be for general purpose, Class A and for
induction motors rated in horsepower.
Page 3 of 9
DIVISION 15 – MECHANICAL Motors, Starters, Control Centers and Wiring SECTION 15055
10. Provide transformer type indicating lights in from cover (Lens color(s)
red-stop, green run) and push to test type indicating lights.
A. General
Page 4 of 9
DIVISION 15 – MECHANICAL Motors, Starters, Control Centers and Wiring SECTION 15055
B. Construction
3. Provide a separate, formed, heavy sheet door for each control unit.
Doors secured to the vertical section frame by screw-fastened,
concealed hinges and bolted door fasteners, capable of being
tightened by hand or screwdriver. Door to be gasketed dust-tight all
around, including disconnect operating handles and knockouts and
opening for required pushbuttons, selector switches and indicating
lights. Do not attach wiring to door.
Page 5 of 9
DIVISION 15 – MECHANICAL Motors, Starters, Control Centers and Wiring SECTION 15055
6. Provide control center with facilities for future field installation of motor
controller units without requiring modification of the bus structures.
9. Provide factory wired terminal strips for all required field connections at
top of each vertical section.
C. Buswork
1. Horizontal bus sized as indicated, but not less than 600 amperes.
Provide bus supports of high-quality insulators with high dielectric
strength low moisture absorption, and high impact strength, so
arranged and secured to bus as to provided the required short-circuit
bracing and integrated equipment rating.
2. Bus bars shall be arranged throughout A-B-C left to right, top to bottom
and front to rear. Where special circuiting precludes this arrangement
has accepted by the Architects/Engineers bus bars shall be
permanently labelled.
Page 6 of 9
DIVISION 15 – MECHANICAL Motors, Starters, Control Centers and Wiring SECTION 15055
5. Horizontal bus shall be full size, tapered bus is not permitted. Provide
bolt holes drilled and tapped for future expansion at the end of
horizontal bus bars including neutral and ground bus. The provisions
shall include bus bars installed and extended to the extreme side of
the section and be fabricated in such a fashion that the addition of a
future section would require only the installation of standard bolted
splice plates.
D. Grounding
E. Motor Controllers
Page 7 of 9
DIVISION 15 – MECHANICAL Motors, Starters, Control Centers and Wiring SECTION 15055
PART 3 - EXECUTION
A. Provide conduit and wiring materials and methods in strict accordance with
Division 16 requirements.
C. Provide all power wiring from load side of starters and contactors required for
Division 15 work.
D. Sizing for starters and wiring shall meet requirements of the Electrical Code.
E. Provide control wiring for all equipment provided or supplied under Division
15.
F. Provide control wiring between kitchen exhaust hood control box and exhaust
fan starter.
I. Refer to Division 16, for all line side power wiring to loose starters, MCCs and
Contactors.
J. Refer to Division 16, for normal and emergency power service locations.
Provide power wiring for electrical tracing, controls and elsewhere where
required.
Page 8 of 9
DIVISION 15 – MECHANICAL Motors, Starters, Control Centers and Wiring SECTION 15055
K. Power wiring and control wiring connected to life safety equipment shall utilize
fire rated cable. (Wiring located in room where equipment is located shall not
be fire rated.)
A. Place warning notices at each starter and on or close to each motor under
BMS control.
B. Provide conspicuous notices with bold lettering and advising that the motor is
under BMS control and may start at any time without warning. Submit notices
at the shop drawing stage for Consultant review.
END OF SECTION
Page 9 of 9
DIVISION 15 – MECHANICAL Mechanical Vibration and Seismic Control SECTION 15071
SECTION 15071
MECHANICAL VIBRATION AND SEISMIC CONTROL
PART 1 - GENERAL
1.1 DESCRIPTION
Noise criteria, seismic restraints for equipment, vibration tolerance and vibration isolation for
HVAC Works.
B. Noise Criteria:
1. Noise levels in all 8 octave bands due to equipment and duct systems shall
not exceed following NC levels:
NC CRITERIA
TYPE OF SPACE
(NC) LEVEL
. Page 1 of 9
DIVISION 15 – MECHANICAL Mechanical Vibration and Seismic Control SECTION 15071
7. For equipment which has no sound power ratings scheduled on the plans,
the contractor shall select equipment such that the foregoing noise criteria,
local ordinance noise levels, and OSHA requirements are not exceeded.
Selection procedure shall be in accordance with ASHRAE Fundamentals
Handbook 2001, Chapter 7, Sound and Vibration.
1. Equipment:
1.4 SUBMITTALS
1. Vibration isolators:
a. Floor mountings
b. Hangers
c. Snubbers
d. Thrust restraints
2. Bases.
4. Acoustical enclosures.
. Page 2 of 9
DIVISION 15 – MECHANICAL Mechanical Vibration and Seismic Control SECTION 15071
B. Isolator manufacturer shall furnish with submittal load calculations for selection of
isolators, including supplemental bases, based on lowest operating speed of
equipment supported.
C. Seismic Requirements: Submittals are required for all equipment anchors, supports
and seismic restraints. Submittals shall include weights, dimensions, standard
connections, and manufacturer's certification that all specified equipment will
withstand seismic Lateral Force requirements as shown on the documents.
The publications listed below form a part of this specification to the extent referenced. The
publications are referenced in the text by the basic designation only.
PART 2 – PRODUCTS
A. Type of isolator, base, and minimum static deflection shall be as required for each
specific equipment application as recommended by isolator or equipment
manufacturer but subject to minimum requirements indicated herein and in the
schedule on the drawings.
B. Elastometric Isolators shall comply with ASTM D2240 and be oil resistant neoprene
with a maximum stiffness of 60 durometer and have a straight-line deflection curve.
. Page 3 of 9
DIVISION 15 – MECHANICAL Mechanical Vibration and Seismic Control SECTION 15071
stops to resist wind velocity. Comply with the design wind velocity of 125 mph (200
kmph).
D. Uniform Loading: Select and locate isolators to produce uniform loading and
deflection even when equipment weight is not evenly distributed.
E. Color code isolators by type and size for easy identification of capacity.
A. Bolt pad mounted equipment, without vibration isolators, to the floor or other support
using ASTM A307 standard bolting, material or equal.
B. Floor mounted equipment, with vibration Isolators: Type SS. Where Type N isolators
are used provide channel frame base horizontal restraints bolted to the floor, or other
support, on all sides of the equipment Size and material required for the base shall be
as recommended by the isolator manufacturer.
C. On all sided of suspended equipment, provide bracing for rigid supports and provide
restraints for resiliently supported equipment. The slack cable restraint method,
Mason Industries, or equal, is acceptable.
A. Floor Mountings:
b. All mountings shall have leveling bolts that must be rigidly bolted to
the equipment. Spring diameters shall be no less than 0.8 of the
compressed height of the spring at rated load. Springs shall have a
minimum additional travel to solid equal to 50 percent of the rated
deflection. Mountings shall have ports for spring inspection. Provide
an all directional neoprene cushion collar around the equipment bolt.
3. Spring Isolators with Vertical Limit Stops: Similar to spring isolators noted
above, except include a vertical limit stop to limit upward travel if weight is
removed and also to reduce movement and spring extension due to wind
loads. Provide clearance around restraining bolts to prevent mechanical short
circuiting. Isolators shall have a minimum seismic rating of one G.
. Page 4 of 9
DIVISION 15 – MECHANICAL Mechanical Vibration and Seismic Control SECTION 15071
4. Seismic Pad: Pads shall be felt, cork neoprene waffle, neoprene and cork
sandwich, neoprene and fiberglass, neoprene and steel waffle, or reinforced
duck and neoprene, with steel top plate and drilled for an anchor bolt.
Washers and bushings shall be reinforced duck and neoprene. Size pads for
a maximum load of 345 kPa (50 pounds per square inch).
B. Hangers: Shall be combination neoprene and springs unless otherwise noted and
shall allow for expansion of pipe.
4. Spring: Vibration hanger shall contain a coiled steel spring in series with a
neoprene grommet. Spring shall have a diameter not less than 0.8 of
compressed operating spring height. Spring shall have a minimum additional
travel of 50 percent between design height and solid height. Spring shall
permit a 15 degree angular misalignment without rubbing on hanger box.
5. The first four (4) Hanger supports from the vibrating equipment for piping 5
mm (2 nches) and larger shall have a pointer and scale deflection indicator.
C. Snubbers: Each spring mounted base shall have a minimum of four all-directional or
eight two directional (two per side) seismic snubbers that are double acting.
Elastomeric materials shall be shock absorbent neoprene bridge quality bearing
pads, maximum 60 durometer, replaceable and have a minimum thickness of 6 mm
(1/4 inch). Air gap between hard and resilient material shall be not less than 3 mm
(1/8 inch) nor more than 6 mm (1/4 inch). Restraints shall be capable of withstanding
design load without permanent deformation.
. Page 5 of 9
DIVISION 15 – MECHANICAL Mechanical Vibration and Seismic Control SECTION 15071
inch) when the fan starts and stops. Restraint assemblies shall include rods, angle
brackets and other hardware for field installation.
2.4 BASES
A. Rails: Design rails with isolator brackets to reduce mounting height of equipment and
cradle machines having legs or bases that do not require a complete supplementary
base. To assure adequate stiffness, height of members shall be a minimum of 1/12 of
longest base dimension but not less than 100 mm (4 inches). Where rails are used
with neoprene mounts for small fans or close coupled pumps, extend rails to
compensate overhang of housing.
B. Integral Structural Steel Base: Design base with isolator brackets to reduce mounting
height of equipment which require a complete supplementary rigid base. To assure
adequate stiffness, height of members shall be a minimum of 1/12 of longest base
dimension, but not less than 100 mm (four inches).
C. Inertia Base: Base shall be a reinforced concrete inertia base. Pour concrete into a
welded steel channel frame, incorporating prelocated equipment anchor bolts and
pipe sleeves. Level the concrete to provide a smooth uniform bearing surface for
equipment mounting. Provide grout under uneven supports. Channel depth shall be a
minimum of 1/12 of longest dimension of base but not less than 150 mm (six inches).
Form shall include 13-mm (1/2-inch) reinforcing bars welded in place on minimum of
203 mm (eight inch) centers running both ways in a layer 40 mm (1-1/2 inches) above
bottom. Use height saving brackets in all mounting locations. Weight of inertia base
shall be equal to or greater than weight of equipment supported to provide a
maximum peak-to-peak displacement of 2 mm (1/16 inch).
D. Curb Mounted Isolation Base: Fabricate from aluminum to fit on top of standard curb
with overlap to allow water run-off and have wind and water seals which shall not
interfere with spring action. Provide resilient snubbers with 6 mm (1/4 inch) clearance
for wind resistance. Top and bottom bearing surfaces shall have sponge type weather
seals. Integral spring isolators shall comply with Spring Isolator (Type S)
requirements.
Provide if necessary to meet the required NC criteria at no additional cost to the Owner.
Enclosures shall be removable and sectional, of a size and weight that sections can be
readily handled with typical lifting and moving equipment available in the equipment room.
Enclosures must contain access openings, observation ports, lights, and ventilation where
required for normal operation, observation and servicing.
. Page 6 of 9
DIVISION 15 – MECHANICAL Mechanical Vibration and Seismic Control SECTION 15071
All vertical risers subjected to thermal expansion and/or contraction shall be supported by
spring isolators and central anchors designed to insure loading within design limits at
structural support points. The riser design must be prepared and submitted for approval by
the same isolation vendor supplying the HVAC mechanical equipment isolation and must
include the initial load, initial deflection, change in deflection, final load and change in load at
all spring support locations. In order to minimize load changes, the initial spring deflection
must be at least 4 times the thermal movement. The submittal must also include anchor loads
when installed, cold filled, and at operating temperature. Include calculated pipe stress at end
conditions and branch off locations as well as installation instruction. The submittal must be
stamped and signed by a licensed professional engineer in the employ of the vibration vendor
for at least five years.
The support spring mounts shall be Type SLF, anchors Type ADA, telescoping guides Type
VSG, all as manufactured by Mason Industries, Inc.
The isolation vendor shall provide and design all brackets at riser spring and anchor locations
where standard clamps lack capacity or do not fit. The contractor must install and adjust all
isolators under the supervision of the designing isolation vendor or his representative.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Vibration Isolation:
5. Extend bases for pipe elbow supports at discharge and suction connections
at pumps. Pipe elbow supports shall not short circuit pump vibration to
structure.
. Page 7 of 9
DIVISION 15 – MECHANICAL Mechanical Vibration and Seismic Control SECTION 15071
B. Inspection and Adjustments: Check for vibration and noise transmission through
connections, piping, ductwork, foundations, and walls. Adjust, repair, or replace
isolators as required to reduce vibration and noise transmissions to specified levels.
3.2 ADJUSTING
A. Adjust vibration isolators after piping systems are filled and equipment is at operating
weight.
C. Attach thrust limits at centerline of thrust and adjust to a maximum of 1/4inch (6-mm)
movement during start and stop.
F. Adjust seismic restraints to permit free movement of equipment within normal mode
of operation.
2 HP AND OVER
500 - 750 RPM --- S 2.5
750 RPM & OVER --- S 2.5
PUMPS
UP --- D,L, ---
TO W
CLOSE 1-/2
COUPLED HP
. Page 8 of 9
DIVISION 15 – MECHANICAL Mechanical Vibration and Seismic Control SECTION 15071
2 HP I S 2”
&
BASE OVE
MOUNTED R
I S 2”
I S 2”
I S 2.5
ROOF VENTILATORS
END OF SECTION
. Page 9 of 9
DIVISION 15 – MECHANICAL Mechanical Insulation SECTION 15080
SECTION 15080
MECHANICAL INSULATION
PART 1 – GENERAL
1.1 DESCRIPTION
A. Field applied insulation for thermal efficiency and condensation control for
B. Definitions
2. Air conditioned space: Space directly supplied with heated or cooled air.
8. Density: Kcm - kilograms per cubic meter (Pcf - pounds per cubic foot).
a. Flat surface: Watt per square meter (BTU per hour per square foot).
b. Pipe or Cylinder: Watt per square meter (BTU per hour per linear
foot).
