Professional Documents
Culture Documents
1.0 SCOPE
10.0 CABLING
10.1 Cable Installation
10.2 Cable Requirements
10.3 Cable Systems
10.4 Cable Bending Radius
10.5 Cable Cleating and Strapping
10.6 Cable Splicing
10.7 Temporary Cables
10.8 Cable Glands/Multi Cable Transits
10.9 Cable Glands Selection
10.10 Junction Boxes
10.11 Cable Termination
10.12 Spare Conductors
11.0 EARTHING
11.1 General
11.2 Main Earth Reference
11.3 Protective Earth
11.4 Instrumentation and Telecommunication Earth
11.5 Equipotential Bonding
11.6 Earth Bar and Earth Boss
14.0 MATERIALS
14.1 Equipment Materials
14.2 Junction Boxes
14.3 Cable Support Systems
14.4 Equipment Brackets and Supports
14.5 Earth Bosses
14.6 Fixing Materials
14.7 Precautions against Galvanic Corrosion
1.1 This specification describes the minimum requirements for the work to be performed by the
Electrical/Instrumentation (E&I) Contractor in order to properly install, test and put in operation the electrical
power, lighting control, earthing and other required systems for a production facility which will be/is located Ithe
Dutch Sector of the North Sea.
1.2 All conflicts between the requirements of these relevant documents or package shall be referred to Company
for clarification.
1.3 The omission from this specification of any item or items essential for the correct functioning of any part of the
specified equipment shall be brought to the attention of Company. Failure to do this shall not absolve the
Contractor from installing the equipment complete in every respect.
1.4 All substitutions and deviations from this specification shall be highlighted by Contractor who shall notify
Company in writing of requested substitutions or deviations. Contractor shall not proceed with any such
substitution, installation or purchasing prior to receiving Company's written approval.
1.5 Contractor shall not carry out any testing or pre-commissioning of equipment or bulk items without submitting
prior notification to Company. Company reserves the right to witness all testing (functional, running, meggering,
or otherwise) and pre-commissioning.
1.6 It shall be Supplier's responsibility to be, or to become knowledgeable of the requirements of the specified
Standards and Codes. Any alterations or changes to the equipment to make it meet the aforesaid requirements
shall be at the expense of the Supplier.
1.7 As used in this specification, the terms and phrases listed below are defined as follows:
Supplier : The firm or person(s) contractually responsible to Company for the assembly, performance and
quality of the unit(s) described herein.
Company : GDF SUEZ E&P Nederland B.V.
Contractor : Party to whom the fabrication, installation, hook-up and commissioning are assigned.
The requirements of the standards, codes and supplemental specifications listed below shall be met unless
specially excluded by this specification and specifications referred to herein.
Latest revision of above referenced specifications can be found on www.gdfsuezep.nl under downloads.
All equipment specified herein shall conform in design, material and performance with the latest editions (with
amendments) of the following Codes and Standards current at time of order placement.
Directive 94/9/EC (ATEX 95) Equipment and protective systems intended for use in potential explosive
atmospheres.
The latest CENELEC standards.
The Regulations of “Het Nederlandse Normalisatie Instituut“ (NEN) as applicable as such but not limited to:
2.3 Certification
Equipment located in hazardous areas shall be certified in accordance with ATEX directive 94/9/EC. Only
equipment with certification issued by the notified bodies will be accepted.
Equipment shall, in all respects, be suitable and/or protected for operation in service conditions typical for
platforms in the North Sea and in a humid, saliferous and corrosive atmosphere. Unless otherwise specified in
the Request for quotation and/or Purchase Order, equipment shall be suitable for use under the following
conditions:
3.2 Indoors:
Maximum temperature : +35°C
Daily average temperature : +20°C.
Minimum temperature : not lower than +5°C.
Relative humidity : up to 90%
Air quality : saline.
3.3 Outdoors:
Maximum temperature : +26°C.
Daily average temperature : +15°C.
Minimum temperature : -20°C.
Relative humidity : up to 100%.
Air quality : saline and moist.
3.4 Altitude
The altitude will not exceed 1000 meters above Mean Sea Level.
The power supplies on the "existing" platforms constructed before 2005 are as follows:
6 kV AC, 3 phase, 3 wire, 50 Hz, un-earthed IT system in accordance with NEN 1041
380V, 3 phase, 4 wire, 50 Hz, TN-C-S system in accordance with NEN 1041
220V, 1 phase, 2 wire, 50 Hz, TN-S system in accordance with NEN 1010
24V DC, 60V DC, 110V DC, Battery systems, IT system in accordance with NEN 1010
48V DC, Battery systems, TT system in accordance with NEN 1010
NOTE 1: Company shall indicate if platform is an existing or new location
The one line diagrams provide further details of platform electrics; supply voltages, fault levels etc.
Electrical devices shall be selected on the basis that a 15% voltage dip of two seconds duration does not cause
the equipment to shutdown.
The furnishing of all labour, supervision, tools and test equipment required for the installation and testing
of the complete E&I system as per contract.
The equipment is to be stored in a dry, heated store and handled in such a manner that upon final
installation all materials and equipment reflect ex-factory finish, appearance and performance.
The testing and adjustment of all E&I equipment and material, including equipment and material furnished
by others.
The furnishing of temporary electrical facilities that the Electrical Contractor may require for his operations
under this contract.
The notification to the Company's representative at least 1 working week prior to performing any test for
final equipment acceptance.
The notification to the Company's representative, as soon as possible, about the failure of any material,
equipment or system to pass a test.
The documentation and certification of all tests and submission of these tests to Company's representative
after each test is performed.
All certificates of delivered equipment shall be submitted to the Company's representative.
The E&I installation shall in every respect be in accordance with the drawings and specifications which cover
the electrical and/or instrumentation work.
The E&I plan drawings accompanying this specification are diagrammatic in nature and do not indicate exact
and complete routes of raceways and wiring. The location of electrical equipment is approximate and subject to
minor corrections.
No measurements of a drawing by scale shall be used to establish dimensions for installation purposes. When
not dimensioned, exact locations are to be defined in the field and shall be satisfactory to Company's
representative.
Contractor shall be guided in his work by drawings of other trades, by architectural and structural drawings and
by Supplier's equipment drawings.
