You are on page 1of 10

Energy Policy 70 (2014) 64–73

Contents lists available at ScienceDirect

Energy Policy
journal homepage: www.elsevier.com/locate/enpol

Levelized cost of electricity (LCOE) of renewable energies


and required subsidies in China
Xiaoling Ouyang c, Boqiang Lin a,b,n
a
Newhuadu Business School, Minjiang University, Fuzhou, Fujian 350108, China
b
Collaborative Innovation Center for Energy Economics and Energy Policy, Institute for Studies in Energy Policy, Xiamen University,
Xiamen, Fujian 361005, China
c
Energy Research School, College of Energy, Xiamen University, Xiamen, Fujian 361005, China

H I G H L I G H T S

 Levelized cost of electricity (LCOE) of renewable energies is systemically studied.


 Renewable power generation costs are estimated based on data of 17 power plants.
 Required subsidies for renewable power generation are calculated.
 Electricity price reform is the long-term strategy for solving problem of high cost.

art ic l e i nf o a b s t r a c t

Article history: The development and utilization of renewable energy (RE), a strategic choice for energy structural
Received 23 January 2014 adjustment, is an important measure of carbon emissions reduction in China. High cost is a main
Received in revised form restriction element for large-scale development of RE, and accurate cost estimation of renewable power
12 March 2014
generation is urgently necessary. This is the first systemic study on the levelized cost of electricity (LCOE)
Accepted 20 March 2014
Available online 13 April 2014
of RE in China. Results indicate that feed-in-tariff (FIT) of RE should be improved and dynamically
adjusted based on the LCOE to provide a better support of the development of RE. The current FIT in
Keywords: China can only cover the LCOE of wind (onshore) and solar photovoltaic energy (PV) at a discount rate of
Levelized cost of electricity 5%. Subsidies to renewables-based electricity generation, except biomass energy, still need to be
Renewable energy
increased at higher discount rates. Main conclusions are drawn as follows: (1) Government policy
Feed-in tariffs
should focus on solving the financing problem of RE projects because fixed capital investment exerts
considerable influence over the LCOE; and (2) the problem of high cost could be solved by providing
subsidies in the short term and more importantly, by reforming electricity price in the mid-and long-
term to make the RE competitive.
& 2014 Elsevier Ltd. All rights reserved.

1. Introduction economic growth is constrained by carbon emissions reduction.


Therefore, it is necessary for China to develop new technologies and
1.1. Research background new energies to meet the growing energy demand, and simulta-
neously, to optimize energy consumption structure. Renewable
China is currently experiencing rapid development of urbani- energy (RE) will play an increasingly important role in energy
zation, along with the requirement for adequate energy supply diversification and the development of low-carbon economy (IEA,
(Jiang and Lin, 2012). The Chinese government proposed that both 2011; Li and Lin, 2013).
energy intensity and carbon intensity would be reduced by 40–45% Supportive government policies have underpinned the rapid
in 2020 compared to the level in 2005, implying that China's development of RE industry in China (Qi et al., 2014). However, the
problem of high-cost is a main restriction for the large-scale
n
development of RE (Lin, 2012). On one hand, power generation
Corresponding author at: Newhuadu Business School, Minjiang University,
Fuzhou, Fujian 350108, China. Tel.: þ86 5922186076; fax: þ 86 5922186075.
costs of RE are higher than that of traditional energy resources; on
E-mail addresses: ouyangxiaoling@gmail.com (X. Ouyang), bqlin@xmu.edu.cn, the other, significant cost reductions cannot be achieved in the
bqlin2004@vip.sina.com (B. Lin). short term. Environmental value is highly related to per capita

http://dx.doi.org/10.1016/j.enpol.2014.03.030
0301-4215/& 2014 Elsevier Ltd. All rights reserved.
X. Ouyang, B. Lin / Energy Policy 70 (2014) 64–73 65