11. Thermal Conductivity (k): Watt per meter, per degree C (BTU per inch
thickness, per hour, per square foot, per degree F temperature difference).
Page 1 of 14
DIVISION 15 – MECHANICAL Mechanical Insulation SECTION 15080
B. Criteria:
b. Closure systems for use with rigid and flexible air ducts tested in
accordance with UL 181, Standard for Safety Factory-Made Air Ducts
and Air Connectors, shall have been tested and listed in accordance
with UL 181A, Standard for Safety Closure Systems for Use with
Rigid Air Ducts and Air Connectors, or UL 181B, Standard for Safety
Closure Systems for Use with Flexible Air Ducts and Air Connectors,
and used in accordance with the conditions of their listings.
c. 2-3.3.2 Air duct, panel and plenum coverings and linings and pipe
insulation and coverings shall not flame, glow, smolder, or smoke
when tested in accordance with a similar test for pipe coverings;
ASTM C 411, Standard Test Method for Hot-Surface Performance of
High-Temperature Thermal Insulation at the temperature to which
they are exposed in service. In no case shall the test temperature be
below 250 degrees F (121 degrees C)
d. 2-3.3.3 Air duct coverings shall not extend through walls or floors that
are required to be fire stopped or required to have a fire resistance
rating.
Page 2 of 14
DIVISION 15 – MECHANICAL Mechanical Insulation SECTION 15080
h. 3-4.6.4 Where air ducts pass through walls, floors or partitions that
are required to have a fire resistance rating and where fire dampers
are not required, the opening in the construction around the air duct
shall be as follows:
4. All materials shall be compatible and suitable for service temperature, and
shall not contribute to corrosion or otherwise attack surface to which applied
in either the wet or dry state.
The insulation thickness indicated in the technical specifications are the minimum
thickness to be provided, regardless of whether the performance specifications
specified below are being met or not.
The temperature rise due to heat gain in the piping system from the source
(chiller) to the farthest AHU/FCU or any point in the piping system shall not
exceed 1.11ºC (2ºF) CHW temperature from the chiller is 5.56ºC (42ºF).
The insulation thickness and also the workmanship shall be such that the CHW
distribution system (equipment, piping, accessories) shall not have any
Page 3 of 14
DIVISION 15 – MECHANICAL Mechanical Insulation SECTION 15080
condensation at any part and portion thereof, or at any worst case operating
condition including that of ambient.
1.4 SUBMITTALS
B. Shop Drawings:
C. Samples:
2. Each type of facing and jacket: Minimum size 100 mm (4 inches square).
The publications listed below form a part of this specification to the extent referenced. The
publications are referenced in the text by basic designation only.
Page 4 of 14
DIVISION 15 – MECHANICAL Mechanical Insulation SECTION 15080
181 - Standard for Safety Factory -Made Air Ducts and Air
Connectors
Page 5 of 14
DIVISION 15 – MECHANICAL Mechanical Insulation SECTION 15080
F. British Standards
G. DIN Standards
PART 2 - PRODUCTS
A. Fed. Spec. HH-B-100 for Vapor Barrier Type I and II: The mold and mildew test
requirement is waived.
1. Type I, low vapor transmission (0.02 perm rating), Beach puncture 50 units:
Use for insulation facing on exposed ductwork, casings and equipment, and
for pipe insulation jackets. Facings and jackets shall be white all service
(ASJ) suitable for painting without sizing.
3. Presized Glass Cloth Jacket, Beach puncture 100 units: Not less than 240
grams per square meter (7.8 ounces per square yard), with integral vapor
barrier where required; for use where specified and in lieu of Type I and Type
II jacket at the Contractor’s option.
4. Factory composite materials may be used provided that they have been
tested and certified by the manufacturer, and witnessed by the authority
having jurisdiction to meet Beach puncture units specified above. Witnessing
of the test may be waived by the authority having jurisdiction.
5. Fire and smoke treatment of jackets and facings shall be permanent. The use
of soluble treatments is not acceptable.
7. PVC Jackets (for indoor CHW Piping): Shall be according to Fed. Spec. L-P-
535, Composition A, Type II, Grade GU. One-piece premolded plastic covers
for fittings, flanges, and valves are limited to indoor piping only.
Page 6 of 14
DIVISION 15 – MECHANICAL Mechanical Insulation SECTION 15080
1. Sheet aluminum: ASTM B209, 3003 alloy, H-14 temper, 0.4 mm (0.016 inch)
thick. Provide moisture barrier lining for service temperature 16 ºC (60 ºF) or
less except where applied over a Type I or II jacket. Longitudinal lap shall be
at least 50 mm (2 inches) wide. For service temperature 16 ºC (60 ºF) or less,
seal all jacket laps in accordance with Mil. Spec. MIL-C-19565, Type II
Coating.
2. Fitting covers: Factory fabricated from not lighter than 0.5 mm (0.020 inch)
thick type 3003 sheet aluminum.
A. Closed-cell polyolefin foam insulation may be provided for ductwork in lieu of mineral
fiber insulation. Insulation efficiency of polyolefin foam must not be less than that of
the specified thickness of mineral fiber insulation, where thickness of polyolefin foam
insulation is not specified.
B. Electron Beam (Physically) Crosslinked, closed cell Polyolefin foam with factory
applied reinforced aluminum foil and acrylic adhesive backing, 25kg/m³ density,
maximum 0.032 W/mK @ 20ºC, non-hydroscopic, water vapor permeability better
than 0.8gm/m²/24hrs (90% RH, 38 ºC), -80 to 100 ºC, service temperature, Class O
fire rating according to BS 476 parts 6 & 7.
a. 25mm (1 inch) complete with foil adhesive and aluminum foil: Supply
air ducts exposed to ambient, unlined air handling units, and final
filter housing. 19mm (3/4 inch) thick for above ceiling below roof deck
areas (supply and return).
b. 19mm (3/4 inch) thick complete with foil adhesive and aluminum foil
in mixed air plenums and pre-filter housing and to all supply and
return air ducts other than the above.
A. Note the NFPA 90A building characteristic requirements of 25/50 in paragraph 1.3.B.
Refer to paragraph 3.1 for items not to be insulated.
B. ASTM C612 (Board, Block), Class 1 or 2, K = 0.037 Watt per meter, per degree C
(0.26 BTU-in/ft² hr ºF), external insulation for temperatures up to 204 ºC (400 ºF).
Page 7 of 14
DIVISION 15 – MECHANICAL Mechanical Insulation SECTION 15080
2. Pipe and duct penetrations requiring fire stop insulation including, but not
limited to the following:
2.4 FLEXIBLE CLOSED CELL ELASTOMERIC RUBBER INSULATION (BASE OFFER FOR PIPING)
A. ASTM C534, k = 0.033 Watt per meter, per degree C (0.27), flame spread not over
25, smoke developed not over 50, for temperatures from minus 4 degrees C (40
degrees F) to 93 degrees C (200 degrees F). No jacket required except those
required under item 2.1 B above.
B. Pipe insulation: Nominal thickness in millimeters (inches are specified in table below
for piping above ground:
Page 8 of 14
DIVISION 15 – MECHANICAL Mechanical Insulation SECTION 15080
2. Chillers, insulate any cold chiller surfaces subject to condensation which has
not been factory insulated.
A. General
All chilled water lines shall be pre-insulated type using polyurethane. All straight
sections, fittings, anchors and other accessories shall be factory fabricated. Each
system layout shall be computer analyzed by the piping system manufacturer to
determine stress on the carrier pipe and anticipated thermal movement of the service
pipe. The system design shall in strict conformance with ANSI B31.1, latest edition.
Factory trained field technical assistance shall be provided for critical periods of
installation; unloading, field joint instruction and testing.
B. Service Pipe
Internal Piping shall have similar specifications as in chilled water pipes under
Section 15181. All joints shall be butt-welded for 2 ½ inches and greater, and socket
or butt-welded for 2 inches and below. Where possible, straight sections shall be
supplied in 40-foot random lengths with piping exposed at each end for field joint
fabrication.
C. Accessories
End seals, gland seals and anchors shall be designed and factory fabricated to
prevent the ingress of moisture into the system.
D. Insulation
Service pipe insulation shall be spray applied. 16k-factor, R141B blowing agent,
nominal 2 pound per cubic foot density, polyurethane foam for straight sections and
preformed polyurethane foam for all fittings. To ensure no voids are present, all
insulation shall be inspected by one of the following three methods: visually checked
prior to application of the protective jacket or infrared inspection of the entire length
24 hours after foaming is complete. The insulation shall be applied to the minimum
thickness specified below. The insulation thickness shall not be less than indicated in
these specifications for hot water piping systems:
E. Protective Jacket
F. Field Joints
The internal pipe shall be hydrostatically tested to 1½ times the operating pressure.
Insulation shall then be poured in place into the field weld area. All field applied
insulation shall be placed only in straight sections. Field insulation of fittings shall not
be accessible. The mold for the polyurethane shall be made of clear adhesive
backed polyester film. The installer shall seal the field joint area with a heat
shrinkable adhesive backed wrap or with wrappings of glass reinforcement fully
saturated with a catalyzed resin identical in properties to the factory-applied resin.
Page 9 of 14
DIVISION 15 – MECHANICAL Mechanical Insulation SECTION 15080
Backfilling shall not begin until the heat shrink wrap has cooled. All insulation and
coating materials for making the field joint shall be furnished by the piping system
manufacture.
A. ASTM C533:
Type I Type II
A. Light weight, high temperature mineral fiber of 50mm (2 inches) thick or ceramic
insulating material with low thermal conductivity K value of 0.033 W/m ºC (0.230 Btu
in/hr ft² Fº) at mean temperature of 38 ºC (100 ºF).
C. Material shall be UL tested for internal grease fire to 1093 ºC (2,000 ºF) with zero
clearance and for through-penetration firestop.
D. Provide stainless steel jacket for all exterior and exposed interior ductwork.
E. Material shall be UL classified for 1 hour, 2 hours, fire rating for grease duct
enclosure, and meet NFPA 96 requirements for direct applied insulating material to
grease ducts with zero clearance.
F. Material flame spread and smoke developed ratings shall not be higher than 5, as per
ASTM E 84/UL 723 flammability test.
A. Insulation inserts at pipe supports: Provide for all insulated piping. Install with metal
insulation shields furnished with pipe supports, Section 15050.
1. Material: Premolded, high density mineral fiber blocks, minimum density 320
kcm (20 pcf), of same thickness as adjacent insulation.
Page 10 of 14
DIVISION 15 – MECHANICAL Mechanical Insulation SECTION 15080
1. Mil. Spec. MIL-A-3316, Class 1: Jacket and lap adhesive and protective finish
coating for insulation.
2. Mil. Spec. MIL-A-3316, Class 2: Adhesive for laps and for adhering insulation
to metal surface.
5. Mil. Spec. MIL-C-19565, Type I or Type II: Vapor barrier compound for indoor
use.
C. Mechanical Fasteners:
1. Pins, anchors: Welded pins, or metal or nylon anchors with tin-coated or fiber
washer, or clips. Pin diameter shall be as recommended by the insulation
manufacturer.
3. Wire: 1.3 mm thick (18 gage) soft annealed galvanized, or 1.9 mm (14 gage)
copper clad steel or nickel copper alloy.
4. Bands: 20mm (3/3 inch) nominal width, brass, galvanized steel, aluminum or
stainless steel.
1. Glass Fabric, open weave: ASTM D1668, Type III (resin treated) and Type I
(asphalt treated).
3. Tape for Flexible Unicellular Insulation: Scoth No. 472, Nashua PE-12, or
approved equal recommended by the insulation manufacturer.
4. Hexagonal wire netting: 25 mm (one inch) mesh, 0.85 mm thick (22 gage)
galvanized steel.
Page 11 of 14
DIVISION 15 – MECHANICAL Mechanical Insulation SECTION 15080
6. PVC fitting cover: Fed. Spec. L-P-535, Composition A, 11-86 Type II, Grade
GU, with Form B Mineral Fiber insert, for media temperature ºC (40 ºF) to
121 ºC (250 ºF). Below 4 ºF) and above 121 ºC (250 ºF) provide double layer
insert. Provide color matching, vapor barrier, pressure sensitive tape.
E. Firestopping Material, Other than Pipe and Duct Insulation: Refer to Section 07841.
PART 3 – EXECUTION
A. Required pressure tests of duct and piping joints and connections shall be completed
and the work approved by the Resident Engineer for application of insulation. Surface
shall be clean and dry with all foreign materials, such as dirt, oil, loose scale and rust
removed.
B. Except for specific exceptions, insulate entire specified equipment, piping (pipe,
fittings, valves, accessories), and duct systems. Insulate each pipe and duct
individually. Do not use scrap pieces of insulation where a full length section will fit.
D. Insulation materials shall be installed in a first class manner with smooth and even
surfaces, with jackets and facings drawn tight and smoothly cemented down at all
laps. Insulation shall be continuous through all sleeves and openings, except at fire
dampers and duct heaters (NFPA 90A). Vapor retarders shall be continuous and
uninterrupted throughout systems with operating temperature 16 degrees C (60
degrees F) and below. Lap and seal vapor barrier over ends and exposed edges of
insulation. Anchors, supports and other metal projections through insulation on cold
surfaces shall be insulated and vapor sealed for a minimum length of 150 mm (6
inches).
E. Install vapor stops at all insulation terminations on either side of valves, pumps and
equipment and particularly in straight lengths of pipe insulation.
F. Construct insulation on parts of equipment such as chilled water pumps and heads of
chillers, convertors and heat exchangers that must be opened periodically for
maintenance or repair, so insulation can be removed and replaced without damage.
Install insulation with bolted 1 mm thick (20 gage) galvanized steel or aluminum
covers as complete units, or in sections, with all necessary supports, and split to
coincide with flange/split of the equipment.
