You are on page 1of 2

TUAS WATER RECLAMATION PLANT

CONTRACT 2A - INFLUENT PUMPING STATIONS VOLUME 4

BILL NO. 3.3


STRUCTURAL AND ARCHITECTURAL WORKS
- ARCHITECTURAL WORKS

Item Description Code Unit Quantity Rate Amount ($)

BUILDING ABOVE COARSE SCREEN


SHAFT ) (CONT'D)

Floor finishes

B Power float concrete floor with approved hardener m2 760 1.00 760.00
non-metallic floor hardener as specified

Page BQ3.3-10 Total to Collection 760.00

Page 1 of 2
TUAS WATER RECLAMATION PLANT
CONTRACT 2A - INFLUENT PUMPING STATIONS VOLUME 4

BILL NO. 3.3


STRUCTURAL AND ARCHITECTURAL WORKS (INDUSTRIAL PUMPING STATION)
- ARCHITECTURAL WORKS

Item Description Code Unit Quantity Rate Amount ($)

INDUSTRIAL INFLUENT PUMPING


STATION (CONT'D)

Floor finishes

B Power float concrete floor with approved hardener m2 11,780 1.00 11,780.00
non-metallic floor hardener as specified

F Power float finish to concrete slab as hardener m2 500 1.00 500.00


specified

Page BQ3.3-34 Total to Collection 12,280.00

Page 2 of 2