income (Flores and Carson, 1997). At present, the relatively low of renewable FIT in Europe, and showed that the interaction of
level of per capita income in China results in the relatively low policy design, electricity price and electricity production cost was a
evaluation and assessment of environmental quality by the gen- more important determinant of renewable electricity development
eral public, and the low willingness as well as low ability to pay for than policy enactment alone.
environment. Apparently, it is difficult for the Chinese government Studies showed that the RE policy in China still needed to be
to encourage the public to support clean energy development and improved. Wu and Xu (2013) reviewed the FIT policy as well as
pay for the renewable energy cost. Therefore, support policies are subsidy policy of RE in China, and showed that the effects of policy
essential for the deployment of RE in China. implementation were unsatisfactory. Zhang et al. (2009) analyzed
Financial subsidy is an important method in dealing with the opportunities and challenges for RE policy in China, and pointed
problem of high-cost of RE. The development of RE requires out that government support was the key power for RE develop-
large-scale investment in research and development (R&D), ment. Schuman and Lin (2012) indicated that China's Renewable
which is characterized by high-risk, high-investment and Energy Law, which regulated the FIT system and funding mechan-
uncertain-return, thus market competition alone cannot meet isms, had led to rapid growth of RE in China. However, there are
the substantial investment demand. The United States govern- still numerous problems for China's supportive policies for RE
ment provides continued financial support for R&D of RE development. Huo and Zhang (2012) pointed out that there was no
(Congressional Budget Office, 2012). Presently, financial funds predetermined degression of the capital subsidy to push cost
are sufficient for the Chinese government to support the devel- reduction; moreover, insufficient R&D in China had impeded the
opment and utilization of RE, thereby to promote the develop- future development of RE.
ment of RE industry (Lin, 2012). The direct financial transfer, To the best of our knowledge, there has been no study that
including the feed-in-tariff (FIT) system, has been commonly systematically estimates the LCOE of RE as well as the required
used by governments in subsidizing RE (IEA, 2011). Subsidies to subsidies under the current FIT system in China. This paper fills a
RE in China are mainly for power generation projects. An much needed research gap. Undoubtedly, the problem of high-cost
accurate estimation of renewable power generation cost is the is imperative for the development of RE. In this study, we
basis of effective government subsidies, which determines the concentrate on evaluating the LCOE of renewables and required
future development of RE in China. subsidies under the existing FIT mechanism in China. Based on our
findings, we propose policy recommendations for decision makers
1.2. The LCOE of renewables and the FIT system on shaping the short-term tactics and the long-term strategy for
RE development.
The LCOE method, which estimates the cost of lifetime- The remainder of this paper is organized as follows. Section 2
generated energy, is used as a benchmarking tool to assess the describes methodology. Section 3 presents results. Section 4
cost-effectiveness of different energy generation technologies discusses required subsidies for renewable power generation.
(OECD, NEA/IEA, 2010). The method of LCOE has been widely used Section 5 summarizes our findings and draws policy implications.
for the estimation of power generation cost (Wiser et al., 2009;
Singh and Singh, 2010; NREL, 2013). For example, IRENA (2012a,