1. Internally insulated ductwork and air handling units. Omit insulation on relief
air ducts.
2. Exhaust air ducts and plenums, and ventilation exhaust air shafts, unless
otherwise specified.
Page 12 of 14
DIVISION 15 – MECHANICAL Mechanical Insulation SECTION 15080
1. Faced board: Apply board on pins spaced not more than 300 mm (12 inches)
on center each way, and not less than 75 mm (3 inches) from each edge of
board. In addition to pins, apply insulation bonding adhesive to entire
underside of horizontal metal surfaces. Butt insulation edges tightly and seal
all joints with laps and butt strips. After applying speed clips cut pins off flush
and apply vapor seal patches over clips.
2. Plain board:
a. Insulation shall be scored, beveled or mitered to provide tight joints
and be secured to equipment with bands spaced 225 mm (9 inches)
on center for irregular surfaces or with pins and clips on flat surfaces.
Use corner beads to protect edges of insulation.
b. For hot equipment: Stretch 25 mm (1 inch) mesh wire, with edges
wire laced together, over insulation and finish with insulating and
finishing cement applied in one coat, 6 mm (1/4 inch) thick, trowel led
to a smooth finish.
c. For cold equipment: Apply meshed glass fabric in a tack coat 1.5 to
1.7 square meter per liter (60 to 70 square feet per gallon) of vapor
mastic and finish with mastic at 0.3 to 0.4 square meter per liter (12
to 15 square feet per gallon) over the entire fabric surface.
d. Chilled water pumps: Insulate with removable and replaceable 1 mm
thick (20 gage) aluminum or galvanized steel covers lined with
insulation. Seal closure joints/flanges of covers with gasket material.
Fill void space in enclosure with flexible mineral fiber insulation.
2. All joints should be butted firmly against each other, Seal all joints with 75mm
reinforced aluminum foil tape. No gluing of joints is required.
5. All supporting hangers should be lined with the same insulation material to
avoid excess compression of insulation. (Refer manufacturer’s instructions).
6. Ensure no air pockets during the installation of the insulation to the duct.
Page 13 of 14
DIVISION 15 – MECHANICAL Mechanical Insulation SECTION 15080
1. Wrap pipe or duct with firestop pipe insulation, seal jacket seam and seal and
joints to adjacent sections of insulation.
2. Seal opening between insulation and pipe sleeve with firestopping material.
3. Among pipe and duct penetrations requiring fire stop insulation are the
following:
a. Floor (platform) of interstitial space (ducts and pipes).
b. Pipe risers through mechanical room floors.
c. Pipe or duct chase walls and floors.
d. Smoke partitions.
e. Fire partitions.
END OF SECTION
Page 14 of 14
DIVISION 15 – MECHANICAL Refrigerant Piping SECTION 15183
SECTION 15183
REFRIGERANT PIPING
PART 1 – GENERAL
1.1 DESCRIPTION
A. Field refrigerant piping for direct expansion HVAC systems. Field refrigerant piping
and associated drain and condenser water piping for walk-in refrigerators and
freezers, including required pipe insulation.
B. Definitions:
2. Brazed joint: A gas-tight joint obtained by the joining of metal parts with alloys
which melt at temperatures higher than 427 degrees C (800 degrees F) but
less than the melting temperatures of the joined parts.
D. Section 15181 – Hydronic Piping: Requirements for water and drain piping and valves.
B. Comply with ASHRAE Standard 15, Safety Code for Mechanical Refrigeration. The
application of this Code is intended to assure the safe design, construction,
installation, operation, and inspection of every refrigerating system employing a fluid
which normally is vaporized and liquefied in its refrigerating cycle.
C. Comply with ASME Boiler and Pressure Vessel Code: Section IX: Welding and
Brazing Qualifications.
1.4 SUBMITTALS
Page 1 of 9
DIVISION 15 – MECHANICAL Refrigerant Piping SECTION 15183
b. Valves
c. Strainers
d. Moisture-liquid indicators
e. Filter-driers
g. Liquid-suction interchanges
i. Gages
C. Design Manual: Furnish two copies of design manual of refrigerant valves and
accessories.
The publications listed below form a part of this specification to the extent referenced. The
publications are referenced in the text by the basic designation only.
Page 2 of 9
DIVISION 15 – MECHANICAL Refrigerant Piping SECTION 15183
B16.24 - Cast Copper Alloy Pipe Flanges and Flanged Fittings, Class
150, 300, 400, 600, 900, 1500 and 2500, (Errata-1991, R
(1998)
A126 - Gray Iron Castings for Valves, Flanges and Pipe Fittings.
A5.8 - Standard Specification for Filler Metals for Brazing and Braze
Welding.
GG - G -76 - Gages, Pressure and Vacuum, Dial Indicating (for Air, Steam,
Oil, Water, Ammonia, Chloro-Flouro Hydrocarbon and
Compressed Gases)
Page 3 of 9
DIVISION 15 – MECHANICAL Refrigerant Piping SECTION 15183
PART 2 - PRODUCTS
A. Refrigerant Piping: Copper refrigerant tube, ASTM B280, cleaned, dehydrated and
sealed, marked ACR on hard temper straight lengths. Coils shall be tagged ASTM
B280 by the manufacturer. Or aluminum refrigerant tube, ASTM B75-02 (subject to
extended warranty coverage by aluminum tube supplier).
B. Water and Drain Piping: Copper water tube, ASTM B88, Type M or L, or refrigerant
tube ASTM B280.
3. Refrigeration Valves:
a. Stop Valves: Brass or bronze alloy, packless, or packed type with gas
tight cap, frost proof, backseating.
e. Check Valves: Brass or bronze alloy with swing or lift type, with tight
closing resilient seals for silent operation; designed for low pressure
drop, and with solder-end connections. Direction of flow shall be
legibly and permanently indicated on the valve body.
Page 4 of 9
DIVISION 15 – MECHANICAL Refrigerant Piping SECTION 15183
7. Flexible Metal Hose: Seamless bronze corrugated hose, covered with bronze
wire braid, with standard copper tube ends. Provide in suction and discharge
piping of each compressor.
8. Liquid-Suction Heat Exchanger: Designed for counter flow and for free
drainage of oil. Size shall suit system conditions and refrigerant used.
Interchangers shall be ASME construction or UL listed.
10. Oil Separators: Provide for condensing units, as shown. All welded steel
construction with capacity to eliminate a minimum of 95 percent of the oil from
the hot gas flowing through it. Provide manufacturer's published ratings for
minimum and maximum refrigeration tonnage corresponding to this oil
separating efficiency. Conform to ASHRAE Standard 69. Separator shall be
equipped with a float valve to prevent return of the hot gas to crankcase, and
shall have isolating stop valves so it can be opened and services without
pumping out any other part of the system. ASME construction or UL listed.
11. Receivers: Conform to ARI 495, steel construction, equipped with tappings for
liquid inlet and outlet valves, pressure relief valve and liquid level indicator.
A. Fed. Spec. GG-G-76, Type III (freon), 65 mm (2-l/2 inch) minimum diameter, bottom
connection, one percent accuracy, graduated in kPa gage (psig) and corresponding
refrigerant temperature, with pressure snubber.
B. Provide board-mounted gages of the following ranges for each compressor. Provide
gage shut-off valve.
1. Suction: 101 kPa (30 inches Hg) vacuum to 1723 kPa (gage) (250 psig).
Page 5 of 9
DIVISION 15 – MECHANICAL Refrigerant Piping SECTION 15183
A. Prefabricated Roof Curb: Galvanized steel or extruded aluminum 300 mm (12 inches)
overall height, continuous welded corner seams, treated wood nailer, 40 mm (1-1/2
inch) thick, 48 kg (3 pound) density rigid mineral fiberboard insulation with metal liner,
built-in cant strip (except for gypsum or tectum decks). For surface insulated roof
deck, provide raised cant strip (recessed mounting flange) to start at the upper
surface of the insulation. Curbs shall be constructed for pitched roof or ridge mounting
as required to keep top of curb level.
B. Penetration Cover: Galvanized sheet metal with flanged removable top. Provide 40
mm (1-1/2 inch) thick mineral fiber board insulation.
C. Flashing Sleeves: Provide sheet metal sleeves for conduit and pipe penetrations of
the penetration cover. Seal watertight penetrations.
B. Insulate refrigerant suction piping from unit cooler to condensing unit. Use 20 mm
(3/4-inch) thick insulation on piping inside the refrigerator or freezer and 40 mm (1-1/2
inch) thick insulation (double layer required) on piping outside the refrigerated space.
C. Insulate unit cooler drain piping in freezer units, over electric heat tracing tape, to
prevent drain from freezing during defrost.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Install refrigerant piping and refrigerant containing parts in accordance with ASHRAE
Standard 15 and ANSI B31.5. Refrigerant piping shall be brazed with 15 percent silver
solder in accordance with AWS A5.8.
2. Install piping with adequate clearance between pipe and adjacent walls and
hangers to allow for service and inspection. Space piping, including insulation,
to provide 25 mm (one inch) minimum clearance between adjacent piping or
other surface. Use pipe sleeves through walls, floors, and ceilings, sized to
permit installation of pipes with full thickness insulation.
3. Locate and orient valves to permit proper operation and access for
maintenance of packing, seat and disc. Generally locate valve stems in
overhead piping in horizontal position. Provide a union adjacent to one end of
Page 6 of 9
DIVISION 15 – MECHANICAL Refrigerant Piping SECTION 15183
all threaded end valves. Control valves usually require reducers to connect to
pipe sizes shown on the drawing.
6. Install hangers and supports per ANSI B31.5 and the refrigerant piping
manufacturer's recommendations.
B. Protect refrigerant system during construction against entrance of foreign matter, dirt
and moisture; have open ends of piping and connections to compressors,
condensers, evaporators and other equipment tightly capped until assembly.
C. Pass nitrogen gas through the pipe or tubing to prevent oxidation as each joint is
brazed. Cap the system with a reusable plug after each brazing operation to retain the
nitrogen and prevent entrance of air and moisture.
D. Pipe relief valve discharge to outdoors for systems containing more than 45 kg (100
pounds) of refrigerant.
E. Firestopping: Fill openings around uninsulated piping penetrating floors or fire walls,
with firestop material. For firestopping insulated piping refer to Section 15080.
A. Apply flexible cellular insulation and fabricate fittings in accordance with the
manufacturer's written instructions.
D. Where possible, slip insulation over the pipe or tubing prior to connection, and seal
the butt joints with adhesive. Where the slip-on technique is not possible, slit the
insulation and apply it to the pipe sealing the seam and joints with contact adhesive.
Optional tape sealing, as recommended by the manufacturer, may be employed.
A. Each refrigerating system erected on the premises shall be provided with an easily
legible permanent sign securely attached and easily accessible, indicating thereon the
name and address of the installer, the kind and total number of pounds of refrigerant
required in the system for normal operations, and the field test pressure applied.
B. Systems containing more than 50 kg (110 lb) of refrigerant shall be provided with
durable signs, in accordance with ANSI A13.1 and ANSI Z53.1, having letters not less
than 12.7 mm (0.5 inch) in height designating:
1. Valves and switches for controlling refrigerant flow, the ventilation and the
refrigerant compressor(s).
Page 7 of 9
DIVISION 15 – MECHANICAL Refrigerant Piping SECTION 15183
2. Signs on all exposed high pressure and low pressure piping installed outside
the machinery room, with name of the refrigerant and the letters "HP" or "LP."
Page 8 of 9
DIVISION 15 – MECHANICAL Refrigerant Piping SECTION 15183
Prior to initial operation examine and inspect piping system for conformance to plans and
specifications and ASME 31.5. Equipment, material, or work rejected because of defects or
nonconformance with plans and specifications, and the Contractor shall correct ANSI codes
for pressure piping.
A. After completion of piping installation and prior to initial operation, conduct test on
piping system according to ASME B31.5. Furnish materials and equipment required
for tests. Perform tests in the presence of Consultant. If the test fails, correct defects
and perform the test again until it is satisfactorily done and all joints are proved tight.
2. The high and low side of each system shall be tested and proved tight at not
less than the lower of the design pressure or the setting of the pressure-relief
device protecting the high or low side of the system, respectively, except
systems erected on the premises using non-toxic and non-flammable Group
A1 refrigerants with copper tubing not exceeding 16 mm (0.62 in) O.D. This
may be tested by means of the refrigerant charged into the system at the
saturated vapor pressure of the refrigerant at 20 degrees C (68 degrees F)
minimum.
B. Test Medium: A suitable dry gas such as nitrogen or shall be used for pressure
testing. The means used to build up test pressure shall have either a pressure-limiting
device or pressure-reducing device with a pressure-relief device and a gage on the
outlet side. The pressure relief device shall be set above the test pressure but low
enough to prevent permanent deformation of the system components.
2. Connect a drum of dry nitrogen to charging valve and bring test pressure to
design pressure for low side and for high side. Refer to Article 1.3, QUALITY
ASSURANCE. Test entire system again for leaks.
Page 9 of 9
DIVISION 15 – MECHANICAL Refrigerant Piping SECTION 15183
END OF SECTION
Page 10 of 9
DIVISION 15 – MECHANICAL Fuel Oil Storage Tank, Piping and Accessories SECTION 15191
SECTION 15191
FUEL OIL STORAGE TANK, PIPING AND ACCESSORIES
PART 1 – GENERAL
1.1 DESCRIPTION
2. The design and size of each item of equipment provided for this project is of
current production and has been in satisfactory operation on at least three
installations for approximately three years. Current models of fluid level and
leak detection systems with less than three years service experience are
acceptable if similar previous models from the same manufacturer have at
least three years service experience.
C. All equipment shall be free from defects which would adversely affect the
performance, maintainability and appearance of individual components or overall
assembly.
D. Tanks, Secondary Containment Systems for Piping, Plastic Piping and Containment
Systems, Tank Level Monitoring Systems, Leak Detection Systems, Cathodic
Protection Systems: Authorized manufacturers representatives shall provide on-site
training of installers and supervision of the installation and testing of the equipment
and systems to assure conformance to written instructions of manufacturers.
