Project Schedule and Planning

Building-up Solar PV System requires several steps and preliminary surveys in order to confirm
the reliability of the project. Each phase is essential and the project will be completed as per
specified in the bidding documents. The project cycle after signing of contract will be as
per the following activities flow diagram.

Phase Step Duration

Phase 1 Detail Feasibility of the Project One Day

Phase 2 System Design One Day

Phase 3 Procurement and Transport of


system component to site Thirty days

Phase 4 System Installation


Thirty Days

Commissioning, training and


Phase 5 handover of the system Five day

Operation and maintenance of the


Phase 6 system As per Bid document