Contractor shall mark-up one set of drawings indicating as-built conditions. During the project Contractor shall
keep an up-to-date record of all changes in the E&I installation and indicate these changes on the relevant
drawings. Company shall have access to these documents at all times.
The following colour code will be used:
Red = out
Blue = in
Yellow = correct
Contractor shall produce all shop-drawings as can be regarded practical to clarify specific installation details.
These drawings shall be returned to Company's representative after completion.
The addition of specifications or drawings to the list will not constitute extra cost if it merely amplifies and/or
clarifies information already shown on previous drawings.
When work is to be done in an area where a fire or explosion hazard exists, a permit in writing from Company or
his representative shall be obtained before flames of any kind, sparking tools or any other means of possible
ignition are employed in the area.
Platform operating conditions may preclude the issue of a permit immediately upon application and Contractor
shall give reasonable notice of his requirements. Applications for permits shall be made during normal staff
hours.
Contractor shall provide electrical safety equipment as required and in such a manner as provide safety
protection for all personnel in the area of work.
Contractor shall be responsible for the suitability and safety of the equipment used by him, and no equipment
shall be used which may be unsafe or likely to cause damage.
Certain low voltage control circuits may require work to be performed while energized. Changes to or
modification of energized power circuits shall be done only after clearance of the lines and equipment by
Company's representative.
When work is to be done on part of the main electrical distribution system which is energized, Contractor shall
not commence work until he has received a written permit from Company's representative to the effect that it
is safe to do so. When the work is completed, Contractor shall sign the permit to that effect and return it to the
Company's representative.
Contractor shall not operate switchgear forming part of the main distribution system or otherwise interfere
with its operation.
No apparatus whatsoever shall be connected and made live without notification to Company's representative.
Where several approved manufacturers are shown for one type of material, all material of that type is to be of
the same manufacturer.
All materials, equipment and methods of installation shall be approved by Company's representative.
Where specific manufacturers are mentioned in the specifications or drawings without qualification as to an
alternate, only that particular make or catalogue number, etc. will be acceptable to Company's representative.
Contractor shall be responsible for furnishing all material and equipment necessary to complete the E&I
installation in accordance with the specifications and drawings.
Contractor shall also furnish and install all material and equipment which is not specifically mentioned or shown
but which is necessary for a proper, complete electrical service.
Concealed work shall be left open for inspection and test until approved by Company's representative.
Contractor shall carry out all installation work with competent tradesmen with experience in this type of
installation. Contractor shall provide competent technical supervision. The complete installation shall be of the
highest grade and carried out in accordance with the relevant rules and regulations herein specified, and
executed to the satisfaction of Company.
Upon request training certificates shall be handed over. (NEN 1010, NEN 1041, NEN 3140, NEN 3840, ATEX
etc,)
All tools, installation and testing equipment shall be provided by Contractor for his use. Where special tools are
recommended by any equipment manufacturer, Contractor shall conform to such recommendations.
Any equipment damaged or broken on site shall be replaced or repaired by Contractor at his cost.
The equipment will be located in either a safe, or a potentially explosive atmosphere. Each area will be
classified as shown on the Hazardous Area Drawings.
However, all outdoor equipment including HVAC equipment shall be classified for use in hazardous areas,
equipment and wiring must comply with the NEN-EN-IEC 60079-14.
EX’n’ equipment shall not be used.
Deviations are subject to written approval by Company.
As minimum requirement equipment shall be suitable for gas group IIB, temperature class T3.
Equipment installed inside battery rooms shall be suitable for gas group IIC or IIB+H2, temperature class T3.
In case the requirement cannot be fulfilled, Contractor/Supplier shall be subjected for approval by Company
Where certified or approved equipment is not available to meet the specific requirements of a classified area,
equipment certified or approved for a more hazardous condition shall be employed, (i.e. when Zone 2
equipment is not available, Zone 1 equipment shall be used).
Depending on the location of the equipment or Packaged Units, one of the following degrees of protection of
the enclosure against contact with live or moving parts and against ingress of solid foreign bodies and liquids
shall be selected in accordance with IEC 60529.
Indoors IP-41;
Outdoors IP-56 as a minimum.
All equipment and materials shall be installed in accordance with the relevant drawings and this specification.
Any variations from the proposed positions shall be agreed in writing with Company prior to installation.
Control stations and safety switches with padlock facility in off mode, for motors and equipment shall be
located as near as possible to the subject motor or equipment.
Electrical control components shall be located so as to be accessible from aisles and walkways used in normal
operation. They shall be mounted with their centre lines at approximately 1200 mm above the platform or
floor.
Sufficient free space for maintenance and escape routes shall be maintained in accordance with the
applicable regulations or standards.
5.1 General
Ex-certified equipment shall be selected in compliance with the applicable standards and area classification
drawings.
Electrical equipment shall, unless unavoidable due to the functionality or necessity, be installed indoor and
away from hazardous areas.
Pressure and deltaP transmitters, which have to be installed outdoors, shall be sheltered by use of enclosure.
Final location shall be selected to avoid interference with escape routes, walkways, other equipment, pipes,
etc. and obstruction against activities related to transport and lifting operations.
Equipment shall not be supported on pipe work, handrails, access ladders or cable ladders. Lighting fixtures
may, however, be mounted underneath cable ladders or as integrated part of handrail support arrangement.
Equipment such as warning lights, lighting fixtures and loudspeakers may be located on the support for cable
ladders and trays or cable ladder's side rail.
Equipment located in areas which do not allow for maintenance accessibility as required, shall as shown on
typical drawing be installed such that the equipment can be rotated, raised or lowered into areas where
maintenance can take place without the need for scaffolding.
All items of electrical equipment such as generators, switchgear, chargers, motors, etc., shall be installed on
prepared foundations by Contractor. The equipment Supplier's representative shall supervise where
appropriate. It shall be Contractor's responsibility to ensure that the prepared foundations are satisfactory
before the equipment is positioned.
Contractor shall install all items of equipment together with all necessary cables and racks.
Contractor shall supply all necessary drawings, guideline and typical installation drawings for all required
supports.
Contractor shall fabricate any supports necessary for such items as control devices, junction boxes, switched
lighting fixtures, panels, etc. These are to be fabricated from stainless steel plate, channel or angles as
necessary to the satisfaction of Company (for typical details see specification 613). All steel channel or angle
Iron supports shall be coated in accordance with coating specification 625, latest revision. All junction boxes
and switches shall be accessible from grade of walkway level.