Page 1 of 11
DIVISION 15 – MECHANICAL Fuel Oil Storage Tank, Piping and Accessories SECTION 15191
E. Tank and piping installation contractor shall be certified as acceptable by local and
pollution control authorities.
H. Assembly of Glass Fiber Reinforced Plastic Piping: Installation personnel shall have
been trained, tested and certified under a procedure approved by the manufacturer of
the piping. Proof of certification, in writing, shall be provided to the CTR or RE.
K. Equipment and materials installed shall be compatible in all respects with other items
being furnished and with existing items so that the result will be a complete and fully
operational system which conforms to contract requirements.
1.4 SUBMITTALS
6. Data certifying tanks are designed for surcharge loads of platforms shown.
B. Fuel Piping:
3. Manufacturer.
Page 2 of 11
DIVISION 15 – MECHANICAL Fuel Oil Storage Tank, Piping and Accessories SECTION 15191
H. Tank and Piping Accessories: Design, construction, and dimensions of vent caps, fill
boxes, fill caps, spill containers and other accessories.
A. Protection of Equipment:
1. Equipment and material placed on the job site shall remain in the custody of
the Contractor until phased acceptance, whether or not the Contractor has
been reimbursed for the equipment and material by the Owner. The
Contractor is solely responsible for the protection of such equipment and
material against any damage.
2. Place damaged equipment in first class, new operating condition; or, replace
same as determined and directed by the Consultant or RE. Such repair or
replacement shall be at no additional cost to the Owner.
3. Protect new equipment and piping systems against entry of foreign matter on
the inside. Clean both inside and outside before painting or placing
equipment in operation.
Page 3 of 11
DIVISION 15 – MECHANICAL Fuel Oil Storage Tank, Piping and Accessories SECTION 15191
3. Clean interior of all tanks prior to delivery for beneficial use by the Owner.
4. Contractor shall be fully responsible for all costs, damages and delay arising
from failure to provide clean systems and equipment.
The publications listed below form a part of this specification to the extent referenced. The
publications are referenced in the text by basic designation only.
A126 - Gray Iron Castings for Valves, Flanges and Pipe Fittings
A234/A234M - ... Piping Fittings of Wrought Carbon Steel and Alloy Steel for
Moderate and High Temperature Service
Page 4 of 11
DIVISION 15 – MECHANICAL Fuel Oil Storage Tank, Piping and Accessories SECTION 15191
1.7 PERMITS
Contractor shall obtain and complete all tank permit and registration forms required by
governmental authorities.
PART - 2 PRODUCTS
B. All piping exposed to the elements or exterior of the building shall be galvanized.
B. For steel piping larger than 12 mm, provide screwed malleable iron fittings rated at
1035 kPa.
2.3 VALVES
A. Provide Crane, Kitz, Nibco, Showa, Toyo or Victaulic valves from one manufacturer,
new, all brass/bronze construction and packed for oil use, to the following Kitz Figure
numbers:
Page 5 of 11
DIVISION 15 – MECHANICAL Fuel Oil Storage Tank, Piping and Accessories SECTION 15191
1. Gate valves 75 mm and smaller, 862 kPa bronze, screwed ends, rising stem,
solid wedge disc, Fig. 24.
2. Globe valves 75 mm and smaller, 862 kPa bronze, union bonnet, screwed
ends with P.T.F.E. disc, Fig. 03.
3. Check valves 75 mm and smaller, 862 kPa bronze, screwed ends, horizontal
swing check, regrinding type, Fig. 22.
4. Ball valves 75 mm and smaller, 1034 kPa, brass or bronze body, two piece,
full port, screwed ends, with chrome plated solid ball, Fig. 58.
B. Provide Jamesbury Type 23-2236MT or equivalent Apollo fuel supply fire safety ball
valve complete with torque handle fusible link; Model LK 500 for 20 mm.
A. Provide standard weight ASTM Specification steel pipe. Weld all joints, except at
connection to muffler discharge pipe where flanges shall be used.
B. Provide 1035 kPa forged steel, welding flange, flanged faced and drilled to conform to
ASA B16.5. Provide asbestos-free high temperature gaskets 1.6 mm thickness.
D. Where piping is exposed to weather, supply two coats of high temperature anti rust
paint.
A. Provide a duplex pumping set, direct driven gear pumps with performance required
on Pump Schedule.
B. Equip each pump with suction and discharge pressure and vacuum gauges,
discharge line globe valve, suction line gate valve, dual check valves, relief valve with
stainless steel trim and piping to return line, thermometer and strainer.
C. Provide under the complete pump set, a stainless steel drip tray with 40 mm upturned
edges.
D. Factory equip pump set with an oil pressure failure switch. Wire to the auto position
of starters to shut off both pumps in the event of oil pressure drop due to oil line
failure, or, increase in pressure due to blockage.
1. Single power source for both fuel oil pumps with main disconnect switch.
2. Individual magnetic starters for each pump with circuit breaker protection.
Page 6 of 11
DIVISION 15 – MECHANICAL Fuel Oil Storage Tank, Piping and Accessories SECTION 15191
7. Auxiliary contacts for BMS use to indicate each pump motor status.
A. Provide storage tanks suitable for under ground mounting located inside or
installation inside a vault of the building (refer to plan for location). Tank shall be
factory tested for a minimum of 5 PSI.
B. Provide tanks with capacity indicated on plans. Provide tanks with manhole access
and connections for piping detailed on the Drawings.
A. Provide diesel fuel day tank complete with support stands. (capacity and location as
shown on plans).
A. Provide Scully Electronic Systems SP-O-E Dynaprobe within Main Storage Tank.
B. Provide Scully Electronic Systems SF-15-LAB Single Point Control Unit in Nema 4
Weatherproof Enclosure with red/green indicating lights, audible high level and alarm
silence pushbutton. Control unit shall incorporate SF-15H module with dynamic self
checking, and high level failsafe feature.
E. Provide engraved nameplate at Controller Location stating "Fill only when green light
is flashing. Stop if red light comes on. Notify Building Engineer."
A. Provide Magnetrol Model 802 Sentinel transmitter with dual D.P.D.T. relays for
high/low level, and 4-20 mA output proportional to level, complete with integral 90
second time delay.
B. Install probe in a 32 mm external oil column with isolation, drain and vent valves.
A. Provide Raycor Turbine Series filter and water separator in the fuel supply line
downstream of the day tank. Assembly shall be 1000 FG (maximum 180 GPH).
Page 7 of 11
DIVISION 15 – MECHANICAL Fuel Oil Storage Tank, Piping and Accessories SECTION 15191
B. Provide a Magnetrol Model 41-5027-XXX shielded capacitance probe and Model 802
Sentinel 4-20 mADC transmitter, with dual DPDT high/low level relays, in the main
fuel oil storage tanks.
PART 3 – EXECUTION
Page 8 of 11
DIVISION 15 – MECHANICAL Fuel Oil Storage Tank, Piping and Accessories SECTION 15191
A. Type: Microprocessor-based systems for central monitoring of fuel and water levels in
all fuel oil storage tanks in the project. High and low level visual and audible alarms.
Volumetric tank-tightness testing. Complete with all transducing, transmitting, and
receiving devices. On board printer to provide complete report of all system functions
upon command. System may be combined with leak detection system specified in
Article, LEAK DETECTION SYSTEMS.
B. Fluid Level Monitor:
1. Digital continuous readout, showing tank oil and water levels in liters,
(smallest reading one liter). Provide identification of product measured,
measuring units, and the tank number.
2. Tank and fuel characteristics contained in preprogrammed non-volatile field-
replaceable databases. Protected power supply.
Page 9 of 11
DIVISION 15 – MECHANICAL Fuel Oil Storage Tank, Piping and Accessories SECTION 15191
Concrete ballast foundations for underground tanks and concrete pads for aboveground tanks
are specified under Section 03300. Ballast foundations shall be sized for buoyancy of entire
tank when empty. Credit for overburden is allowed.
A. Slope fill and vent piping to storage tank. Provide swing joint pipe connections.
B. Terminate the oil tank vent in a manufactured vent fitting similar to OPW catalogue
#45.
A. Provide sufficient fuel to circulate for 48 hours to clean fuel system. Discard
circulated fuel.
B. Fill complete system, including all tanks and piping with fuel oil recommended by
generator manufacturer.
A. Provide all connectors, hangers and brackets required for a satisfactory installation.
Allow for expansion in the vertical and horizontal directions, especially at locations
where pipes pass through roof or wall.
A. Fuel pumps shall be able to run at all times. Fuel shall recirculate from day tank to
main storage tanks.
Page 10 of 11
DIVISION 15 – MECHANICAL Fuel Oil Storage Tank, Piping and Accessories SECTION 15191
B. Wire low level switch on day tank to generator control panel to annunciate low fuel
alarm.
C. Wire high space temperature switch in Generator Room to generator control panel to
annunciate ventilation failure alarm.
D. Field calibrate all level controls. Provide 24 VDC power to level controls, connected
to emergency power source.
E. Provide all wiring and devices necessary to implement the pump and alarm/trouble
controls described in this section.
3.8 TESTING
B. Pressure test exhaust stack at 35 kPa with air. Maintain test pressure for a minimum
of 1 hour.
END OF SECTION
Page 11 of 11
DIVISION 15 – MECHANICAL DX Split System & Window Type Air-Conditioning Units
SECTION 15781
SECTION 15781
DX Split System & Window Type Air-Conditioning Units
PART 1 - GENERAL
A. The provision of all equipment , labor, materials and the performance of all operations in
connection with the supply and installation of packaged and room air conditioners as
specified herein and shown on the drawings.
B. Coordination. The Contractor shall be responsible for proper coordination of the work of
all trades.
A. Manufacturers: Firms regularly engaged in the manufacture of packaged and room air
conditioning equipment and fittings whose products have been in satisfactory use in
similar service for not less than 10 years.
B. Installer: Firms regularly engaged in the installation of packaged and room air
conditioning equipment of a similar quality and scope as this project for at least five
years.
A. The DX Split System and room air conditioners shall comply fully with the latest
relevant American, international and British Standards in all respects.
B. The following are the most commonly used standards associated with packaged air
conditioners, however the Contractor shall ensure that all applicable standards are
complied with, whether listed here or not.
Page 1 of 5
DIVISION 15 – MECHANICAL DX Split System & Window Type Air-Conditioning Units
SECTION 15781
1.5 SUBMITTALS
1.7 WARRANTY
1. Carrier
2. Trane
3. Samsung
4. Mitsubishi
5. Hitachi
6. National
7. LG
8. Midea
Page 2 of 5
DIVISION 15 – MECHANICAL DX Split System & Window Type Air-Conditioning Units
SECTION 15781
PART 2 - PRODUCT
A. Direct Expansion (DX) split system air conditioning units shall be installed as
indicated on the drawings and shall be complete with all required refrigerant piping,
temperature controls and all other necessary ancillary items.
B. The units shall deliver the design cooling capacity at the external ambient specified.
The units are rated at 35°C and shall be suitable for continuous operation with
reduced capacity at an external ambient temperature 40°C.
C. Controls shall be factory wired and completely enclosed within the unit. All operating
controls shall be located in a single area. Adjustable thermostats shall automatically
cycle the compressor to maintain space conditions and the sensing element shall
extend across the complete face of the cooling coil.
Submit data to demonstrate that the units will produce the efficiency rates specified.
1. Window Type Units: Units shall produce not less than 9.5 BTU’s per hour
cooling per watt-input for 230 volts AC units.
E. Exhaust Air
Provisions shall be made in the unit for controlled exhausting of room air and/or the
controlled admittance of fresh air from the unit.
F. Unit Supports
H. Unit electrical power shall be 230 volts three phase, 60 hertz or as indicated on the
drawings. The unit shall be capable of operating within line voltage limits of + 3 % to
-4.6 %.
I. Evaporator and condenser coils shall be of copper tube construction with aluminium
fins and additional anti corrosion coating suitable for salty spray atmosphere.
(“Thermoguard”, “Eroguard”, or equal).
J. Compressor motors shall be two pole, permanent split capacitor type protected
against both thermal and electrical overload.
K. Filters shall be washable type, easily accessible, and shall cover the full unit area of
re-circulated air. Air filter shall be of aluminium wood material and shall have a
minimum efficiency of 60% when tested in accordance with BS; 2831 Test Dust No.
3.
L. Refrigerant stop valves which incorporate a spindle gland shall be serviceable with
the valves “in situ”.
M. For refrigerant piping insulation, Refer to Section 15080 and the required
manufacturer insulation. Tape all joints to form a good vapor seal, then wrap with
glass cloth and paint with two coats of approved vapor seal.
Page 3 of 5
DIVISION 15 – MECHANICAL DX Split System & Window Type Air-Conditioning Units
SECTION 15781
O. The evaporator/fan coil section shall be ceiling, wall or floor standing and complete
with concealed control panel and finishes as indicated on the drawings.
1. On/Off/Heat/Cool Control.
2. Low/High Heating and Cooling Control.
3. Adjustable Thermostat.
Page 4 of 5
DIVISION 15 – MECHANICAL DX Split System & Window Type Air-Conditioning Units
SECTION 15781
PART 3 - EXECUTION
B. All products shall be inspected at time of delivery for damage and for compliance with
specifications.
C. All products that are found to be damaged, or not in accordance with the
specifications shall immediately be repaired or removed from the site and replaced.
Repairs shall not be undertaken before Engineer’s review of the Contractor’s
proposed action.
E. The Contractor shall supply handling equipment such as lifting beams, reinforced
canvas slings, protective paddings, struts, cradles, etc., required to handle products
without damaging hardware or linings and coatings.
3.2 INSTALLATION
A. All units mounted externally shall have a raised concrete base with a minimum height
of 150mm above surrounding surfaces. The base shall be sloped to provide natural
drainage and ensure that ponding does not occur under the unit.
B. Each packaged unit of whichever type shall be complete with a local electrical
disconnect switch.