2012b) estimated power generation costs of different technologies
around the world in 2010. OECD, NEA/IEA (2010) did a compre- 2. Methodology
hensive research based on data of 190 power plants located in 21
countries. Roth and Ambs (2004) accessed the LCOE of 14 Levelized cost of electricity (LCOE) is a convenient tool for
electricity generation technologies. Results indicated that incor- comparing the unit costs of different technologies over their
porating externalities into the full cost approach has an enormous economic life (OECD, NEA/IEA, 2010). The LCOE methodology is
impact on the LCOE and the relative attractiveness of electricity an abstraction from reality and is used as a benchmarking or
generation options. Darling et al. (2011) calculated the LCOE for ranking tool to assess the cost-effectiveness of different energy
photovoltaics based on input parameter distributions feeding a generation technologies (Branker et al., 2011). Estimation of the
Monte Carlo simulation. LCOE of renewables is the basis of the appropriate FIT.
Feed-in-tariff (FIT), a policy mechanism for subsidizing RE, is There are two models for calculating the LCOE: (1) the EGC
more effective than alternative supportive schemes in promoting Spreadsheet model and (2) the System Advisor Model (SAM). The
renewable energy technologies, as it provides long-term financial former has been widely used in research reports by the OECD and
stability for investors (Lesser and Su, 2008). Recent experience IEA/NEA in the cost estimation of power generation, while the
from countries around the world suggested that FIT was the most later is developed by National Renewable Energy Laboratory
effective policy that promoted the rapid and sustained deploy- (NREL). The advantage of the EGC Spreadsheet model is that it
ment of RE (European Commission, 2008; Couture and Gagnon, can estimate the LCOE of different generation technologies under
2010; Thiam, 2011). Degression of tariff rates could deliver renew- the constraint of limited data. Therefore, we use this method to
able generation capacity at lower cost (Mabee et al., 2012). Unit predict the LCOE of renewables in China.
subsidy cost of renewables is expected to fall gradually over time As shown in Fig. 1, there are four major components determin-
thanks to ongoing R&D and learning-by-doing, coupled with rising ing the LCOE of renewable power generation technologies –
fuel and wholesale electricity prices and higher CO2 prices (IEA, resource quality, equipment cost and performance, the balance
2011). Klein et al. (2008) analyzed different FIT designs that were of project cost and the capital cost. All of them can vary
applied in the Member States of the European Union, and significantly between individual projects and countries (IRENA,
proposed that national FIT design should take local conditions 2012a, 2012b). Khatib (2010) reviewed “Projected costs of gener-
such as renewable electricity potentials, the cost of electricity grid ating electricity—2010 Edition” by OECD, NEA/IEA (2010), and
as well as social aspects into account. If not properly designed, FIT emphasized the key conclusion of the study “the LCOE is deter-
could be economically inefficient. Lesser and Su (2008) put mined by country-specific circumstances”. Therefore, in order to
forward an innovative two-part FIT, consisting of both a capacity obtain more accurate results, the LCOE of RE should be studied
payment and a market-based energy payment. Moore et al. (2013) based on specific countries. Following the above principle, this
indicated that FIT needed to meet industrial payback and industrial paper attempts to estimate the LCOE of renewable energies based
targets. Jenner et al. (2013) assessed the strength and effectiveness on the data of 17 power plants in China.
66 X. Ouyang, B. Lin / Energy Policy 70 (2014) 64–73