Deviations are subject to written approval by Company.
Junction boxes shall be grouped together on separate junction box racks; the design is part of the scoop of
Contractor.
Company will give the approval for the final location and the design of the junction box racks.
Contractor shall install an engraved plastic nameplate to each item of electrical equipment. Each plate shall
indicate the equipment number and point of isolation and shall be securely and permanently attached to
equipment or supports of the equipment with stainless steel screws.
Execution of nameplates shall be as per nameplate detail drawing provided.
Tagging shall be effected in such a way that equipment certification is not affected. Contractor shall propose
alternatives to screws if fastening by screws will affect certification and Zone ratings.
Electrical equipment shall be aligned, levelled, plumbed and firmly secured to the nearest suitable firm steel
work. They shall not be bracketed to process lines, handrails, lattice, floors, etc.
Throughout the construction period, all equipment and materials shall be adequately protected where
necessary.
All couplings between motor and driven equipment shall be provided with personnel protection guards.
All equipment and installations shall comply with the electromagnetic compatibility requirements both in
emission and immunity.
To comply with EMC the above mentioned aspects have to be observed during the construction of electrical,
instrumentation and telecommunication installations.
The modules (blocks) contain a conductive foil which establishes a full 360º low transfer impedance contact
with the cable screen.
The frames shall be constructed of 316 stainless steel to make contact with the conductive foil of the module.
6.1 Lighting
The installation of the lighting system shall be based on the lighting arrangement drawings, and safety
requirements as well as visibility and visual satisfaction for persons working in the environment.
Contractor's scope of work shall include the complete design of the lighting circuits and the installation of all
lighting fixtures, junction boxes and feeder cables between the junction boxes and lighting fixtures.
Drawings provided by Company shall be used as base for this design (quantities e.g.).
Contractor shall be fully responsible for the commissioning of the lighting circuits (inclusive earth leakage
tests).
Lighting fixtures shall be in compliance with preferred Supplier list and/or relevant drawings.
Preferably fluorescent lighting fixtures shall be used.
6.1.2.3 Floodlights
In general floodlights shall be used for illumination of the main deck and the jacket of the platform and shall
be in compliance with the lighting arrangement drawings.
6.1.2.4 Lamps
The life time of the lamps of lighting fixtures shall be 70.000 hours as a minimum.
Special consideration shall be made with respect to the selection of the light colour. As much as possible
discrimination of colours shall be avoided.
6.1.2.5 Tagging
All lighting fixtures shall be tagged with a tag plate in compliance with the relevant lighting arrangement
drawings (panel nr. - group nr – next in line (L601-45/23)).
As-built information shall be handed over to Company.
6.1.5.1 The lighting system (with exemption of indoor and escape lighting fixtures) shall be switched off during the
night to prevent unnecessary presence of birds. This shall be accomplished by disconnecting the power to
the lighting fixtures by means of contactors installed inside the lighting distribution panel.
7.1 General
Contractor's scope of work shall include the complete engineering, design of the heat tracing circuits and the
installation of all heating tapes, junction boxes and feeder cables between the junction boxes.
Heat tracing design shall be handed over to Company for review before installation will start.
Contractor shall be fully responsible for the commissioning of the heat tracing circuits (inclusive earth leakage
tests).A complete test report shall be handed over to Company which includes the inrush current, voltage drop
and phase balance.
The P&ID's and Piping Line Lists indicate those pipes and associated items which are to be traced.
Installation of the heat tracing materials shall be as indicated on provided typical heat tracing details.
Contractor shall be responsible for both the final heat tracing detail as discussed in the Supplier installation
manuals and the preparation of the Electrical Heat Tracing Schedule.
Where heat tracing is pre-installed on Supplier skid packages it will be pre-wired to Supplier's skid mounted
junction boxes. Contractor’s scope of work shall include the installation of supply cables between these
junction boxes and the small power distribution board.
Heat tracing cables shall be strapped to equipment and pipes using glass fibre tape, spaced approximately at
300 mm intervals along pipes and as required elsewhere. Stainless steel straps, SST 316L, shall be used on
high temperature cables.
Heat tracing cables shall be installed along the lower semi-circle of the pipes.
Cables shall pass through thermal insulation from below or side on vertical pipes.
Heat tracing cables shall be installed in such a way that it allows dismantling of joints, valves, instruments, etc.
without cutting or damaging the cable.
Where the heat tracing cables are crossing flanges, thermal insulation covers or other sharp edges, protectors
of stainless steel 316L shall be used.
Heat tracing cables shall not be spliced.
Purpose made flexible stainless steel conduit shall be used for protection of the heat tracing cable between
stand alone junction boxes and insulation entry kit.
Flexible conduits protecting heat tracing cables shall be fixed to support approximately every 200 mm.
Heat tracing cables shall be 100% covered. Exceptions may be in instrument enclosures.
The heat tracing cable shall be protected against damage by applying an aluminium tape/foil on top of the
cable when cellular glass is used as insulation material.
Details of the routing of supply cables between the main junction boxes located on the various decks and the
heating circuits are not shown on the drawings and it is the responsibility of Contractor to establish the most
satisfactory routes for the various cables and to supply and install any additional racks or trays required.
Main junction boxes shall be installed and accessible from grade or walkway level.
It is allowed to install heat tracing main junction boxes on E & I main junction boxes racks.
Junction boxes shall be installed directly to pipes by means of appropriate brackets (316 SS) or on steel
supports adjacent to the pipe or instrument.
Prior to final installation of control valve and other in-line instruments, process lines shall be properly flushed.
Each instrument shall be available for maintenance and disconnection without interfering with the process.
The installations shall be arranged so that it can be heat traced and thermal insulation applied.
All indicating instruments are to be located between 1 – 1.8 m above grating.
Direct mounted instruments shall be used whenever applicable.
Impulse tubing shall be as short as possible and be installed so that gas/liquid pockets are avoided.
Instruments shall be installed below tapping point for liquid service and above tapping point for gas service.
For some installations use of direct flange mounted capillary tubing may be considered.
