You are on page 1of 9

Đề thi trắc nghiệm chương 2 và 3

Câu Hỏi 1
Đúng
Đạt điểm 1,00 trên 1,00

Đặt cờ
Đoạn văn câu hỏi
When computing standard cost variances, the difference between actual and standard price
multiplied by actual quantity yields a(n):
Select one:

a.
price variance.

b.
quantity variance.

c.
Combined price and quantity variance.
 

d.
efficiency variance.
Phản hồi
Câu trả lời của bạn đúng
The correct answer is:
price variance.

Câu Hỏi 2
Đúng
Đạt điểm 1,00 trên 1,00

Đặt cờ
Đoạn văn câu hỏi
Poor quality materials could have an unfavorable effect on which of the following variances?
 
Select one:

a.
Labor Efficiency Variance: No           
Material Quantity Variance: Yes
                            
 

b.
Labor Efficiency Variance: Yes      
Material Quantity Variance: No
               

c.
Labor Efficiency Variance: No
Material Quantity Variance: No
              

d.
Labor Efficiency Variance: Yes             
Material Quantity Variance: Yes
                                      

Phản hồi
Câu trả lời của bạn đúng
The correct answer is:
Labor Efficiency Variance: Yes             
Material Quantity Variance: Yes

Câu Hỏi 3
Đúng
Đạt điểm 1,00 trên 1,00

Đặt cờ
Đoạn văn câu hỏi
The following labor standards have been established for a particular product:
Standard labor-hours per unit of output ............. 2.4 hours
Standard labor rate.............................................. $15.45 per hour
The following data pertain to operations concerning the product for the last month:
Actual hours worked ............5,400 hours
Actual total labor cost........... $85,860
Actual output ........................ 2,200 units
What is the labor rate variance for the month?
 
Select one:

a.
$2,430U

b.
$4,284U

c.
$1,908U

d.
$4,284F
Phản hồi
Câu trả lời của bạn đúng
The correct answer is:
$2,430U

Câu Hỏi 4
Đúng
Đạt điểm 1,00 trên 1,00

Đặt cờ
Đoạn văn câu hỏi
The direct labor standards for a particular product are:
4 hours of direct labor @ $12.00 per direct labor-hour = $48.00
During October, 3,350 units of this product were made, which was 150 units less than budgeted.
The labor cost incurred was $159,786 and 13,450 direct labor-hours were worked. The direct
labor variances for the month were:
Select one:

a.
Labor Rate Variance       Labor Efficiency Variance
        $1,614 U                                  $600 U
 

b.
Labor Rate Variance       Labor Efficiency Variance
        $1,614 F                                 $600 U
 

c.
Labor Rate Variance       Labor Efficiency Variance
        $1,614 F                                 $600 F
 

d.
Labor Rate Variance       Labor Efficiency Variance
        $1,614 U                                 $600 F
 
Phản hồi
Câu trả lời của bạn đúng
The correct answer is: Labor Rate Variance       Labor Efficiency Variance
$1,614 F                                 $600 U

Câu Hỏi 5
Đúng
Đạt điểm 1,00 trên 1,00

Đặt cờ
Đoạn văn câu hỏi
A quantity of a particular raw material was purchased for $43,250. The standard cost of the
material was $2.00 per kilogram and there was an unfavorable materials price variance of
$3,250. How many kilograms were purchased?
Select one:

a.
20,000
b.
23,250

c.
24,875

d.
21,625
Phản hồi
Câu trả lời của bạn đúng
The correct answer is:
20,000

Câu Hỏi 6
Đúng
Đạt điểm 1,00 trên 1,00

Đặt cờ
Đoạn văn câu hỏi
Victoria Corporation uses a standard costing system in which variable manufacturing overhead
is assigned to production on the basis of the number of machine setups. The following data
pertain to one month's operations:
-    Variable manufacturing overhead cost incurred: $70,000
-    Total variable overhead variance: $4,550 favorable
-    Standard machine setups allowed for actual production: 3,550
-    Actual machine setups incurred: 3,500
The standard variable overhead rate per machine setup is:
Select one:

a.
$20.00

b.
$21.00

c.
$18.44
d.
$20.30
Phản hồi
Câu trả lời của bạn đúng
The correct answer is:
$21.00

Câu Hỏi 7
Đúng
Đạt điểm 1,00 trên 1,00

Đặt cờ
Đoạn văn câu hỏi
Mcgahen Medical Clinic measures its activity in terms of patient-visits. Last month, the budgeted
level of activity was 1,080 patient-visits and the actual level of activity was 990 patient-visits.
The clinic's director budgets for variable overhead costs of $3.30 per patient-visit and fixed
overhead costs of $10,600 per month. The actual variable overhead cost last month was $3,380
and the actual fixed overhead cost was $8,780.
In the clinic's flexible budget performance report for last month, what would have been the
spending variance for the total overhead cost?
Select one:

a.
$113U

b.
$297F

c.
$2,004F

d.
$1,707F

Phản hồi
Câu trả lời của bạn đúng
The correct answer is:
$1,707F

Câu Hỏi 8
Đúng
Đạt điểm 1,00 trên 1,00

Đặt cờ
Đoạn văn câu hỏi
Goy Corporation's flexible budget performance report for last month shows that actual indirect
materials cost, a variable overhead cost, was $28,194 and that the variance for indirect
materials cost was $1,887 unfavorable. During that month, the company worked 11,100
machine-hours. Budgeted activity for the month had been 11,200 machine-hours. The cost
formula per machine-hour for indirect materials cost must have been closest to:
Select one:

a.
$2.69

b.
$2.37

c.
$2.35

d.
$2.71
Phản hồi
Câu trả lời của bạn đúng
The correct answer is:
$2.37

Câu Hỏi 9
Đúng
Đạt điểm 1,00 trên 1,00

Đặt cờ
Đoạn văn câu hỏi
Mcgahen Medical Clinic measures its activity in terms of patient-visits. Last month, the budgeted
level of activity was 1,080 patient-visits and the actual level of activity was 990 patient-visits.
The clinic's director budgets for variable overhead costs of $3.30 per patient-visit and fixed
overhead costs of $10,600 per month. The actual variable overhead cost last month was $3,380
and the actual fixed overhead cost was $8,780.
what would have been the activity variance for the total overhead cost?
Select one:

a.
290F

b.
290U

c.
297U

d.
297F

Phản hồi
Câu trả lời của bạn đúng
The correct answer is: 297F

Câu Hỏi 10
Đúng
Đạt điểm 1,00 trên 1,00

Đặt cờ
Đoạn văn câu hỏi
Mcgahen Medical Clinic measures its activity in terms of patient-visits. Last month, the budgeted
level of activity was 1,080 patient-visits and the actual level of activity was 990 patient-visits.
The clinic's director budgets for variable overhead costs of $3.30 per patient-visit and fixed
overhead costs of $10,600 per month. The actual variable overhead cost last month was $3,380
and the actual fixed overhead cost was $8,780.
what would have been the total spending and activity variance for the total overhead cost?
Select one:

a.
1636U

b.
2004U

c.
2004F

d.
1636F
Phản hồi
Câu trả lời của bạn đúng
The correct answer is: 2004F

You might also like