On site • Financing Levelized costs


Equipment • Operation & Maintanance of electricity
• Taxes
• Transport cost • Project development • at 5% discount rate
• Site preparation • Capacity factor
• Import levies • at 8% discount rate
• Working capital • Lifetimes
• Value-added taxes • at 10% discount
• Auxiliary equipment • Costs of decommissioning rate
Factory gate • Contingency payments
Equipment Project cost

Fig. 1. Cost indicators of renewable power generation.

The LCOE is equal to the lifecycle cost divided by lifetime the additional required subsidies for renewable power generation,
energy production (Fig. 1). If the electricity prices were equal to our estimation takes government interventions such as value-added
the levelized average lifetime costs of electricity generation by tax and favorable income tax into account. Furthermore, we do
different technologies, an investor would precisely break even on not consider the price of CO2 (Lin and Li, 2011; Li and Zhang, 2012;
an investment project. The above statement is based on two Li et al., 2013), the income from Clean Development Mechanism
important assumptions: (CDM) as well as the external benefits from reductions of environ-
mental pollution and carbon emissions. All data provided are
1) Interest rate: the interest rate “r” used for discounting costs and nominal which do not exclude the factor of inflation.
benefits is stable and does not vary during the lifetime of the Data of wind (onshore) power plants in this paper are taken
project under consideration. from the Feasibility Study Reports of Halahaixiang wind power
2) The electricity price: the electricity price is stable and does not project in Heilongjiang province, Ningdong wind power project in
change during the lifetime of the electricity generation project. Ningxia province, Qiaowan wind power project in Gansu province,
Azuoqi wind power project in Inner Mongolia, Laizhou wind power
The calculation of the LCOE starts from Eq. (1), which states project in Shandong province, and Turpan wind power project in
that income of power generation equals to the cost of power Xinjiang province. Data of solar power plants are taken from
generation (both of them are in present value terms). Feasibility Study Reports of Maigaiti solar power project in Xinjiang
province, Gonghe solar power project in Qinghai province, Weiwu
T  T  solar power project in Gansu province, Jialonggou solar power
∑ Et P E ð1 þ rÞ  t ¼ ∑ ðI t þ Ot þ M t þ Dt Þð1 þ rÞ  t ð1Þ
t¼0 t¼0 project in Tibet, Wuqia solar power project in Xinjiang province,
TianheYangguang solar power project in Qinghai province. Data of
where Et is the amount of electricity production in year t; Pe
biomass power plants are taken from the Feasibility Study Reports
denotes the constant price of electricity; (1 þr)  t indicates the
of Houde biomass project in Hubei province, Dangyang biomass
discount factor for year t; It is the investment cost in year t (e.g.,
project in Hubei province, Hailun biomass project in Heilongjiang
the initial construction investment, interest payment, administra-
province, Baoquanling biomass project in Heilongjiang province,
tion cost, taxes, etc.); Ot & Mt signifies the operations and
and Huoqiu biomass project in Anhui province.
maintenance costs in year t; Dt stands for decommissioning cost
in year t; T represents the lifespan of a power plant; t represents
the t year life-cycle for a power plant. All variables are calculated
in nominal terms for the convenience of evaluating required 3. Results
subsidies under the current FIT system in China in Section 5.
Eq. (1) is followed by 3.1. Wind (onshore)1
 T 
T  
P e ¼ ∑ ðI t þ Ot þ M t þ Dt Þð1 þ rÞ  t = ∑ Et ð1 þrÞ  t ð2Þ Major influencing factors of the LCOE of wind (onshore) include
t¼0 t¼0
the construction costs, operations and maintenance (O&M) costs,
The Eq. (2) is equivalent to Eq. (3) electricity generation amount and lifespan of a power plant.
 T  Among these factors, the construction cost is composed of equip-
T  
LCOE ¼ P e ¼ ∑ ðI t þ Ot þM t þDt Þð1 þ rÞ  t = ∑ Et ð1 þrÞ  t ment cost, infrastructure and construction cost, and interest
t¼0 t¼0 payment during the construction period. According to Tegen
ð3Þ et al. (2012), O&M costs make up 10–15% of the LCOE in the first
several years of a turbine's lifecycle, and then increase to 20–35%
Using the discounted cashing flow (DCF) method, the calcula-
by the end of its lifetime. O&M costs consist of material costs,
tions of LCOE of renewable energies in this paper are based on the
repair costs, line maintenance costs, etc. Material costs may vary
levelized average lifetime cost approach. In this paper, we use Eq.
from CNY 0.8 to 2 million per year according to the capacity of a
(3) to estimate the LCOE of different renewables in China. The
wind farm (Zhang, 2011). Repair costs will rise with the increase in
most important assumptions are the utilization of fixed discount
service life of a wind turbine. In this paper, we assume that the
rates, which are 5%, 8% and 10%. Due to limited data, the discount
rate could not be differentiated by renewable energy market and
the risk of different technologies (Khatib, 2010). 1
Based on estimates from China Meteorological Administration (2009), China's
It should be noted that the estimation is based on data of potential capacity of onshore wind is about 2380 GW at 50-meter hub height; and
different power plants located in different regions of China, while China's potential capacity of offshore wind is about 200 GW, taking account of hub
heights of 50 m and water depth of 5–25 m in the offshore area. In late 2010, China
the impact of power plants on the entire power system is not surpassed the U.S. as the country with the largest installed capacity of wind power.
included (e.g., the cost of grid connection, dispatching costs due to The total installed capacity of wind power grew at the rate of 20.8% annually, and
intermittence of wind and solar energy, etc.). In order to evaluate reached 75324.2 MW in 2012 (CWEA, 2012).
X. Ouyang, B. Lin / Energy Policy 70 (2014) 64–73 67