Instrument panels and control cubicles shall be supported by pre-fab skids of UNP-100 channel. Unless
otherwise specified, these supports (skids) shall be delivered, supplied and designed by Contractor. The
supports shall be coated in accordance with the Painting and Coating Specification 525 prior to installation.
Contractor shall be responsible for correct alignment, levelling, plumbing and securing of the panels.
In case the instruments have been removed from the panel for shipping purposes, Contractor shall re-install
and re-connect these instruments.
Instrument and accessories shall be installed and connected in accordance with the hook-up and instrument
lay-out drawings and manufacturer's instructions. Lay-out drawings shall be used as guidelines, exact
locations shall be determined in cooperation with Company.
Instruments shall be mounted such that there is sufficient space around the installation to provide for ease of
installation, removal and maintenance. Where used, instrument housings shall be of sufficient size to provide
these requirements.
Instrument housing shall be supplied with explosion proof SS 316L self-limiting electrical heating element.
All locally mounted instruments shall be mounted as near to the point of measurement as possible and placed
in an accessible location. Close-coupling shall be used where practical, but otherwise the instrument shall be
"stand-mounted" with the centre line 1.4 metres above grade or walkway.
Instruments shall not impede process operation or access.
For services subject to vibration, the impulse lines to the instruments shall be provided with damping devices
e.g. pulsation dampeners (siphon) and capillaries.
Instruments shall be aligned, levelled, plumbed and firmly secured to the nearest suitable firm steelwork. They
shall not be bracketed to process line, handrails, lattice floors etc.
Equipment supports shall be delivered, supplied and designed by Contractor, after approval of the fabrication
drawings by Company.
Throughout the Work, instruments shall be adequately protected where necessary by weather and fireproof
coverings of an approved type.
All bolts, nuts and washers shall be 316 stainless steel (A4).
8.3.3 Tubing.
316L Stainless steel imperialized compression type fittings shall be selected for the applicable pressure
ratings specified and sized for the tubing described above and shall be installed in strict accordance with the
manufacturer's recommendations. Fittings shall be manufactured by “Swagelok”.
Contractor shall insure that all instrument fitters are certified for “Swagelok” twin ferrule fittings.
All tube connections shall be inspected by a third party invited by Company.
Contractor shall correct all deviations as indicated in the third party inspection report.
Threads for screwed connections shall be cut only with sharp thread cutting tools and by application of cutting
oil during operation.
Only NPT type threads shall be used for screwed connections. The thread cutting shall be in accordance with
API Code for threading.
Before make-up of threaded joints, threads shall be brushed, cleaned and sealed, using a method approved by
Company applied to the male portion. Care shall be taken to ensure that no sealant material enters the pipe.
The number of joints in tubing shall be kept to a minimum, consistent with good practice. All shall be made
with the aid of approved tubing benders, correct for the size of tube being worked, to ensure neat serviceable
bends.
Tubes shall be run in vertical and horizontal planes as far as possible and shall be run with the minimum
number of changes of direction consistent with the good practice and neat appearance. Horizontal runs shall
have the tubes mounted one above the other.
No tubing shall be installed in such a way that it is subject to vibration or any other mechanical stress.
All tubing shall be de-burred properly after cutting (preferably with a de-burring drill on a drilling machine). After
de-burring process, all tubing shall be cleaned by blowing through with filtered dry and oil-free compressed air
before connection to instrument.
The installed, but not connected, tubes shall have their ends capped to prevent the entry of foreign material.
All instrument tubing connected to process piping shall be run with a slope of not less than 1 to 12, except
where otherwise specified. The slope shall be down from the tapping points for liquids and up from the tapping
points for gas service.
Contractor must pay special attention to the correct location of vents and drains to ensure that they are
respectively at the highest and lowest point of tubing runs. All drains shall be connected to the closed drain
systems or plugged by an isolation valve.
Instrument air supply to instruments may need to be filtered and the pressure to be reduced via an air
filter/regulator set. Contractor shall supply and install the required air filter/regulator according to the hook-up
drawings. The filter/regulator set shall have a stainless steel body.
No component of any other tube fitting manufacturer will be interchanged or intermixed with the four
components (body, nut, front ferrule and back ferrule) of the tube fitting.
Do not use medium-pressure nut and ferrules with any standard tube fittings or vice versa.
Tubing shall be flushed and pressure tested by Contractor as listed below:
Flushing
Flushing shall be carried out on hydraulic systems, with exception of the hydraulic cabinets and wellhead
control panels since they have been flushed by the panel Supplier. All hydraulic lines shall be flushed to a
minimum cleanliness level to ISO 4406 class 15/12 (equal to NAS 1638 class 6).
Prior to commencement a flushing procedure shall be issued for review to Company (flushing procedure can be
part of the system test procedure). Flushing samples shall be analyzed by a Notified Body. Flushing reports and
records of samples shall be available for review during FAT.
Items that could be damaged due to flushing shall be removed or by-passed during flushing. Items which
create high restrictions due to orifice dimensions shall be removed or by=passed.
When the flushing is completed the tubes remain filled and all connection shall be plugged with metal plugs. In
case s different flushing fluid is used this shall removed and tubes shall be blown out with dry nitrogen.
Important note :
All installed components such as valves; regulators shall be suitable to operate without problems with oil
cleanliness to ISO 4406 class 19/16 (equal to NAS 1638 class 10)
For continuously supporting five or more single tubes, one 316L SS cable tray shall be used.
For continuously supporting four or less single tubes, 316L SS angle bar (50 x 50), or 316L SS Unistrut channel
shall be used.
The tubing shall be secured to the tray with "STAUFF" type PP-ACHV (white) fastening blocks at (maximum) 0.6
metres intervals. Blocks with stainless steel cover plates, bolts and nuts shall be delivered and supplied by
Contractor. To prevent corrosion between the "Stauff" blocks and the SS tubing, Molykote 111 shall be applied
on top and bottom "Stauff" block before the installation of the top "Stauff" block. After fasting the bulging
should be removed.
This shall be done on all “Stauff” blocs (e.g. process, instrument air and hydraulic tubing).
Contractor shall ensure that all “Stauff” blocks (including Company supplied items) shall be kept clean and free
of dirt, dust and blasting grid during fabrication, Company shall have the right to supervise the preventive
measures and precautions carried out by Contractor.
In case of any doubt “Stauff: blocks shall be reinstated by Contractor.
