GSI ORE PRODUCTION CONTROL WEEK-28 (JULI 2020)

13.232,00 111.984,00
PLAN CNI PLAN GSI DEVIASI PLAN
DATE ACTUAL GSI DEVIASI PLAN CNI WTD MTD YTD
(WMT) (WMT) GSI
6-Jun 2.255,00 2.900,00 1.408 (847) (1.492) 1.408 14.640 113.392
7-Jun 2.255,00 2.900,00 1.552 (703) (1.348) 2.960 16.192 114.944
8-Jun 2.255,00 2.900,00 240 (2.015) (2.660) 3.200 16.432 115.184
9-Jun 2.255,00 2.900,00 (2.255) (2.900)
10-Jun 2.255,00 2.900,00 (2.255) (2.900)
11-Jun 2.255,00 2.900,00 (2.255) (2.900)
12-Jun 2.255,00 2.900,00 (2.255) (2.900)
TOTAL 15.785 20.300 3.200 (12.585) (17.100) 3.200 16.432 115.184

Target WTD CNI 15.785 →→→ Balanced WTD & Achievement (12.585) 20% WMT - %
Target WTD GSI 20.300 →→→ Balanced WTD & Achievement (17.100) 16% WMT - %

Target MTD CNI 40.016 →→→ Balanced MTD & Achievement (23.584) 41% WMT - %
Target MTD GSI 80.000 →→→ Balanced MTD & Achievement (63.568) 21% WMT - %

UPDATE PRODUKSI DAILY UPDATE PRODUKSI WEEKLY UPDATE PRODUKSI MONTHLY


22-28 JUNI 2020 WEEK 28 JULI 2020
18,00 3.500

16,00 16 % -17.100 WMT


3.000
2.900,00 2.900,00 2.900,00 2.900,00 2.900,00 2.900,00 2.900,00 20.300 20.300 20.300 20.300 20.300 20.300 20.300 80.000 80.000 80.000 80.000 80.000 80.000 80.000
14,00
2.500
12,00 21%
2.255,00 2.255,00 2.255,00 2.255,00 2.255,00 2.255,00 2.255,00 15.785 15.785 15.785 15.785 15.785 15.785 15.785

10,00 2.000
20% -63,568 WMT
1.552 17,00
8,00 1.500 40.016 40.016 40.016 40.016 40.016 40.016 40.016
1.408 -12.585 WMT
6,00 11,92
11,07 -23,584 WMT
1.000
4,00 7,90
2.960 3.200 14.640 16.192 16.432 41 %
5,62 5,30 500 1.408
2,00
240
6-JUN 7-JUN 8-JUN 9-JUN 10-JUN 11-JUN 12-JUN
0,00 - 6-JUN 7-JUN 8-JUN 9-JUN 10-JUN 11-JUN 12-JUN
6-Jun 7-Jun 8-Jun 9-Jun 10-Jun 11-Jun 12-Jun
Monthly Cummulative Target Monthly GSI
Total Hujan Total Slippery Weekly Cummulative Target Weekly GSI
ACTUAL GSI PLAN CNI (WMT) Target Weekly CNI Target Monthly CNI
GSI DOME CONTROL

No Dome Total Barging Remain


22 G-022 5.481,302 CLOSE TOTAL BARGING DAN ACTUAL DOME
23 G-023 1.829,316 CLOSE 7.000,000
24 G-024 4.850,530 CLOSE
25 G-025 4.879,623 CLOSE 6.000,000 5.616,000
26 G-026 3.584,856 CLOSE 5.000,000
27 G-027 6.264,700 711,310
28 G-028 5.366,500 2.056,800 4.000,000
29 G-029 5.616,000 3.008,000 2.944,000
30 G-030 3.008,000 3.000,000
31 G-031 1.424,000 2.056,800
2.000,000 1.424,000
32 G-032 2.944,000
1.000,000 711,310
0 0 0 0 0
0,000
G-022 G-023 G-024 G-025 G-026 G-027 G-028 G-029 G-030 G-031 G-032

Total Barging Remain

PRODUKSI CONTROL
July 16.432,00
TOTAL (wmt) 101.052,463 15.760,110
June 2.352 36.864

Total Hujan dan Slippery WEEK 28 May


880
9.472 36.272

Date Total Hujan Total Slippery April 24.208


1.440 22.096
6-Jun 5,62 11,92 1.408
March 10.544
7-Jun 5,30 11,07 3.760

8-Jun 7,90 17,00 - 5.000 10.000 15.000 20.000 25.000 30.000 35.000 40.000
ACTUAL ORE ACTUAL OB ACTUAL TOP SOIL
9-Jun
10-Jun
11-Jun
12-Jun BARGING WEEK 28 (JULI 2020)
Total 18,82 39,99
BG. GHANI NAILA
Maintenance Rampdoor VS Barging
Maintenance 6.000,000
Date Rampdoor
TARGET Barging BG.
6-Jun 5200 5.208,363 BG. GHANI NAILA 5.000,000
7-Jun
4.000,000
8-Jun
9-Jun 3.000,000
10-Jun
2.000,000
11-Jun
12-Jun 1.000,000

6-Jun