Table 1
Investment costs of wind (onshore) power plants in China.

Plant name Capacity Estimated Overnight Construction Equivalent Interest payment Decommissioning Average O&M
(MW) electricity construction costs duration (year) hours (million CNY/year) costs (CNY/kW) costs (CNY/kWh)b
generation (million CNY)a
(GWh/year)

Laizhou 32  1.5 95.22 450.14 1 1984 22.11 444.29 0.090


Halahaixiang 33  1.5 106.70 444.21 1 2155 21.82 424.86 0.080
Ningdong 33  1.5 103.50 434.03 1 2091 21.32 415.12 0.080
Turpan 33  1.5 102.45 424.81 1 2049 20.87 406.31 0.079
Azuoqi 80  2.5 376.22 1598.05 2 1811 65.20 365.41 0.060
GuazhouQiaowan 134  1.5 422.58 1894.28 2 2102 77.29 431.26 0.063

a
Overnight construction costs include owner's construction costs, contingency costs and interest payment.
b
Average O&M costs are the discounted values.

Table 2
The LCOE of wind (onshore) power in China.

Plant name Location Category of wind Tax-exclusive FIT The LCOE (CNY/kWh)
resource area (CNY/kWh)a
At 5% discount rate At 8% discount rate At 10% discount rate

Laizhou Shandong Class IV 0.562 0.624 0.745 0.827


HalaHaixiang Heilongjiang Class IV 0.562 0.552 0.656 0.729
Ningdong Ningxia Class III 0.535 0.560 0.665 0.738
Turpan Xinjiang Class III 0.535 0.540 0.640 0.709
Azuoqi Inner Mongolia Class I 0.470 0.473 0.572 0.640
Qiaowan Gansu Class II 0.498 0.497 0.609 0.680

a
Rate of value-added tax for wind power projects in China is 8.5%. The initial value of FIT multiplied by 1.085 is tax-exclusive FIT.