The supports shall be fabricated by Contractor (or supports to be made of SS 316L), including coating in
accordance with the Painting and Coating Specification 525. Coating shall be finished before installation of
supporting materials. The required small mounting materials and consumable items shall be delivered and
supplied by Contractor.
Capillaries of filled systems shall run independently of all other lines and shall be continuously supported using
316L SS angle bar (refer to 6.7.4) 316L SS Unistrut channel with adequate fastening clamps or tie-wraps at
0.25 m intervals. Adequate means of protecting capillaries from damage shall be employed. Special care shall
be taken against kinks in the capillaries on bends or changes of direction.
Cable trays shall be run with the width of the tray in a horizontal plane. A short section may be run with the
width in a vertical plane after Company's approval. In this case, additional support shall be provided to prevent
sagging.
Under certain circumstances and with Company's approval, trunking or conduits may be used instead of cable
trays. The required materials shall be delivered and supplied by Contractor.
Unless otherwise specified, the process pipelines and handrails shall not be used to support instrument
pressure and air piping and tubing.
Process equipment, rotating equipment and electric motors which are liable to vibration shall not be used to
support instrument tubing.
Multi-core transit, insert frames and blocks, supplied by Contractor, shall be provided after piping or tubing
installation, in accordance with the drawings or when required by Company.
8.4.1 Company shall supply to Contractor, instrument equipment and installation materials which are listed in the
instrument listings and as tabulated in the contract document.
Contractor shall be responsible for proper handling, storage, condition and protection of the materials supplied
to him.
On receipt of equipment, Contractor will check for compliance with the specifications and instrument data
sheets. Non-compliance or damage to equipment supplied to Contractor shall be reported to Company
immediately.
Subsequent deficiencies or damage becomes the responsibility of Contractor.
8.4.2 Contractor shall design, supply and install all items of material and equipment and all services which are not
expressly stated in the specifications or drawings as being supplied by Company or by Others (e.g. cables,
supporting materials, angle bar, conduit, pipe, structural steel etc.) in order to complete the entire instrument
installation. All Contractor designed and/or supplied materials and services shall be subjected to Company’s
approval.
8.4.3 Contractor shall supply all consumable materials such as, but not limited to, electrical insulation materials,
bolts and nuts, clamps, clips, tie-wraps, relief’s, wire markers, cable lugs, welding rods, crimp connector etc.,
unless specifically listed in the list of materials.
8.5 Identification
8.5.1 All major equipment shall be provided with nameplates by the manufacturer with Manufacturer's and Industry
Standard Data. Additionally, all equipment shall be properly marked with nameplates of an approved type,
indicating the tag number as assigned on the drawings.
8.5.2 All instrument and control devices shall be properly marked with a nameplate, fixed to the support of the
instrument or control device, describing the tag number and the function of equipment as assigned on the
drawings. The tag plate including support shall be in compliance with drawing as per specification 613.
8.5.3 All electrical terminals, wiring and terminal strips, shall be identified. Each cable shall be marked at both ends
with proper approved type markers (not dymo-tape), outside the terminal boxes or panels. Terminal boxes shall
be marked inside and outside the box.
8.5.4 All nameplates shall be supplied and installed by Contractor. The nameplates shall be of "RESOPAL" yellow-
black-yellow laminated and fitted on a stainless steel brackets, which shall be mounted to the nearest
steelwork or process pipeline. The nameplates shall have slotted holes and be fixed with stainless steel screws.
Nameplates to be fixed to explosion proof type equipment shall be glued with cyanoacrilate or other certified
means (and under no circumstances screwed).
8.5.5 Contractor shall ensure that all identification and marking corresponds to the drawings. Where no
identification or markings appear on the drawings, as-built drawings showing identification and markings must
be supplied.
8.5.6 All single and multi-core transmission tubing shall be properly marked in an approved way with the
identification numbers assigned on the drawings. Each multi-core tubing shall be marked at both ends, outside
the terminal boxes or panels. Each tube shall be marked with the bulkhead number to which the tube will be
connected. All tubing and tubing run markings shall be noted on as-built drawings to be supplied by Contractor.
Public Address and Alarm System equipment shall be located above deck level as follows:
Loudspeakers, 2000-3000 mm.
Warning lights maximum 3000 mm.
Intercom stations in process areas ± 1700 mm.
Loudspeakers shall not be located above suspended ceilings or behind obstructions which will hinder free
space sound distribution.
Loudspeakers shall be installed on brackets which allow for future adjustments as follows:
At the horizontal plan, 180°
Downwards 90° from the vertical plane.
RJ45 socket:
Type 8(8) : UP0 RJ45 Jack conform EIA/TIA 568A or B
Endurance : > 750 plug-in cycles per IEC 60603-7
IDC connector : AWG 26-22 isolation
Contact springs : CuCn
Contact surface : Ni + Au
Nominal current : 1A
Core identification in the form of coloured or numbered conductor insulation as specified shall be strictly
observed. The same colour or number shall be used for equivalent terminals where identical duties are
involved.
All cables shall be identified at each gland termination by the use of the specified tags by their respective
numbers, as indicated on the Cable Schedule.
Cable supported on cable tray or cable rack shall be securely fixed as defined below:
All cables shall be fastened to the cable rack with coated stainless steel ty-raps, spaced 1 metre apart for
vertical runs and 1.5 metres apart from horizontal runs.
All HV and LV single core power cables shall be secured to cable rack using non-magnetic trefoil clamps
spaced 0.9 m for vertical runs and 0.3 m for horizontal runs. Trefoils clamps shall be supplemented by plastic
coated stainless steel straps.
Cables run on cable tray or rack may be installed in layers. Power cables shall not be stacked more than 3
layers deep. Control and instruments cables shall be installed in a neat and orderly manner and shall be
adequately secured by the methods detailed above. Cables shall be installed on racks in accordance with the
drawings, but as a general rule the following shall apply:
a) High voltage power cables on rack.
b) Low voltage power and motor control cables may be installed on the same rack.
c) Low voltage lighting and small power cables may be installed on the same rack.
d) Cables carrying continuous information signals (i.e. analogue or digital transmissions), instrument DC
supplies, fire and gas cabling, intrinsically safe circuit cabling and general instrumentation cabling shall
be installed on a dedicated instrument rack.