C. The units shall be of the sizes, capacities, duties and types indicated on the drawings
and shall be installed in strict accordance with the manufacturers requirements.
END OF SECTION
Page 5 of 5
DIVISION 15 – MECHANICAL Ductwork and Accessories SECTION 15810
SECTION 15810
DUCTWORK AND ACCESSORIES
PART 1 - GENERAL
Section 15050, "Basic Mechanical Materials and Methods," with the additions and modifications
specified herein, applies.
The work involves the supply and installation of ductworks and its accessories including hangers,
diffusers, grilles, flexible ducts and louvers. Outside air ductworks including grilles and hangers
associated with air ventilation equipment shall also be supplied and installed by the Contractor.
1.3 SUBMITTALS
A. Corrosion Protection
Special protection is not required for components that have a zinc coating conforming to ASTM A
386 or a duplex coating of zinc and paint. Where expressly stipulated in equipment requirements
paragraphs below, the affected equipment items shall be protected by the manufacturer with a
corrosion-inhibiting coating or paint system that has been approved capable of satisfactorily
withstanding the following test. Test method shall be ASTM B 117. Period of test shall be 125 hours
for equipment intended for installation indoors; test period shall be 500 hours for equipment which
will be installed outdoors or which will be otherwise subjected to marine atmosphere. Each
specimen shall have a standard scratch as defined in ASTM D 1654.
1.5.1 Criteria
Thickness of coating or paint system on the actual equipment shall be identical to that on the
test specimens with respect to materials, conditions of application, and dry film thickness.
Page 1 of 12
DIVISION 15 – MECHANICAL Ductwork and Accessories SECTION 15810
1.6 DIMENSIONS
Duct sizes given in the drawings are clear internal dimensions and allowance shall be made for both
internal and external insulation and/or acoustic linings where applicable.
PART 2 - PRODUCTS
2.1 MATERIALS
ASTM A 123
A. All sheet metal work for the air-conditioning and ventilation systems shall be furnished,
installed, completely connected, cleaned, tested and adjusted by the Contractor. This shall
include the following major items of work.
1. All sheet metal work exposed to the weather and elsewhere as indicated on the
drawings, shall be built substantially as shown, of galvanized steel sheet properly
braced and supported and secured to the building construction and/or equipment.
Wherever not otherwise specified thickness shall be as follows:
Larger Thickness
Dimension Galvanized
US Duct (mm) Iron
Up to 750 No. 24 US Ga
Page 2 of 12
DIVISION 15 – MECHANICAL Ductwork and Accessories SECTION 15810
Size an spacing of the stiffeners used shall be in accordance with the requirement
of the latest edition of the ASHRAE HANDBOOK.
Groove and Pittshburgh look seams and slip joints shall be used for all rectangular
ducts unless otherwise specified. All slip joints shall be made in the direction of air
flow. Air tight solder joints shall be applied to hot air stainless steel duct and nay air
duct passing through public lavatories or kitchens.
C. All ducts 450 mm and larger shall be crossbroken. The Contractor may submit alternate
detail of bracing for approval; thickness of metal shall remain unchanged.
D. All ductwork which is to be insulated and is over 2000 mm in the larger dimension and all
uninsulated ductwork over 1350 mm in the larger dimension shall have angle iron on all four
corners running along the length of the duct and the same size as the girth angles. This
shall be used as additional stiffeners and to prevent sagging of the wide ducts.
F. All duct elbows having an inside radius smaller than the width of the elbow shall be equipped
with approved single thickness vanes.
G. All ductwork shall be substantially built with approved joints and seams, smooth on the
inside and a neat finish on the outside. Duct joints shall be as near airtight as possible, with
laps made in the direction of air flow and no flanges projecting into the air stream. Joints
and seams shall be sealed with sealants, soldering or welding.
H. While the drawings shall be adhered to as closely as possible, runs and sizes of ductwork
may be varied only after coordination with Engineers so that designed ceiling height, etc., will
be terminated.
I. All openings of the ductwork must be kept tightly closed during construction to keep rubbish
out. All open ends must be covered with plastic to keep the internal surfaces free of all dust
and debris. Non-conformance to this requirements shall incur heavy penalty on the
contractor.
J. It is the intention that this Contractor shall provide all ductwork and all auxiliary work required
for the installation of the complete sheet metal work needed for the operation of the system
specified herein.
Page 3 of 12
DIVISION 15 – MECHANICAL Ductwork and Accessories SECTION 15810
A. Galvanized steel, interlocking blade type, UL listing and label, 1 ½ hour rating, 70 ºC (160
ºF), fusible link, 100 percent free opening with no part of the blade stack or damper frame in
the air stream.
B. Fire dampers in fume hood exhaust or wet air exhaust shall be stainless steel
construction, all others may be galvanized steel.
1. The damper frame may be of design and length as to function as the mounting
sleeve, thus eliminating the need for a separate sleeve, as allowed by UL 555.
Otherwise provide sleeves and mounting angles, minimum 1.9 mm (14 gage),
required to provide installation equivalent to the damper manufacturer‟s UL test
installation.
3. Combination fire and smoke dampers: multi-louver or curtain type units meeting
all requirements of both dampers shall be used where shown and may be used at
the Contractor‟s option where applicable.
2.4 (OMITTED)
A. Where duct connections are made to fans and air handling units, install a non-combustible
flexible connection of 822 g (29 ounce) neoprene coated fiberglass fabric approximately 150
mm (6 inches) wide. For connections exposed to sun and weather provide hypalon coating
in lieu of neoprene. Burning characteristics shall conform to NFPA 90A. Securely fasten
flexible connections to round ducts with stainless steel or zinc-coated iron draw band with
worm gear fastener. For rectangular connections, crimp fabric to sheet metal and fasten
sheet metal to ducts by screws 50 mm (2 inches) on center. Fabric shall not be stressed
other than by air pressure. Allow at least 25 mm (one inch) slack to insure that no vibration is
transmitted.
2.6 (OMITTED)
D. Swirl Diffuser:
a. For Initiatory circulation.
1. Diffuser face and side entry plenum boxes constructed of rolled,
galvanized steel.
2. Discharge nozzle and top entry plenum constructed of aluminum.
3. Swirling, rotational type air pattern.
4. Finish: Off-white baked enamel as approved by Architect.
Page 5 of 12
DIVISION 15 – MECHANICAL Ductwork and Accessories SECTION 15810
1. Staircase
a. Extruded aluminum construction.
b. Removable core.
c. Off-white baked enamel finish
d. Category Four Approved Products. See Section 01 6200 for definitions
of Categories.
1. Krueger: 5815 with flat border frame.
2. Metal*Aire: 42F.
3. Titus: 1707, Type 1 border.
2.8 LOUVERS
Fixed type. Fold or bead the edges of louver blades to exclude driving rain. Louver frames shall be
made of 16 gage aluminum. Provide insect screen constructed of the same type metal as the
louvers. Louver depth shall be as indicated.
A. Bird Screens
With 12mm by 12mm mesh, 0.33 diameter stainless steel wire. Insect screen frames shall
be grooved type with vinyl or neoprene spline insert for securing screen cloth.
B. External Louvers
Weatherproof external louvers shall be supplied and installed by the Mechanical Contractor
unless otherwise specified.
C. Plenum boxes
Plenum boxes shall be fabricated from Ga. 24 GI sheet complete with interval dividers and
acoustically lined internally. Duct tapping points shall have volume dampers.
Damper controller and cable shall be concealed behind the wall. Cable to consist of
Bowden cable .054” stainless steel control wire encapsulated in 1/16” flexible galvanized
spiral wire sheath. Controller to be mounted in 4-1/2” square non-flammable enclosure
complete with control knob, support bracket, cover plate and external flanges for wall stud
installation. Controller to be 14 gauge steel rack and pinion gear drive converting rotary
motion to push-pull motion. Control shaft shall be D-style flatted ¼” diameter with 265-
degree rotation providing graduations for positive locking and control, and 1-1/2” linear
travel capability. Control kit is designed to be surface mounted and to allow easy
adjustment of damper from the control knob. Control kit shall be Young Regulator Model
270-700 or prior approved equal.
2.10 COMPONENTS
b. Fire retardant, waterproof, airtight, resistant to acids and grease, and withstand
constant temperatures of 250 deg F 121 deg C.
c. Acceptable Manufacturer‟s Standard Model/Style.
1. Duro Dyne: MFN.
2. Ventfabrics: Ventglas.
Page 7 of 12
DIVISION 15 – MECHANICAL Ductwork and Accessories SECTION 15810
Page 8 of 12
DIVISION 15 – MECHANICAL Ductwork and Accessories SECTION 15810
F. Air Turns:
a. Single curved blades or vanes, with one inch 25 mm trailing edge, arranged to
permit air to make abrupt turns without appreciable turbulence.
b. Quiet and free from vibration under operating conditions.
Fabricate from minimum 20 gage galvanized steel. Where sleeves are installed in
bearing walls, provide structural steel sleeves as indicated. Size sleeves to provide 25
mm clearance between duct and sleeve or between insulation and sleeve for insulated
ducts.
Provide 25 mm clearance between the duct and the sleeve, or 25 mm clearance between
insulation and sleeve for insulated ducts except at grilles, registers, and diffusers.
2.11.3 Packing
Page 9 of 12
DIVISION 15 – MECHANICAL Ductwork and Accessories SECTION 15810
PART 3 - EXECUTION
3.1 INSTALLATION
3.1.1 General
Installation shall conform with NFPA 90A and SMACNA FGDCS HPDCS and LPDCS.
Provide mounting and supporting of ductwork and accessories including, but not limited to
structural supports, hangers, vibration isolators, stands, clamp and brackets, access doors,
and dampers. Use electrical isolation between dissimilar metals. Install ductwork
accessories as indicated in accordance with the manufacturer's printed instruction. Allow
clearance for inspection, repair, replacement and service.
3.1.2 Ductwork
Install airtight. When air distribution systems are operated, there shall be no chatter,
vibration or dust marks.
Those required to suit the sizes of factory-fabricated equipment actually furnished, shall be
designed to minimize expansion and contraction. Use gradual transitions in field changes
as well as modifications to connecting ducts.
SMACNA DCS, Section 4. Attach supports only to structural framing members and
concrete slabs. Do not anchor supports to metal decking unless a means is provided and
approved for preventing the anchors from puncturing the metal decking. Where supports
are required between structural framing member, provide suitable intermediate metal
framing.
3.1.3.1 (OMITTED)
Provide flexible connectors between fans and ducts or casings and where ducts are of
dissimilar metals as indicated. For round ducts, securely fasten flexible connectors by
zinc-coated steel clinch-type draw-bands. For rectangular ducts, lock flexible connectors
to metal collars.
Page 10 of 12
DIVISION 15 – MECHANICAL Ductwork and Accessories SECTION 15810
Remove all debris and dirt from ducts and wipe clean. Before installing air outlets, use air
handler to blow dry air through entire system at maximum attainable velocity. Provide
temporary air filters for this operation.
Provide for ductwork penetrations in floors, walls, and partitions through which metallic
and plastic ductwork passes.
A. Duct Sleeves: Fill space between duct and sleeve or between insulation and
sleeve for insulated ducts with mineral fiber, except at grilles, registers, and
diffusers.
B. Prepared Openings: Fill space between duct and opening or between insulation
and opening for insulated ducts with mineral fiber, except at grilles, registers, and
diffusers.
C. Closure Collars: Fit collars snugly around ducts or insulation. Grind edges of
collar smooth to preclude tearing or puncturing insulation covering or vapor
barrier. Provide nails with maximum 150 mm centers on collars.
Provide for automatic dampers, volume dampers, fire dampers, coils, thermostats,
temperature controllers, valves, filters, humidifiers and other concealed apparatus
requiring service and inspection in the duct systems.
3.1.8 Dampers
When installed on ducts to be thermally insulated, equip each damper operator with
stand-off mounting brackets, bases, or adapters to provide clearance between the duct
and operator not less than the thickness of insulation. Stand-off mounting items shall be
integral with the operator or standard accessory of damper manufacturer.
3.1.9 Packing
Pack spaces between sleeve or opening and duct or duct insulation with mineral fiber.
The Contractor is responsible for the administration and direction of tests. Furnish instruments,
equipment, connecting devices and personnel for the tests. Notify the Project Manager 7 days
before inspection or testing is scheduled.
Page 11 of 12
DIVISION 15 – MECHANICAL Ductwork and Accessories SECTION 15810
Not all low velocity ductwork need to be tested unless specified elsewhere in this
specification or especially called for by the Project Manager for random test of equivalent to
20% of total air duct length in the whole sub-contract.
Upon completion of testing and balancing of air systems, conduct sound level tests
of conditioned spaces. Use approved calibrated sound level meter and record
sound levels in DBA with air systems off, with heating system only operating and
with cooling system only operating. Record the following data for each room
system in quadruplicate:
C. Test Locations
Take sound level reading at location 1.80 meters from face of each outlet on a line
at 45 degrees with face of outlet.
D. Remedial Action
If sound level is at any observation point exceeds 20 45 DBA, the Contractor shall
take remedial action as directed.
Page 12 of 12
DIVISION 15 – MECHANICAL Metal Ducts and Accessories SECTION 15815
SECTION 15815
METAL DUCTS AND ACCESSORIES
PART 1 – GENERAL
1.1 DESCRIPTION
1. Supply air, return air, outside air, exhaust, and relief systems.
B. Definitions:
C. Duct System Construction and Installation: Referenced SMACNA Standards are the
minimum acceptable quality.
Page 1 of 18
DIVISION 15 – MECHANICAL Metal Ducts and Accessories SECTION 15815
2. At the beginning of the work, leak test representative samples of the duct
construction for each pressure class greater than 750 Pa (3 inches w.g). The
sample specimen shall be minimum 25% of the ductwork of the selected
system representing each pressure class, and shall include at least five
transverse joints, typical seams, an access door, and at least two typical
branch connections and an elbow. The sample specimen shall be part of the
actual ductwork to be installed for the project.