material cost is CNY 6.0 per MWh based on the feasibility study Based on Table 1 and Eq. (3), the estimated LCOE of wind
report (FSR). There is no repair cost in the first two years of a wind (onshore) in China is reported in Table 2.
turbine's lifetime under warranty. According to FSR, the rate of From Table 2, the levelized cost of wind (onshore) power
repair cost is assumed to be 1% of the total fixed capital cost in the ranges from 0.473 to 0.624 CNY/kWh at 5% discount rate, and
third operating year of a wind turbine's lifetime, which rises to 4% ranges from 0.640 to 0.827 CNY/kWh at 10% discount rate. The
after the fourth year. The discount rates in this paper are set as 5%, LCOE of wind power exhibits an increasing trend with the decline
8% and 10% under three scenarios. According to OECD, NEA/IEA in the quality of wind resources. The levelized cost of wind
(2010), expected lifespan of a wind plant is 20 years. (onshore) electricity of Azuoqi in Inner Mongolia is 0.473 CNY/
Other influencing factors of the LCOE of wind (onshore) are as kWh at 5% discount rate, which is the lowest among the above
follows: financial expenses, administrative expenses, taxes and wind (onshore) power plants. Moreover, it is close to the current
decommissioning costs. Financing costs are mainly interest pay- value of tax-exclusive FIT (0.470 CNY/kWh), implying that the
ments involved with borrowing money for the construction of feed-in tariffs (excluding tax) in China could only cover the LCOE
wind farms. For most of the wind power projects in China, about of wind (onshore) at the lowest discount rate. Averagely, the LCOE
70–80% of the investments are supported by bank loans. Basically, of wind (onshore) at 8% discount rate is about 0.1 CNY/kWh,
the loan terms are about 10–16 years and the interest rates range higher than that at 5% discount rate, and the LCOE of wind
from 6% to 8% accordingly. Labor cost takes the largest proportion (onshore) at 10% discount rate is about 0.07 CNY/kWh, higher
in the administrative expenses. In order to simplify calculation, we than that at 8% discount rate.
assume that there is no difference in the unit labor costs among
different wind farms. The average annual salary per worker is set 3.2. Solar photovoltaics2
as CNY 60,000. In addition, employees' benefits, compensation
insurance and housing funds are assumed to account for 14% and The cost of electricity generated by a photovoltaic (PV) system
43% of total administrative expenses, respectively. Taxes consist of is determined by the capital cost, the discount rate, the variable
value-added tax (VAT), additional tax and income tax. The pre- costs, the level of solar irradiation and the efficiency of solar cells
ferential VAT rate for wind power projects in China is 8.5%. The (IRENA, 2012a, 2012b). Cost of financing and efficiency is sub-
rate of city maintenance and construction tax is 5%, the rate of stantial, implying the huge potential of cost reduction. Specifically,
education surtax is 3%, and the income tax rate is 25%. For wind construction cost is composed of the PV system (photovoltaic
power projects in China, enterprises could enjoy income tax arrays, solar inverters, electrical substations) cost, infrastructure
exemption in the first three years and half reduction of income construction cost, installation cost, interest payment and contin-
tax in the subsequent three years. Moreover, we assume that fixed gency cost. Cost of PV modules makes up over half of the total
assets depreciate at a rate of 5% during twenty-year depreciation equipment cost in the PV system, which fluctuates with market
period. The residual value of fixed assets accounts for 30% of the prices. The discount rates in this paper are set as 5%, 8% and 10%.
initial investment value, which is consistent with the data from
OECD, NEA/IEA (2010). Lastly, decommissioning cost is assumed to 2
According to Wang and Zheng (2012), the average solar radiation in China is
account for about 5% of the construction cost. about 1500 kWh/m2 annually, and the annual solar radiation is above 1000 kWh/
Table 1 presents the costs of wind power plants located in m2 for 98% of China's total land area, and 2000 kWh/m2 for 3% of China's total land
different regions of China. area. In 2007, China became the world's major producer of solar photovoltaic cells.
68 X. Ouyang, B. Lin / Energy Policy 70 (2014) 64–73

Table 3
Investment costs of solar PV power plants in China.

Plant name Capacity Estimated electricity Overnight Construction Equivalent Interest payment Decommissioning Average O&M
(MW) generation construction duration (year) hours (h) (million CNY/year) costs (CNY/kW) costs (CNY/kWh)b
(GWh/year) cost (million CNY)a

Jialonggou 10 17.2 224.79 1 1720 10.25 1085.11 0.073


Wuqia 20 36.79 238.24 1 1839 22.64 595.6 0.044
Gonghe 25 43.81 465 1 1752 15.28 898.83 0.098
Weiwu 30 49.99 405.95 1 1667 19.94 642.55 0.066
TianhuaYangguang 50 79.5 591 0.25 1590 28.08 562.62 0.060
Maigaiti 100 179.38 1281.01 1 1794 55.06 636.64 0.061

a
Overnight construction costs include owner's construction costs, contingency costs and interest payment.
b
Average O&M costs are values after discounting.

