CCO #002
In Process
DESIGNATED REVIEWER: REVIEWED BY:
DUE DATE: 05/05/2021 REVIEW DATE:
DESCRIPTION:
O-CE #006 - SCE / Bulletin 1 modifications Vault Room and VE Items Implemented by Ownership
SCE / Bulletin #1 & VE Plan Revisons
This Change Order is for the added doors related to the Bulletin one issuance changing the location of the vault room and added electrical room
door#116 and #124 and #123. This co also includes a deduction of a deleted door #117.
Reference: EP-3 Alta
ATTACHMENTS:
EP-3 (revised) Changes per Bulletin 1 plan set.pdf
CHANGE ORDER LINE ITEMS:
# Budget Code Description Amount
1 08-100.LS Doors and Frames.Lump Sum Bulletin 1 Door Changes $2,662.00
Grand Total: $2,662.00
CCO #002
The original (Contract Sum) $ 889,214.00
Net change by previously authorized Change Orders ($8,816.00)
The contract sum prior to this Change Order was $ 880,398.00
The contract sum would be changed by this Change Order in the amount of $ 2,662.00
The new contract sum including this Change Order will be $ 883,060.00
The contract time will not be changed by this Change Order by 0 days.
In Process
Thank you for this opportunity to submit this proposal for finish carpentry (addendum), labor and materials (based on
non-prevailing wage rate), on your Broadway & Magnolia project located at Long Beach, CA.
Changes based on Plan Set dated 1/31/2020 – Bulletin 1 and RFI #281
In Process
($4,407.00)
Set 33
Additional #116 & #124.1 Doors at 1st Floor: 18ga 3/0 x 7/0 Hollow Metal Flush
$3,296.00
door (Rating per Schedule) on 16ga HM Welded frame with HW Set 17
Additional Door #123 at 1st Floor: 18ga 4/0 x 8/0 Hollow Metal Flush door
(Rated) on 16ga HM Welded frame with Electrified Hardware (Falcon 25 series
$3,773.00
Rim Exit Device; Von Duprin 6300 series Electric Strike; Von Duprin PS902
Power Supply; Falcon SC81 Door closer; Hinges; Door stop; Weatherstrip)
TOTAL (ADD COST) $2,662.00
EP-3 (revised)
For additional information on your project, please contact Alex Rigor at 714-330-8624 / email: alexr@contractorsmail.com
Payment Schedule: 25% Exterior Jambs, 30% Material Drop, 35% Ready Paint, 10% Hardware Installation
All invoices are net 30 days of invoice date. A late charge of 1 1/2% per month is due on unpaid balances.
Respectfully Submitted
____________________
Alex Rigor
Acceptance of Proposal: Acceptance turns this document into a binding contract in which you personally guarantee to pay the amount of this
contract. The Owner/Builder will indemnify and hold this contractor harmless against any and all claims made related to this project. Payment is to
be paid within Ten (10) days at 100% no retention is to be taken. Purchaser personally guarantees to pay any and all cost, and attorneys fees
necessary to collect all past due amounts. Any past due amounts shall bear interest of 1-1/2% per month.
Contractor’s License: Contractors are required by law to be licensed and regulated by the California Contractors State License Board. Any
questions concerning a contractor may be referred to the registrar; Contractors State License Board at 9821 Business Park Drive, Sacramento,
California 95827, mailing address is P.O. Box 2600, Sacramento, California 92826