3. The leakage amount shall not exceed the permissible leakage rate in CFM
per 100 square feet of duct surface for the pressure and leakage classes
shown in table below. The permissible leakage rate shall be calculated as per
Section 4 of SMACNA HVAC Air Duct Leakage Test Manual.
5. If a specimen fails to meet the permissible leakage level, the contractor shall
modify all ductwork installed represented by this specimen to bring it into
compliance and shall retest it until acceptable leakage is demonstrated to the
Consultant.
E. Duct accessories exposed to the air stream, such as dampers of all types (except
smoke dampers) and access openings, shall be of the same material as the duct or
provide at least the same level of corrosion resistance.
1.4 SUBMITTALS
1. Rectangular ducts:
Page 2 of 18
DIVISION 15 – MECHANICAL Metal Ducts and Accessories SECTION 15815
b. Duct liner.
d. Access doors.
b. Duct liner.
d. Access sections.
e. Installation instructions.
5. Fire dampers, fire doors, and smoke dampers with installation instructions.
8. Flexible connections.
The publications listed below form a part of this specification to the extent referenced. The
publications are referenced in the text by the basic designation only.
Page 3 of 18
DIVISION 15 – MECHANICAL Metal Ducts and Accessories SECTION 15815
G. Australian Standards
AS 1530.4 – 1990 Methods for fire tests on building materials, components and
structures
Par 4 – Fire-resistance tests of elements of building
construction
Page 4 of 18
DIVISION 15 – MECHANICAL Metal Ducts and Accessories SECTION 15815
PART 2 – PRODUCTS
A. General: Except for systems specified otherwise, construct ducts, casings, and
accessories of galvanized sheet steel, ASTM A653 or A875, coating G90 (“APO
Galfan”) or equal; or aluminum sheet, ASTM B209, alloy 1100, 3003 or 5052.
B. Specified Corrosion Resistant Systems: Stainless steel sheet, ASTM A167, Class
302 or 304, Condition A (annealed), Finish No. 4 for exposed ducts and Finish No. 2B
for concealed duct or ducts located in mechanical rooms.
1. Damper frames, damper blades and shafts, shall be stainless steel or PVC
coated galvanized steel, with non-ferrous bearing material.
C. Grease Duct: Double wall Metalbestos Model PS, factory-built grease duct, UL
labeled and complying with NFPA 96 may be furnished in lieu of specified materials
for kitchen and grill hood exhaust duct. Installation and accessories shall comply with
the manufacturers catalog data. Outer jacket or exposed ductwork shall be stainless
steel. Square and rectangular duct shown on the drawings will have to be converted
to equivalent round size.
D. Joint Sealing: Refer to SMACNA Standards, paragraph S1.8 and S1.9
2. Tape: Use only tape specifically designated by the sealant manufacturer and
apply only over wet sealant. Pressure sensitive tape shall not be used on
bare metal or on dry sealant.
C. Seal Classes: As shown on the drawings and in accordance with SMACNA HVAC Air
Duct Leakage Test Manual.
D. Kitchen and Grill Hood (Ventilator) Exhaust Ducts: Comply with NFPA 96.
1. Material: 1.6mm (16 gage) steel sheet (black iron), ASTM A569, or 1.3mm
(18 gage) stainless steel. Use stainless steel for exposed duct in occupied
areas.
E. Round and Flat Oval Ducts: Furnish duct and fittings made by the same manufacturer
to insure good fit of slop joints. When submitted and approved in advance, round and
flat oval duct, with size converted on the basis of equal pressure drop, may be
furnished in lieu of rectangular duct design shown on the drawings.
Page 5 of 18
DIVISION 15 – MECHANICAL Metal Ducts and Accessories SECTION 15815
2. Provide bellmouth, conical tees or taps, laterals, reducers, and other low loss
fittings as shown in SMACNA Standards.
3. Ribbed Duct Option: Lighter gage round/oval duct and fittings may be
furnished provided certified tests indicating that the rigidity and performance
is equivalent to SMACNA standard gage ducts are submitted.
G. Casings and Plenums: Construct in accordance with SMACNA Standards Section VI,
including curbs, access doors, pipe penetrations, eliminators and drain pans. Access
doors shall be hollow metal, insulated with latches and door pulls, 500 mm (20
inches) wide by 1200 - 1350 mm (48-54 inches) high. Provide viewport in the doors
where shown. Provide drain for outside air louver plenum. Outside air plenum shall
have exterior insulation. Drain piping shall be routed to the nearest floor drain.
I. Duct Hangers and Supports: Refer to SMACNA Standards Section IV. Avoid use of
trapeze hangers for round duct.
A. Duct sizes shown on drawings for lined duct are clear opening inside lining.
B. Rectangular Duct or Casing Liner: ASTM C1071, Type I (flexible), or Type II (board),
25 mm (one inch) minimum thickness matte face with anti-mircobial coating, applied
with mechanical fasteners and 100 percent coverage of adhesive in conformance
with SMACNA, Duct Liner Application Standard.
C. Round and Oval Duct Liner: Factory fabricated double-walled with 25 mm (one inch)
thick sound insulation and inner perforated galvanized metal liner. Construction shall
comply with flame and smoke rating required by NFPA 90A. Metal liner shall be 1.0 to
0.60 mm (20 to 24 gage) having perforations not exceeding 2.4 mm (3/32 inch)
diameter and approximately 22 percent free area. Metal liner for fittings need to be
perforated. Assemblies shall be complete with continuous sheet mylar liner, 2 mil
thickness, between the perforated liner and the insulation to prevent erosion of the
insulation. Provide liner couplings/spacer for outer shell to liner size. Provide liner
spacing/concentricity leaving airway unobstructed.
Page 6 of 18
DIVISION 15 – MECHANICAL Metal Ducts and Accessories SECTION 15815
A. Provide access doors, sized and located for maintenance work, upstream, in the
following locations:
2. Each fire damper (for link service), smoke damper and automatic control
damper.
4. For cleaning kitchen hood exhaust duct, locate access doors at 6 m (20 feet)
intervals and at each change in duct direction.
B. Openings shall be at large as feasible in small ducts, 300 mm (12 inch by 12 inch)
minimum where possible. Access sections in insulated ducts shall be double-wall,
insulated. Transparent shatterproof covers are preferred for uninsulated ducts.
2. For round and flat oval duct: Access sections shall be not less than 1.0 mm
(20 gage) housing welded or riveted to a duct section.
A. Galvanized steel, interlocking blade type, UL listing and label, 1 ½ hour rating, 70 ºC
(160 ºF), fusible link, 100 percent free opening with no part of the blade stack or
damper frame in the air stream.
B. Fire dampers in fume hood exhaust or wet air exhaust shall be stainless steel
construction, all others may be galvanized steel.
A. Maximum air velocity, through free area of open damper, and pressure loss: low
pressure and medium pressure duct (supply, return, exhaust, outside air): 450 m/min
(1500 fpm). Maximum static pressure loss: 32 Pa (0.13 inch WG).
B. Maximum air leakage, closed damper: 0.32 cubic meters/min/square meter (4.0 cfm
per square foot) at 750 Pa (3 inches wg) differential pressure.
Page 7 of 18
DIVISION 15 – MECHANICAL Metal Ducts and Accessories SECTION 15815
1. Meet requirements of Table 6-1 of UL 555S, except the Fire Endurance and
Hose Stream test.
2. Frame: Galvanized steel channel with side, top and bottom stops or seals.
Galvanized steel, interlocking blade type, UL listing and label, 71 ºC (160 ºF) fusible link, 3
hour rating and approved for openings in Class A fire walls with rating up to 4 hours, 100
percent free opening with no part of the blade stack or damper frame in the air stream.
A. General: Factory fabricated, complying with NFPA 90A for connectors not passing
through floors of buildings. Flexible ducts shall not penetrate any fire or smoke barrier
which is required to have a fire resistance rating of one hour or more. Flexible duct
length shall not exceed 1.5 m (5 feet). Provide insulated acoustical air duct
connectors in supply air duct systems and elsewhere as shown.
C. Insulated Flexible Air Duct: Factory made including mineral fiber insulation with
maximum C factor of 0.25 at 24 ºC (75 ºF) mean temperature, encased with a low
permeability moisture barrier outer jacket, having a puncture resistance of not less
than 50 Beach Units. Acoustic insertion loss shall not be less than 3 dB per 300 mm
(foot) of straight duct, at 500 Hz, based on 150 mm (6 inch) duct, of 750 m/min (2500
fpm).
D. Application Criteria:
Page 8 of 18
DIVISION 15 – MECHANICAL Metal Ducts and Accessories SECTION 15815
E. Duct Clamps: 100 percent nylon strap, 80 kg (175 pounds) minimum loop tensile
strength manufactured for this purpose or stainless steel strap with cadmium plated
worm gear tightening device. Apply clamps with sealant and as approved for UL 181,
Class 1 installation.
A. Where duct connections are made to fans and air handling units, install a non-
combustible flexible connection of 822 g (29 ounce) neoprene coated fiberglass fabric
approximately 150 mm (6 inches) wide. For connections exposed to sun and weather
provide hypalon coating in lieu of neoprene. Burning characteristics shall conform to
NFPA 90A. Securely fasten flexible connections to round ducts with stainless steel or
zinc-coated iron draw band with worm gear fastener. For rectangular connections,
crimp fabric to sheet metal and fasten sheet metal to ducts by screws 50 mm (2
inches) on center. Fabric shall not be stressed other than by air pressure. Allow at
least 25 mm (one inch) slack to insure that no vibration is transmitted.
General: In addition to those shown on the schematic diagrams, the Contractor shall provide
duct-mounted sound attenuators where required to satisfy the Room Noise Criteria specified
under Section 15071, without additional cost to the Owner. Adjustments of fan ESP shall be
done accordingly.
A. Cleaning, not less than 1.0 mm (20 gage) galvanized sheet steel, or 1.3 mm (18
gage) aluminum fitted with suitable flanges to make clean airtight connections to
ductwork. Sound-absorbent material faced with glass fiber cloth and covered with not
less than 0.6 mm (24 gage) or heavier galvanized perforated sheet steel, or 0.85 mm
(22 gage) or heavier perforated aluminum. Perforations shall not exceed 4 mm (5/32-
inch) diameter, approximately 25 percent free area. Sound absorbent material shall
be long glass fiber acoustic blanket meeting requirements of NFPA 90A.
B. Entire unit shall be completely air tight and free of vibration and buckling at internal
static pressures up to 2000 Pa (8 inch water gage) at operating velocities.
C. Pressure drop through each unit: Not to exceed indicated value at design air
acoustical performance 80 Pascal maximum.
D. Cap open ends of attenuators at factory with plastic, heavy duty paper, cardboard, or
other appropriate material to prevent entrance of dirt, water, or any other foreign
matter to inside of attenuator. Caps shall not be removed until attenuator is installed
in duct system.
A. Aluminum, ASTM B209, louvered, spun, or fabricated using panel sections with roll-
formed edges, 13 mm (1/2 inch) mesh aluminum or galvanized welded wire bird
screen, with gravity or motorized dampers were shown, accessible interior, designed
for 2200 km/h winds.
B. See hood schedule on the drawings. Sizes shown designate throat size. Area of hood
perimeter opening shall be not less than the throat area.
C. Dampers for Gravity Ventilators Without Duct Connection: Construct damper of the
same material as the ventilator and design to completely close opening or remain
Page 9 of 18
DIVISION 15 – MECHANICAL Metal Ducts and Accessories SECTION 15815
wide open. Hold damper in closed position by a brass chain and catch. Extend chains
300 mm (12 inches) below and engage catch when damper is closed.
Galvanized steel or extruded aluminum 300 mm (12 inches) above finish roof service,
continuous welded corner seams, treated wood nailer, 40 mm (1-1/2 inch) thick, 48 kg/cubic
meter (3 pound/cubic feet) density rigid mineral fiberboard insulation with metal liner, built-in
cant strip (except for gypsum or tectum decks). For surface insulated roof deck, provide
raised cant strip (recessed mounting flange) to start at the upper surface of the insulation.
Curbs shall be constructed for pitched roof or ridge mounting as required to keep top of curb
level.
Section 15050.
1. Design and installation to meet the criteria listed above, and meet
requirements of the latest Sheet Metal and Air Conditioning Contractors
National Association (SMACNA), Seismic Restraint Manual Guidelines for
Mechanical Systems for the prescribed Seismic Hazard Level (SHL).
2. Design and installation to meet the criteria listed above, and meet the most
current requirements of the National Uniform Seismic Installation Guidelines
(NUSIG). Contractor shall submit all design tables and information for the
design force levels, stamped and signed by a professional engineer
registered in the place where project is located.
A. All sheet metal ducts and air plenums within mechanical rooms or within a distance of
50 feet total duct length of connected vibration-isolated equipment (whichever is
longer) shall be isolated from the building structure by either Unit SLRS or 30N
Page 10 of 18
DIVISION 15 – MECHANICAL Metal Ducts and Accessories SECTION 15815
B. Ducts within the specified limits which penetrate the building construction shall be
isolated from the building by using resilient penetration sleeve/seals. Resilient lateral
guides shall be used wherever lateral support of vertical duct runs is required within
the specified limits.
C. Flexible Duct Connections: Sheet metal ducts or plenum openings shall be squarely
aligned with the fan discharge, fan intake, or adjacent duct section prior to installation
of the flexible connection, so that the clear length is approximately equal all the way
around the perimeter. Flexible duct connections shall not be installed until this
provision is met. The fan unit or adjacent duct section shall be able to move 1 inch in
any direction without causing metal-to-metal contact or stretching taut the flexible
connection.
A. Manufactured type with a minimum 50 mm (two inch) length for insulated duct, and a
minimum 25 mm (one inch) length for duct not insulated. Test hole shall have a flat
gasket for rectangular ducts and a concave gasket for round ducts at the base, and a
screw cap to prevent air leakage.