Cables passing through floors or other positions via cable transits where they are liable to mechanical damage
shall be protected up to 150 mm above floor level to Company's satisfaction, as per installation drawings.
In general cables shall not be installed when the ambient temperature is below 4ºC.
Cables shall not be run adjacent to any heated pipes or ducts. Where crossing above heated pipes or ducts is
unavoidable, the cables must be kept at least 150 mm from the outer surface of insulation of such pipes or
ducts. Alternatively, a heat barrier such as Durasteel shall be installed to protect the cables from exposure to
excessive heat.
All cables shall be of one continuous length from outlet to outlet and glanded at both ends. No splices shall be
permitted in the cable between boxes or equipment.
All cable cores shall be copper stranded. Solid core cables shall not be used.
Contractor shall supply 20% spare terminations in all junction boxes and equipment in his supply.
Access for maintenance and an orderly layout shall be ensured when cabling below raised floor is performed.
Once a cable has been cut, a protective cap/sealing shall be applied on the end, when being exposed to humid
atmosphere.
All cable entries to equipment located outdoors and in wash down areas shall be from below. Top entry is not
allowed and side entry shall be provided with drip nose.
Sufficient cable spare length shall be provided for equipment which needs future adjustments (floodlights,
loudspeakers, etc.) or where equipment has to be dismounted for maintenance and calibration without
disconnecting the cable.
General instrumentation.
Fire and Gas.
ESD.
Telecommunication.
DCS.
Foundation Fieldbus.
General Electrical (control).
Powered Outputs.
Cable without armour may be used for lighting and small power installation inside the living quarter.
Cable without armour is subject to written approval by Company.
Fire resistant cables shall be used whenever required as mentioned on the cable list provided by Company.
Where the cable support systems are installed horizontally one above the other, the cable network shall be
arranged from top to bottom, system 1, system 2 and system 3.
Cable ladders installed horizontally shall have sufficient space to facilitate cable pulling and
cleating/strapping.
Instrument and telecommunication cables shall be separated from low voltage power cables and high voltage
cables by minimum 300 mm.
Instrumentation and telecommunication cables may be routed on system 2 cable support systems when the
defined distance between the individual systems can be kept.
When separation of the cable systems specified above is not possible or practical, a metal segregation barrier
shall be installed to avoid induced disturbances on the instrument/telecommunication cables.
Non IS, IS instrument cables and Foundation Fieldbus shall be routed on the same cable ladders/trays,
segregation is required.
System 1
According to : Standard
: IEC:60092-354
: IEC:60092-351
: IEC 60092-359
: IEC 60228 class 2
: IEC:60332-1
: IEC:60332-3-22
: IEC 60502-02
: IEC 60754-1,2
: IEC:61034-1.2
According to : Standard
: IEC:60092-354
: IEC:60092-351
: IEC 60092-359
: IEC 60228 class 2
: IEC:60332-1
: IEC:60332-3-22
: IEC 60754-1,2
: IEC:61034-1.2
According to : Standard
: IEC:60092-351/353 (≤300mm2 ) or
: IEC 60502-1 ( ≥ 300mm2 )
: IEC 60092-359
: IEC 60228 class 2
: IEC:60332-1
: IEC 60754-1,2
: IEC:61034-1.2
According to : Standard
: IEC:60092-351/359/376
: (2003-05)
: IEC 60228 class2
: IEC 60332-3-22
: IEC:60332-1
: i-1,2EC:60754-1.2
: IEC 60754-1,2
: IEC:61034-1.2
According to : Standard
: IEC:60092-351/359/376
: (2003-05)
: IEC 60228 class2
: IEC 60332-3-22
: IEC:60332-1
: i-1,2EC:60754-1.2
: IEC 60754-1,2
: IEC:61034-1.2
According to : Standard
: IEC:60092-351/359/376
: (2003-05)
: IEC 60228 class2
: IEC 60332-3-22
: IEC:60332-1
: i-1,2EC:60754-1.2
: IEC 60754-1,2
: IEC:61034-1.2
CAUTION FIBRE OPTICS I ACOLAN N6731 24G-50/125-OM3 I PUR INCOR-P I <length mark>
Category : CAT7
According to : EN 50288
IEC 61156
Modbus
Operating I Faber 100543 – 1x2x1.0: I PUR
temperature INCOR-P
-30 to +80°C. I <length mark>
Trunking or conduits may be used for special mechanical protection of single field routed cables for shorter
distances (approximately 5 m.). Where conduits are used, they shall be installed with open ends.
A computer based cable routing system reflecting the layout of the main cable support system (i.e. cable
ladders with width 300 mm and above) represented by ladder segment references, transit numbers, etc. and
necessary describing information related to the individual cable including its route, shall be used in the design.
Secondary cable routing shall be designed by Contractor (i.e. cable ladders up to 300mm or
“scheepsladderbaan”).
Field cables may utilise the main cable support system provided the route of the individual cable is being
registered in the routing system and the filing and loading of the main cable support system is acceptable.
The cable ladders shall not be filled so the height of the cable ladder side rail is exceeded.
The minimum permissible bending radius specified by Supplier shall be adhered to.
10.5.1 General
Ultra violet resistant plastic straps (Make Thomas & Betts) shall be used for horizontal runs when cables are
placed on the upper side of ladders and trays. Sufficiently sized straps shall be used for this purpose (min. type
27MX).
Stainless steel 316L coated straps shall be used for vertical runs and for horizontal runs in the vertical plane.
For strapping of fibre-optical and coaxial cables, Supplier guidelines shall be adhered to.
The distance between cable straps shall not exceed the distance between the horizontal and vertical runs on
the cable tray. Therefore each cable shall be strapped on each horizontal and vertical run on the cable tray.
Cable cleats for single core power cables shall be approved for the prospective short circuit stress.
The distance between cleats for single core cables shall be as specified by the cable manufacturer based on
the prospective short circuit level. The distance shall be selected such that cable will not be damaged by a
possible short circuit.
Temporary cables routed on permanent cable support systems shall be installed such that they will not obstruct
permanent installations and are easy to remove.
Temporary cables shall not be pulled through multi cable transits intended for permanent cables.
Dedicated MCT frames shall be installed for this purpose (e.g. rental generator, etc.).
Cables shall be terminated into enclosures using mechanical type compression glands or MCT's.
