Construcción de una casa prefabricada estilo

Americana
Exhibit I Sequence and Time Requirements of Jobs

In that exhibit, the column “immediate predecessors” determines the sequence


relationships of the jobs and enables us to draw the project graph, Exhibit II. Here, in
each circle the letter before the comma identifies the job and the number after the
comma indicates the job time.