B. Provide instrument test holes at each duct or casing mounted temperature sensor or
transmitter, and at entering and leaving side of each heating coil, cooling coil, and
heat recovery unit.
Each regulator shall solely operate on duct pressure and require no external power supply.
Each regulator shall be preset and factory calibrated requiring no field adjustment to the
airflows as indicated on the design drawing, and shall be rated for use in air temperatures
o o o o
ranging from -25 to 140 F (-32 to 60 C). Constant airflow regulators shall be capable of
maintaining constant airflow within +/- 10% of scheduled flow rates (15% for units 50 cfm or
less), within the operating range of 0.2 to 0.8 in. w.g. differential pressure, or 0.6 to 2.4. in.
w.g. on high-pressure models. Sound power levels shall not exceed those for each size and
cfm rating as scheduled. Regulators shall be provided as an assembly consisting of a flame
resistant plastic body with self-inflating silicon element housed within a .75mm galvanized
steel sleeve or flanged plate for mounting in either round or rectangular duct. Each round
sleeve must be fitted with a brush gasket to assure perimeter air tightness with the interior
surface of the duct. All Constant Airflow Regulators will require no maintenance and must be
warranted for a period of no less than five years. Constant Airflow Regulators shall be
installed in tight ducting systems in accordance with all applicable codes and manufacturer’s
instructions.
B. Material: 60 percent free area perforated plate made of 3.5 mm (10 gage) galvanized
steel with round openings equally spaced over entire face area. Maximum air
pressure drop through distribution plate for air volumes scheduled shall be 25 Pa
(0.10-inch WG). Bolt plate to a sturdy steel support frame.
Page 11 of 18
DIVISION 15 – MECHANICAL Metal Ducts and Accessories SECTION 15815
A. Materials:
1. Steel or aluminum except that all units installed in operating rooms shall be
aluminum or stainless steel. Provide manufacturer's standard gasket.
3. Contractor shall review all ceiling drawings and details and provide all ceiling
mounted devices with appropriate dimensions and trim for the specific
locations.
B. Performance Test Data: In accordance with Air Diffusion Council code 1062R4. Refer
to Section 15071, for NC criteria.
1. Ceiling Diffusers: Suitable for surface mounting, exposed T-bar or special tile
ceilings, off-white finish, square or round neck connection as shown on the
drawings. Provide plaster frame for units in plaster ceilings.
d. Slot diffuser/plenum:
Page 12 of 18
DIVISION 15 – MECHANICAL Metal Ducts and Accessories SECTION 15815
D. Return and Exhaust Registers and Grilles: Provide opposed blade damper without
removable key operator for registers.
1. Finish: Off-white baked enamel for ceiling mounted units. Wall units shall
have a prime coat for field painting, or shall be extruded aluminum with
manufacturer's standard aluminum finish.
7. Filter Grilles: Standard face hinged to a mounting frame with space for a 25
mm (one inch) throwaway filter. Hold face closed by a locking screw. Provide
retaining clips to hold filter in place. Provide one inch thick fiberglass
throwaway filter.
A. General: Fabricate duct accessories from the same material as the ductwork in which
the accessory will be installed, unless specified otherwise.
B. Manual Splitter Dampers: Fabricated from same material as the ductwork two gauges
heavier than duct in which installed with splitters long enough to completely close the
branch duct without flutter. In all cases, blade dimension in direction of airflow shall
be 1-1/2 times width of branch duct not less than 12 inches. Provide a locking
quadrant and align its operating handle with the damper blade.
2. Blade and fastener material shall be the same as the ductwork in which the
damper is to be installed. Rod shall be galvanized steel. Blade shall be
riveted or bolted to rod.
Page 13 of 18
DIVISION 15 – MECHANICAL Metal Ducts and Accessories SECTION 15815
3. Dampers shall be of a length suitable to shut off branch ducts without causing
damper flutter.
4. Cross break dampers and stiffen edges with two edge brakes for rigidity.
Provide additional stiffening angles, as required.
5. Provide continuous rods and outside end bearings on all damper assemblies.
Additionally, provide inside end bearings on internally lined ducts. Mark the
ends of damper rods with a saw cut to indicate blade position.
2. Blade, rod, linkage, frame, and fastener material shall be the same as the
ductwork in which the damper is to be installed.
3. Blades shall be center crimped for stiffness and to receive pins and rods, and
edge crimped to interlock with adjacent blades on full shutoff. Provide
additional stiffening angles, as required.
5. Provide continuous rods on all drive damper assemblies. Mark the ends of
the damper shaft extension with a saw cut to indicate blade position.
7. Bushings for galvanized steel dampers shall be oil impregnated bronze, sized
to match with pins. Bushings for aluminum and stainless steel ductwork shall
be nylon or other suitable thermoset plastic.
a. Ventlok as specified.
a. as regulator.
Ventlok Figure 635 dial approved by the Architect/Engineer.
Page 14 of 18
DIVISION 15 – MECHANICAL Metal Ducts and Accessories SECTION 15815
a. Ventlok Figure 644 dial regulator with Hi-Vel hardware, and Figure
a. As approved by the Architect/Engineer.
609 end bearings.
F. Turning Vanes:
1. Acceptable Manufacturers:
a. Elgen All-Tight
c. Titus
a. Ventlok
b. Duro-Dyne
c. Ruskin
Page 15 of 18
DIVISION 15 – MECHANICAL Metal Ducts and Accessories SECTION 15815
2. Description:
a. Provide sufficient Ventlok No. 360 sealant for application between the
door frame and duct for installations in ductwork with seal Class A
and B, and in ductwork serving cleanrooms.
H. Spin-in Fittings – Description: Straight pattern sheet metal spin-in fitting with 45
degree scoop designed for connection to sheet metal ductwork. Assemble using spot
welds or rivets. Button-punch fabrication is prohibited. Provide a specified balancing
damper in the ductwork immediately downstream of each spin-in fitting.
I. Backdraft Dampers:
b. Dowco
c. Ruskin
d. Field
2. Description
Page 16 of 18
DIVISION 15 – MECHANICAL Metal Ducts and Accessories SECTION 15815
2. Description: Round upblast damper with two-piece design frame shall be 10-
gauge galvanized steel with 1-1/2 inch flange. Blades shall be 20-gauge
galvanized steel with ¾ inch axle and stainless steel bearing sleeve.
PART 3 – EXECUTION
3.1 INSTALLATION
B. Fabricate, install and test ductwork and accessories in accordance with referenced
SMACNA Standards:
1. Drawings show the general layout of ductwork and accessories but do not
show all required fittings and offsets that may be necessary to connect ducts
to equipment, boxes, diffusers, grilles, etc., and to coordinate with other
trades. Fabricate ductwork based on field measurements. Provide all
necessary fittings and offsets at no additional cost to the Owner. Coordinate
with other trades for space available and relative location of HVAC equipment
and accessories on ceiling grid. Duct sizes on the drawings are inside
dimensions which shall be altered by Contractor to other dimensions with the
same air handling characteristics where necessary to avoid interferences and
clearance difficulties.
2. Provide duct transitions, offsets and connections to dampers, coils, and other
equipment in accordance with SMACNA Standards, Section II. Provide
streamliner, when an obstruction cannot be avoided and must be taken in by
a duct. Repair galvanized areas with galvanizing repair compound.
C. Install duct hangers and supports in accordance with SMACNA Standards, Section
IV.
E. Seal openings around duct penetrations of floors and fire rated partitions with fire stop
material as required by NFPA 90A.
Page 17 of 18
DIVISION 15 – MECHANICAL Metal Ducts and Accessories SECTION 15815
F. Flexible duct installation: Refer to SMACNA Standards, Section III. Ducts shall be
continuous, single pieces not over 1.5 m (5 feet) long (NFPA 90A), as straight and
short as feasible, adequately supported. Centerline radius of bends shall be not less
than two duct diameters. Make connections with clamps as recommended by
SMACNA. Clamp per SMACNA S3.33 and S3.34 with one clamp on the core duct
and one on the insulation jacket. Flexible ducts shall not penetrate floors, or any
chase or partition designated as a fire or smoke barrier, including corridor partitions
fire rated one hour or two hour. Support ducts SMACNA Standards.
G. Where diffusers, registers and grilles cannot be installed to avoid seeing inside the
duct, paint the inside of the duct with flat black paint to reduce visibility.
I. Air Flow Measuring Devices (AFMD): Install units with minimum straight run
distances, upstream and downstream as recommended by the manufacturer.
J. Low Pressure Duct Liner: Install in accordance with SMACNA, Duct Liner Application
Standard.
END OF SECTION
Page 18 of 18
DIVISION 15 – MECHANICAL Fans & Ventilations SECTION 15836
SECTION 15836
AXIAL FANS
PART 1 - GENERAL
1.2 SUMMARY
1. Tubeaxial fans.
2. Vaneaxial fans.
3. Mixed-flow fans.
A. Project Altitude: Base fan performance ratings on actual Project site elevations above
sea level.
1.4 SUBMITTALS
A. Product Data: Include rated capacities, furnished specialties, and accessories for
each type of product indicated and include the following:
Page 1 of 10
DIVISION 15 – MECHANICAL Fans & Ventilations SECTION 15836
C. Coordination Drawings: Show fan room layout and relationships between components
and adjacent structural and mechanical elements. Show support locations, type of
support, and weight on each support. Indicate and certify field measurements.
E. Operation and Maintenance Data: For axial fans to include in emergency, operation,
and maintenance manuals.
B. AMCA Compliance: Products shall comply with performance requirements and shall
be licensed to use the AMCA-Certified Ratings Seal.
C. NEMA Compliance: Motors and electrical accessories shall comply with NEMA
standards.
C. Lift and support units with manufacturer's designated lifting or supporting points.
Page 2 of 10
DIVISION 15 – MECHANICAL Fans & Ventilations SECTION 15836
1.7 COORDINATION
B. Coordinate size and location of concrete bases. Cast anchor-bolt inserts into bases.
Concrete, reinforcement, and formwork requirements are specified in Division 3.
C. Coordinate installation of roof curbs, equipment supports, and roof penetrations. These
items are specified in Division 7 Section "Roof Accessories."
A. Furnish extra materials described below that match products installed and that are
packaged with protective covering for storage and identified with labels describing
contents.
PART 2 - PRODUCTS
1. Greenheck.
2. Niagara (The New York Blower Company).
3. Kruger.
C. Description: Fan wheel and housing, factory-mounted motor with belt drive or direct
drive, an inlet cone section, and accessories.
H. Drives: Factory mounted, with final alignment and belt adjustment made after installation.
3. Fan Pulleys: Cast iron with split, tapered bushing; dynamically balanced at
factory.
4. Motor Pulleys: Adjustable pitch for use with motors through 5 hp; fixed pitch for
use with larger motors. Select pulley so pitch adjustment is at the middle of
adjustment range at fan design conditions.
5. Belts: Oil resistant, nonsparking, and nonstatic; matched sets for multiple belt
drives.
6. Belt Guards: Fabricate of steel for motors mounted on outside of fan cabinet.
7. Motor Mount: Adjustable base.
8. Shaft Bearings: Radial, self-aligning ball or roller bearings.
a. Ball-Bearing Rating Life: ABMA 9, L10 of 100,000 hours.
b. Roller-Bearing Rating Life: ABMA 11, L10 of 100,000 hours.
c. Extend lubrication lines to outside of casing and terminate with grease
fittings.
I. Accessories:
J. Motors: Comply with requirements in Section 15055 Motors, Starters, Control Centers
and Wiring.
Page 4 of 10
DIVISION 15 – MECHANICAL Fans & Ventilations SECTION 15836
K. Factory Finishes:
L. Isolators: Restrained spring isolators having a static deflection of 1 inch (25 mm).
1. Greenheck.
2. Niagara (The New York Blower Company).
3. Kruger.
C. Description: Fan wheel and housing, straightening vane section, factory-mounted motor
with belt drive or direct drive, an inlet cone section, and accessories.
G. Wheel Assemblies: Cast-aluminum hub assembly, machined and fitted with threaded
bearing wells to receive blade-bearing assemblies with replaceable, cast-aluminum
blades; factory mounted and balanced.
H. Drives: Factory mounted, with final alignment and belt adjustment made after installation.
1. Service Factor Based on Fan Motor Size: 1.15.
2. Fan Shaft: Turned, ground, and polished steel designed to operate at no more
than 70 percent of first critical speed at top of fan's speed range.
3. Fan Pulleys: Cast iron with split, tapered bushing; dynamically balanced at
factory.
4. Motor Pulleys: Adjustable pitch for use with motors through 5 hp; fixed pitch for
use with larger motors. Select pulley so pitch adjustment is at the middle of
adjustment range at fan design conditions.
Page 5 of 10
DIVISION 15 – MECHANICAL Fans & Ventilations SECTION 15836
5. Belts: Oil resistant, nonsparking, and nonstatic; matched sets for multiple belt
drives.
6. Belt Guards: Fabricate of steel for motors mounted on outside of fan cabinet.
7. Motor Mount: Adjustable base.
8. Shaft Bearings: Radial, self-aligning ball or roller bearings.
a. Ball-Bearing Rating Life: ABMA 9, L10 of 100,000 hours.
b. Roller-Bearing Rating Life: ABMA 11, L10 of 100,000 hours.
c. Extend lubrication lines to outside of casing and terminate with grease
fittings.
I. Accessories
K. Factory Finishes:
1. Greenheck.
2. Niagara (The New York Blower Company).
3. Kruger.
C. Description: Fan wheel and housing, factory-mounted motor with belt drive, and
accessories.
1. Inlet and Outlet Connections: Outer mounting frame and companion flanges.
2. Guide Vane Section: Integral guide vanes downstream from fan wheel designed to
straighten airflow.
3. Mixed-Flow Outlet Connection: Two flanged discharge(s) perpendicular to fan
inlet.
F. Drives: Factory mounted, with final alignment and belt adjustment made after installation.
Page 7 of 10
DIVISION 15 – MECHANICAL Fans & Ventilations SECTION 15836
G. Accessories:
1. Mounting Clips: Horizontal ceiling clips welded to fan housing, of same material as
housing.