Cable glands shall be in accordance with the attached preferred Supplier list.
The selection and delivery of cable glands for all equipment to suit the appropriate dimensions of the selected
cable, shall be the responsibility of Contractor.
Glands shall be suitable for the reception of all strands of the wire armouring which shall be securely clamped
in a permanent manner. Glands shall be provided with clamping rings for cables with wire braids (see cable
description).
When glands are fitted via clearance holes in re-inforced polyester marshalling boxes, safety switches and
control switches a brass earth-continuation plate shall be installed internally, to maintain earth continuity.
All Multi Cable Transit frames and stay plates shall be 316 SST.
When cable transits are used on panels, cables have to be earthed with the braided earthwire to the earthing
bar.
Cable transits shall be installed such that the integrity of the bulkhead or wall is maintained. Contractor shall
locate and install cable transits. Cable transits shall be provided with 20% spare entries.
Cable transits complete with all inserts shall be provided by Contractor.
When preparing cables prior to fitting glands, the gland manufacturer's instructions shall be followed. In all
cases, care shall be taken to ensure that the lay of the armour is maintained after the gland is completely
fitted. Cables that have "bird caged" shall be replaced by Contractor at his expense.
All cable ends which are not terminated finally, immediately after cutting, shall be sealed effectively to prevent
ingress of moisture and shall be protected from damage until termination is complete.
For EMC requirements the modules (blocks) contain a conductive foil which establishes a full 360º low transfer
impedance contact with the cable screen.
The certification of the cable glands, blanking and drain plugs shall comply with the certification of the
equipment in which the glands/plugs are connected.
Ex d glands shall have clamping of braid armour and sealing of inner and outer sheath on Ex d direct entry
equipment installed in IIC classified area’s.
GDF SUEZ E&P Nederland B.V.
Specification 610 Rev. 13 Page 43 of 56
Dual certified glands, Ex d and Ex e (flameproof and increased safety) to be used and installed according to
Supplier specifications.
For EEXi circuits, EEXi certified glands shall be used.
Spare and unused glands shall be properly blinded (certified plug where applicable) or sealed.
Blind plugs shall be provided by Contractor.
When junction boxes are installed in exposed areas, drain plugs shall be installed. Anti condensation heating
shall be provided in boxes containing active components.
Junction boxes shall be designed with sufficient space for the expected number of cables and cable make-
off's.
Cables with braid armour shall have outer heat shrink sleeve which is fitted over the complete cable make-off.
Instrument and telecommunication cables with both braid armour and screen shall have inner and outer heat
shrink sleeves:
The inner sleeve shall be drawn over the inner bedding, i.e. passed under the braiding providing insulation
between braiding and screen.
The outer sleeve shall be fitted over the complete cable make-off.
The inner sleeve may be excluded at terminations providing a minimum of 50 mm inner bedding.
To minimise the extent of hot work, sleeves of type self vulcanising-tape may be used on units in operation.
10.11.2 Termination
All HV cables shall be connected with voltage stress cone termination kits.
All HV voltages stress cone termination kits shall be in compliance with preferred Supplier list.
All cable conductors shall be terminated by use of compression lugs or ferrules dependent upon the type of
termination. The compression ferrule shall be the type where the conductor strands are inserted through the
whole ferrule and reach the bottom of the terminal.
In switchboards and distribution boards adequate space shall be provided for the use of a clip-on ampere
meter without causing undue stress on the cable conductors or connections.
The braid armour and the screen shall be separated from each other as well as from the conductors, twisted
and fitted as required. This shall be done without any reduction of the cross sectional area.
Where the screens shall be left disconnected (applicable for field instruments), it shall be sealed and isolated
with an isolating cap which allows for insulation testing without any disconnecting.
Only one conductor is allowed in each terminal of a terminal block/row for external connections. This is not
related to terminals as an integrated part of internal components (e.g. relays, contactors) of the equipment.
Cable termination for instrumentation (junction boxes, panels etc.) shall be connected to terminals of
Phoenix-Contact of the Clip line series. (max up to 2,5 mm2)
Moulded cables as a part of electric devices such as solenoid valves or pressure switches shall be connected
to an EEXe moulded plastic junction box (Contractor’s scope) in the direct vicinity of the device (often several
devices are connected to one central EEXe junction box). From this junction box a cable in compliance with
Company’s specification shall be used for connection to the control system.
The unarmoured or unshielded cable(s) shall be protected against mechanical damage as much as possible.
Identical solution as described above for devices with very small termination housings (to small to adapt
armoured cabling).
If the device is in the vicinity of the system, the unarmoured or unshielded cable shall be sufficiently protected
against mechanical damage. Special attention shall be paid to the type of glands if these cables will be
connected to EEXd enclosures.
In cabinets all spare conductors shall be marked with terminal number and connected to terminals.
If there are no spare terminals left in the cabinet, all spare conductors shall be covered with yellow/green
sleeves, marked with relevant cable number and connected directly to the relevant earth bar.
11.1 General
The installation shall be installed according to the general earthing layout drawings and shall be in accordance
with the applicable codes and standards. For general earthing philosophy refer to Specification 613.
Earth bars shall be located to allow easy access for inspection and maintenance.
Earth wires shall be as short as possible, series looping of earth wiring is not allowed.
The Main earth reference for al earthing systems shall be the main structure.
If aluminium is used for any part of the main structure, attention shall be given to ensure that continuity in the
structural earth is maintained at aluminium/steel interface points.
The Main earth reference points shall be earth bosses welded to the structure as close as possible to the
cabinet/equipment. Alternatively, earth bars mounted on earth bosses welded to structure may be used.
Main electrical equipment (skids, MCC panels, containers, etc.) shall be earthed at least at two separate
points.
There shall be a separate Main earth reference point for PE and IE.
The distance between the PE and IE reference points shall be minimum 1000 mm.
Field equipment shall be connected to the PE system through a separate conductor in the cable. The braid
armour shall be earthed and shall be electrically continuous from the field to the central equipment PE bar.
Equipment supplied by single core cables shall be connected to PE by a separate earth cable. The separate
earth cable shall run alongside the power cables to form a "cable system" and be terminated to the field
equipment earth terminal as well as feeding and earth bar/terminal.
