Professional Documents
Culture Documents
CE 509
CE509
CE Projects Design 2
SUBMITTED BY:
GROUP 15
LEADER:
LATORENO, JOSH KIRBY
MEMBERS:
HABITAN, JERICO O.
PADILLA, ALEXEJOY JAMES
VILLANUEVA, JEREMIAH
CE52S2
SUBMITTED TO:
ENGR. JENNIFER CAMINO
INSTRUCTOR
4.3.4.1 Ground Improvement Using Wet Soil Mixing
4.3.4.2 Design Process
START
Determine Settlement of
Structure
Computed
NO
Settlement <
Actual
Settlement
Scheduling
Estimation
End
4.3.4.3 Ground Improvement Using Wet Soil Mixing Using Lime
SOIL DATA
adhesion cu 0.97
SOIL STRESS
LOADINGS
Pv 103.65 kN Pv < Q
Q 122.73 kN Ok
SLIP SAFETY
Vult 64.04 kN Ok
The resulted economic sections for the design of ground improvement using Wet Soil Mixing as shown in
Table having a diameter of 0.6 m, horizontally spaced at 0.70 m and vertically spaced at 0.60 m
respectively. The Length of the columns is 0.3 m.
The designers use a typical footing in order to design the stone columns. The total number of stone
columns used was the number of columns used multiplied to the number of footing of the structure.
Figure: Layout Plan – Wet Soil Mixing