You are on page 1of 2

A.

SuperStructure
1. Concrete
a. Ground Floor
i. Slab on Grade
1. GF: FRC Slab on Grade
2. GF: Cure Slab on Grade
3. GF: Strip Form for Slab on Grade
ii. Exterior Walls
1. GF: FRC Exterior Wall
2. GF: Cure Exterior Wall
3. GF: Strip Form for Exterior Wall
iii. Column
1. GF: FRC Columns
2. GF: Cure Columns
3. GF: Strip Form for Columns
iv. Elevator Walls and Shafts
1. GF: FRC Elevator Shaft
2. GF: Cure Elevator Shaft
3. GF: Strip Form for Elevator Shaft
b. Second Floor
i. Suspended Beams and Slab
1. SF: FRC Beams and Slab
2. SF: Cure Beams and Slab
3. SF: Strip Form for Beams and Slab
ii. Stair
1. SF: FRC Stair
2. SF: Cure Stair
3. SF: Strip Form for Stair
iii. Exterior Walls
1. SF: FRC Exterior Wall
2. SF: Cure Exterior Wall
3. SF: Strip Form for Exterior Wall
iv. Column
1. SF: FRC Columns
2. SF: Cure Columns
3. SF: Strip Form for Columns
v. Elevator Walls and Shafts
1. SF: FRC Elevator Shaft
2. SF: Cure Elevator Shaft
3. SF: Strip Form for Elevator Shaft