Before installation of the bolted earth connections, ensure that all surfaces are free of paint, corrosion and
grease to provide minimum resistance.
Earth cables shall be installed in one length. Joints are not allowed.
The copper braid of single core cables shall be earthed at both ends.
The IE shall be the earth reference for non intrinsically safe, intrinsically safe instrumentation and
telecommunication 0 volt references, etc.
The IE screen shall be left floating in the field end. It shall be electrically continuous from the field equipment
and be connected to IE bar in the central cabinet.
Exposed conductive parts located in hazardous and mechanical ventilated areas shall be equipotential bonded
to the main structure.
Equipotential bonding shall be provided between the platform structure and all pre assemblies, modules and
decks which are not welded.
Equipotential bonding shall be applied for equipment which is isolated from main structure.
Earth bars shall be fabricated from copper and provided to suit number and size of connections.
Main earth bars shall be fabricated from tinned copper.
PE bars shall be connected to the nearest convenient main structure point through an insulated earth
conductor or through the supply/feeder cable.
IE bars shall be isolated from the enclosure and connected to the nearest convenient main structure point
through an insulated earth conductor.
Where earth bosses are used, each earth boss shall only have one connection. Surface of earth bosses shall
be free of paint.
After connection the whole assembly shall be sealed against corrosion.
Mounting bosses shall be used for mounting of equipment on the outside of buildings, such as cable trays
lighting fixtures junction boxes etc.
Construction.
Cable ladder shall be type welded construction. Profiled side beams with draining holes on bottom for drainage
of water. Slotted C-type rungs for possibility of mounting of clamps and ancillary items.
The side beams shall be of continuous side beam perforation in order to prevent drilling in case of connecting
shortened straight elements
All main cable trays shall be type heavy duty with a minimum height of 125mm, side runs shall have a minimum
height of 50mm.
Fittings
Only fittings should be used that belong to manufacturer’s standard range. At a minimum this range should
consist of: 45° flat bends, 90° flat bends, T-pieces, inside and outside risers, adjustable articulated riser sets
and branch pieces.
Fittings should have similar sidewall profile as straight lengths to have a smooth joint and to avoid sharp edges.
Fittings should have integrated couplers to allow easy fixing to the straight lengths.
Material/finishing
All items shall be Stainless Steel Type 316L, and pickled and passivated after fabrication by manufacturer
Contractor shall verify the deliveries of the supplier are accordingly
.
Ventillated cover
For cable ventilation purposes manufacturer’s standard range should offer a standard solution for cable
ladder cover mounting of 25mm above side beam level.
Installation instructions
Manufacturer’s installation instructions shall be followed.
Supporting
Main cable tray supporting system shall be fully welded and coated according to specification 525.
Side runs supporting systems can be mounted on stainless Steel 316L type “Unistrut” or welded and coated
supports as per specification 525.
Cable ladders installed horizontally shall have sufficient space to facilitate cable pulling and fixing.
Cable support systems shall be located to leave sufficient space for surface protection of adjacent structure.
Main cable ladders inside Living quarters and offices can be type “Scheepsladderbaan” also inside these
buildings cable ladders and supporting system can be Hot dip galvanised according to NEN EN ISO 1461 (BS
EN ISO 1461).
In offices and living quarters where multidiscipline socket outlets are grouped together, multipurpose cable
channels designed for recessed installed outlets shall be used.
Protection shield shall be installed where cables can be exposed to physical damages.
Equipment brackets and supports shall not be installed on removable deck, hatches, grating, panels, handrails,
pipes or other removable equipment unless specified otherwise.
13.1 General
All marking shall be in accordance with the cable schedule, instrument list and equipment list.
13.3 Equipment
All labels shall be fabricated and installed in accordance with the following requirements:
Labels shall be located close to the equipment and be easily visible.
Labels shall not be mounted on removable parts.
Labels shall be fixed by SST 316L screws, rivets or suitable glue (only in dry areas).
Labels shall be of engraved traffolyte, marked as follows:
- Black letters on yellow background, letter size 10-2- mm.
Electrical, instrumentation and telecommunication systems (service description in English language).
- White letters on red background, letter size 10-20 mm.
Instrument ESD systems, Fire & Gas systems and warning labels (service description in English
language).
Supply tubing shall be marked with consumer tag number at the distribution manifold or at hook-up to main
line.
When tubing enters through bulkheads/penetrations, tubing shall be marked with tag number on both sides.
13.5 Cabling
13.5.1 Cables
Each cable shall be marked with indelible and non-corrosive cable markers indicating the cable number. The
cable markers shall be clearly visible after cleating and strapping.
Individual conductors and wires shall be identified with a closed, slip-on type plastic cable identification ferrule,
carrying a number identical to the terminal. This is also applicable to the single conductors for cross wiring
between the terminal blocks in panels.
AC systems:
Phase 1 L1
Phase 2 L2
Phase 3 L3
Neutral N
Protective Earth PE
Protective Earth/Neutral PEN
Instrument Earth IE
DC systems:
Positive pole (+)
Negative pole (-)
13.5.3 Colour coding of earth conductors, earth bars and cables screen
Bonding
Static earth conductors shall be coloured yellow/green.
All equipment and materials shall minimum be flame retardant with low halogen content.
Equipment enclosures located outdoors, in natural ventilated areas and wash down areas, shall be made of
proven sea water resistant material or protected by a coating system.
Junction boxes shall be made of glassfibre reinforced plastic with polyester resin. In outdoor areas exposed to
changing environmental conditions stainless steel 316L may be used.
Cable support systems located outdoors and indoors in natural ventilated areas and wash down areas shall be
made of stainless steel 316 L.
Cable protection shields shall be made in the same material as the cable support system in the area.
Equipment brackets, supports and junction box stands shall be fabricated from 316L SS.
Screws, bolts, nuts and spring washers shall be made of stainless steel 316L. Star washers shall not be used.
Long term precautions against galvanic corrosion shall be taken whenever contact between dissimilar metals is
present, by the use of PTFE (Teflon) strip.
All instrumentation and consumable materials shall be supplied in accordance with the preferred supplier list.
Contractor shall specify the type/model, material and other technical data of the applicable instrumentation.
Other type/manufacturer shall not be used without written approval from Company.
Material Manufacturer
Floodlights IMT
Orga
Chalmit
Terminals Phoenix-Contact