2. Inlet and Outlet Screens: Wire-mesh screen on fans not connected to ductwork of
same material as housing.
3. Backdraft Dampers: Butterfly style, for mounting with flexible connection to the
discharge of fan or direct mounted to the discharge diffuser section of same
material as housing.
4. Motor Cover: Cover with side vents to dissipate motor heat, of same material as
housing.
5. Inlet Bell: Curved inlet for when fan is not attached to duct, of same material as
housing.
6. Inlet Cones: Round-to-rectangular transition of same material as housing.
7. Outlet Cones: Round-to-rectangular transition of same material as housing.
8. Stack Cap: Vertical discharge assembly with backdraft dampers, of same material
as housing.
I. Factory Finishes:
B. Square steel panel, deep drawn venturi, arc welded to support arms and fan/motor
support brackets, baked enamel finish. Provide wall collar for thru-wall installations.
Page 8 of 10
DIVISION 15 – MECHANICAL Fans & Ventilations SECTION 15836
A. Sound-Power Level Ratings: Comply with AMCA 301, "Methods for Calculating Fan
Sound Ratings from Laboratory Test Data." Factory test fans according to AMCA 300,
"Reverberant Room Method for Sound Testing of Fans." Label fans with the AMCA-
Certified Ratings Seal.
B. Fan Performance Ratings: Establish flow rate, pressure, power, air density, speed of
rotation, and efficiency by factory tests and ratings according to AMCA 210, "Laboratory
Methods of Testing Fans for Rating."
PART 3 - EXECUTION
3.1 INSTALLATION
B. Support floor-mounting units using restrained spring isolators having a static deflection of
25 mm (1 inch). Vibration- and seismic-control devices are specified in Division 15
Section "Mechanical Vibration and Seismic Controls."
1. Secure vibration and seismic controls to concrete bases using anchor bolts cast in
concrete base.
E. Support suspended units from structure using threaded steel rods and spring hangers
with vertical-limit stops having a static deflection of 25 mm (1 inch). Vibration-control
devices are specified in Division 15 Section "Mechanical Vibration and Seismic Controls."
3.2 CONNECTIONS
A. Duct installation and connection requirements are specified in other Division 15 Sections.
Drawings indicate general arrangement of ducts and duct accessories. Make final duct
connections with flexible connectors. Flexible connectors are specified in Division 15
Section "Duct Accessories."
A. Perform the following field tests and inspections and prepare test reports:
B. Test and adjust controls and safeties. Replace damaged and malfunctioning controls
and equipment.
3.4 ADJUSTING
C. Lubricate bearings.
END OF SECTION
Page 10 of 10
DIVISION 15 – MECHANICAL Air Terminal Units SECTION 15840
SECTION 15840
AIR TERMINAL UNITS
PART 1 - GENERAL
1.1 DESCRIPTION
Air terminal units, air flow control valves, and fan-coil units.
F. Section 15950 - Testing, Adjusting, and Balancing: Flow rates adjusting and
balancing
1.4 SUBMITTALS
C. Samples: Provide one typical air terminal unit for approval by the Consultant. This unit
will be returned to the Contractor after all similar units have been shipped and
deemed acceptable at the job site.
D. Certificates:
Page 1 of 5
DIVISION 15 – MECHANICAL Air Terminal Units SECTION 15840
The publications listed below form a part of this specification to the extent referenced. The
publications are referenced in the text by the basic designation only.
1.6 GUARANTY
PART 2 - PRODUCTS
A. General: Factory built, pressure independent units, factory set-field adjustable volume,
suitable for single or dual duct applications, as indicated. Clearly show on each unit
the unit number and factory set air volumes corresponding to the contract drawings.
Section 15950. Testing, adjusting and balancing work assume factory set air volumes.
Coordinate flow controller sequence and damper operation details with the drawings
and Section 15900.
2. Maximum room sound levels: Not to exceed criteria stated in Section 15071.
(Low-pressure duct is usually unlined. The inlet pressure should not be less
than 374 Pa (1-1/2 inches water gage), unless shown otherwise on drawings.
Provide terminal sound attenuators where necessary to comply with the noise
criteria. Sound tests and correction of deficiencies is specified in Section
15950.
C. Casing: Unit casing shall be constructed of galvanized steel not lighter than 0.85 mm
(22 gage) or aluminum sheet not lighter than 1.3 mm (18 gage). Casing of units
serving surgery area (where applicable) shall be of aluminum. Provide hanger
brackets for attachment of supports.
Page 2 of 5
DIVISION 15 – MECHANICAL Air Terminal Units SECTION 15840
air stream will not detach material. No lining material is permitted in the boxes
serving surgery areas.
2. Access panels (or doors): Provide panels large enough for inspection,
adjustment and maintenance without disconnecting ducts, and for cleaning
heating coils attached to unit, even if there are no moving parts. Panels shall
be flushed, gasketed airtight, and shall require no tool other than a
screwdriver to remove. Access panels on low-pressure side, i.e., downstream
of volume damper, do not require gasket if tightly fitted.
3. Total leakage from casing: Not to exceed 2 percent of the nominal capacity of
the unit when subjected to a static pressure of 747 pa (3 inch water gage),
with all outlets sealed shut and inlets fully open.
D. Construct dampers and other internal devices of corrosion resisting materials which
do not require lubrication or other periodic maintenance. The dampers and other
internal or external devices for boxes serving surgery area shall be of stainless steel
or aluminum.
1. Variable Air Volume Units (VAV): Externally powered electronic DDC control
capable of BMS interface, variable air volume, with field adjustable maximum
and minimum set points.
2. Constant volume single duct. The unit shall contain within the casing, a
mechanical constant volume regulator. Volume regulator shall control air
delivery to within plus or minus 5 percent of specified air flow subjected to
inlet pressure up to 1500 pa (6 inches water gage). Controls will be designed
to provide required sequence of operation.
Page 3 of 5
DIVISION 15 – MECHANICAL Air Terminal Units SECTION 15840
A.. Units shall be normally closed, constant volume, DDC control type with attenuators
and/or lined duct required to meet room NC criteria. Air terminal units (boxes) may be
used for this service.
C. Noise Levels: Operating at full cooling capacity, sound power level shall not exceed by
more than 5 dB the numerical value of sound pressure levels associated with noise
criteria specified in Section 15071. Select units at intermediate speed, for compliance
with the noise criteria.
D. Chassis: Galvanized steel, acoustically and thermally insulated to attenuate noise and
prevent condensation.
E. Cabinet Type: Not lighter than 1.3 mm (l8 gage) steel, reinforced and braced. Arrange
components and provide adequate space for installation of piping package and
control valves. Finish shall be factory-baked enamel in manufacturer's standard color
as selected by the architect. Provide synthetic rubber or polyurethane gasket for
air-tight installation to the wall for outside air to vertical units and return air to
horizontal units.
l. Vertical Unit: Provide 1.6 mm (l6 gage) steel front panel with 13 mm (l/2-inch)
thick fiberglass insulation and provide screw-type levelers.
a. Air outlet grilles: Adjustable four-way air deflection located in the top
panel.
b. Provide two hinged access doors (one each side) equipped with key
operated cam-lock fasteners in the unit top panel located to provide
access to the unit controls.
2. Horizontal Unit: Hinged bottom access panel with cam-lock fasteners. Provide
stamped integral discharged grilles in front of cabinet.
F. Concealed Units: Enclosed type with inlet and outlet duct collars.
l. Motors: 3-speed permanent split capacitor type with integral thermal overload
protection, for operation at not more than l200 RPM.
2. Provide a fan speed selector switch, with off position, mounted in a junction
box in the cabinet of each unit. Switch shall have a set of auxiliary contacts
which are open when the switch is in the "off" position and closed when the
switch in either of the other positions.
Page 4 of 5
DIVISION 15 – MECHANICAL Air Terminal Units SECTION 15840
I. Piping Package: Furnished with unit by the manufacturer to fit control valves provided
by the controls supplier. Submit manufacturer's detailed drawings of the piping in the
end compartments, for approval, prior to fabrication of the piping packages. Provide
gate valves on the supply and return pipes and balancing fittings on the return pipes.
J. Drain Pan: Galvanized steel or carbon steel bonderized and finished with not less than
two coats of baked enamel or equally durable finish, and of strength to requirement of
function it performs in unit. Inside or outside surfaces of drain pan shall be coated with
mastic type insulation or closed cell polyurethane. Provide a similar secondary drain
pan, which may be steel or PVC, provided with a drain connection to catch
condensation from all piping, coils and primary drain pan.
K. Air Filter: Manufacturer's standard throwaway type, not less than one inch thick,
supported to be concealed from sight and be tight fitting to prevent air by-pass. Filters
shall have slide out frames and be easily replaced without removing enclosure or any
part thereof.
L. Control valves and unit mounted return air thermostats are to be field installed.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Work shall be installed as shown and according to the manufacturer’s diagrams and
recommendations.
C. Support units rigidly so they remain stationary at all times. Cross-bracing or other
means of stiffening shall be provided as necessary. Method of support shall be such
that distortion and malfunction of units cannot occur.
D. Locate air terminal units to provide a straight section of inlet duct for proper
functioning of volume controls.
END OF SECTION
Page 5 of 5
DIVISION 15-MECHANICAL Air Filters SPECIFICATION SECTION 15861
PART 1 - GENERAL
1.1 DESCRIPTION
B. Definitions: Refer to ASHRAE 52.1 for definitions of face velocity, net effective filtering
area, media velocity, resistance (pressure drop), atmospheric dust spot efficiency and
dust-holding capacity.
1. Submit a test report for each Grade of filter being offered. The report shall be
less than five years old and will have been prepared by an independent
testing laboratory using test equipment, method and duct section as specified
by ASHRAE Standard 52.1 for type filter under test and acceptable to
Consultant, indicating that filters comply with the requirements of this
specification. Test for 150 m/min (500 fpm) will be accepted for lower velocity
rated filters provided the test report of an independent testing laboratory
complies with all the requirements of this specification.
2. Selection procedures: All filters tested shall have been procured by the
independent testing laboratory from the open market independent of
manufacturer of these filters and a statement to this effect must accompany
test report.
3. Owner’s Option: The Owner at its option may take one of the filters for each
different type submitted and run an independent test to determine if the filter
meets the requirements of this specification. When the filter meets the
requirements, the Owner will pay for the test. When the filter does not meet
the specification requirements, the manufacturer will be required to pay for
the test and replace the filters with filters that will perform as required by the
specifications.
B. Filter Supplier Warranty for Extended Surface Filters: Guarantee the filters against
leak, blow-outs, and other deficiencies during their normal useful life. Defective filters
shall be replaced at no cost to the Owner.
C. Nameplates: Each filter shall bear a label or name plate indicating manufacturer's
name, filter size, rated efficiency, UL classification, and file number.
1.4 SUBMITTALS
4. HEPA filters.
Page 1 of 6
DIVISION 15-MECHANICAL Air Filters SPECIFICATION SECTION 15861
5. Magnehelic gages.
D. Suppliers warranty.
The publications listed below form a part of this specification to the extent referenced. The
publications are referenced in the text by basic designation only.
PART 2 - PRODUCTS
A. To allow temporary use of HVAC systems for testing and in accordance with
Paragraph, TEMPORARY USE OF MECHANICAL AND ELECTRICAL SYSTEMS in
Section 15010, provide one complete set of additional (replacement) filter elements.
B. The Consultant will direct whether these additional filters will either be installed as
replacements for dirty units or turned over to the Owner for future use as
replacements.
A. Use factory assembled air filters of the extended surface type with supported or
non-supported cartridges for removal of particulate matter in air conditioning, heating
and ventilating systems. Filter units shall be of the extended surface type fabricated
for disposal when the dust-load limit is reached as indicated by maximum (final)
pressure drop.
Page 2 of 6
DIVISION 15-MECHANICAL Air Filters SPECIFICATION SECTION 15861
F. Maximum initial and final resistance, Pa (inches of water), for each filter cartridge
when operated at 150 m/min (500 feet per minute) face velocity:
G. Dust Holding Capacity: When tested to 250 Pa (l.00-inch water) at 150 m/min (500
fpm) face velocity, the dust holding capacity for each 600 mm by 600 mm (24 inches
Page 3 of 6
DIVISION 15-MECHANICAL Air Filters SPECIFICATION SECTION 15861
by 24 inches) (face area) filter shall be at least the values listed below. For other filter
sizes the dust holding capacity shall be proportionally higher or lower to the face area.
H. Minimum Media Area: The minimum net effective media area in square meter (square
feet) for each 600 mm by 600 mm (24 inches by 24 inches) (face area) filter at 150
m/min (500 fpm) face velocity shall be at least the values listed below. For other filter
sizes the net effective media area shall be proportionally higher or lower.
2. Access doors: Double skin insulated, at each end of the housing with
continuous gasketing on the perimeter and positive locking devices. Design
doors to withstand a minimum positive/negative 1.0 kPa (four inches of water)
static pressure.
Page 4 of 6
DIVISION 15-MECHANICAL Air Filters SPECIFICATION SECTION 15861
1. Minimum 1.6 mm (l6 gage) galvanized steel, 100 mm (4 inches) deep, factory
complete with hardware necessary for field assembly, suitable for either
upstream or downstream filter servicing. All members shall be cut to size and
prepunched for easy assembly into modules of the size and capacity noted in
the schedules.
K. Magnehelic Differential Pressure Filter Gages: Nominal 100 mm (four inch) diameter,
zero to 500 Pa (zero to two inch water gage) range, flush mounted in aluminum panel
board, complete with static tips, copper or aluminum tubing, and accessory items to
provide zero adjustment. Provide one gage for each extended surface filter section.
Provide Petcocks for each gauge.
PART 3 – EXECUTION
3.1 INSTALLATION
A. Clean and vacuum air handling units and plenums to the satisfaction of the Consultant
prior to starting air handling systems.
END OF SECTION
Page 5 of 6