Table 4 0.1 CNY/kWh lower than the exiting FIT (excluding tax). The
The LCOE of solar PV in China. current feed-in tariffs (excluding tax) in most regions are higher
than the LCOE of solar PV projects at 5% discount rate, except those
Plant name Tax-exclusive FIT The LCOE (CNY/kWh)
(CNY/kWh)a in Qinghai province (TianheYangguang project) and Tibet (Jialong-
At 5% At 8% At 10% gou project). The LCOE of solar PV at 8% discount rate is about
discount discount discount 0.2 CNY/kWh, higher than that at 5% discount rate; and the LCOE
rate rate rate at 10% discount rate is about 0.14 CNY/kWh, higher than that at 8%
Gonghe, Qinghai 0.922 0.818 0.978 1.085
discount rate.
Maigaiti, Xinjiang 0.922 0.839 1.012 1.133
Wuqia, Xinjiang 0.922 0.897 1.084 1.212 3.3. Biomass3
Weiwu, Gansu 0.922 0.965 1.147 1.270
TianheYangguang, 1.060 1.168 1.426 1.605
Qianghai Most of China's biomass power plants adopt direct combustion
Jialonggou, Tibet 1.060 1.337 1.616 1.800 technologies that use agro-forestry wastes as raw materials. There
are three determinant factors for the LCOE of biomass: construc-
a
The value-added tax rate for solar PV projects is 8.5%, and the initial value of
tion costs, fuel costs and discount rates. Construction costs are
FIT multiplied by 1.085 is tax-exclusive FIT.
composed of costs of generator sets and boilers, electric power
construction and installation and interest payment during the
construction period. Among all expenses, costs of generator sets
According to the feasibility study report (FSR) of photovoltaic and boilers make up about 60–80% of the total construction
power plants in China, we assume that the O&M cost of a solar investments. Fuel costs denote the charges of straw as well as
plant accounts for 0.2% of the total construction cost in the first other agricultural and forestry wastes, which make up about 60–
five years, and rises to 0.5% in the subsequent seven years and then 70% of the LCOE of biomass energy. In this article, we assume that
reaches 1% in the last thirteen years. Based on the above assump- the prices of straw and other agricultural and forestry wastes
tions, the O&M cost makes up 10–12% of the LCOE of solar PV, range from CNY 200 to 400 per ton. Discount rates are set in three
which is in line with the data of OECD, NEA/IEA (2010). Besides, scenarios: 5%, 8% and 10%. Moreover, we assume that the auxiliary
the attenuation of the PV system will lead to the decline in power rate is 12% based on the Feasibility Study Reports (FSR) of
electricity generation. Systematic efficiency of a solar PV is usually biomass power plants in China.
assumed to be about 80% of the initial value by the end of its Other factors influencing costs of biomass power generation
lifecycle. In this article, we assume that the electricity generation are O&M costs, financial expenses, administrative expenses and
amount decreases at the rate of 0.8%. taxes. In this article, we assume that the O&M costs are CNY
Other factors that influence the cost of solar PV power genera- 350 per kW. Financial costs mainly come from interest payments.
tion are as follows: financial costs, administrative expenses, taxes For most of biomass power plants in China, about 70–80% of the
and decommissioning costs. Specifically, assumptions in this part investments are supported by bank loans. The interest rates range
are almost the same as assumptions in the estimation of the LCOE from 6% to 7% and the loan terms are usually 10 years. Labor costs
of wind (onshore) power in China; the only difference is that make up the largest proportion in administrative expenses. Com-
required laborers for the solar PV system are much fewer. In pared with other RE technologies, biomass power projects are
general, only 3–4 workers are needed for a solar PV plant with the labor-intensive. Generally, a biomass power plant with the capa-
capacity of 10 MW. Expected lifespan of a solar PV power plant is city of 30 MW needs about 150 workers in China. Based on the FSR
25 years in this article. of biomass power plants in China, we assume that annual income
Table 3 presents the cost of solar PV power plants located in per labor is CNY 40,000; the employees' welfare and insurances
different regions of China. are assumed to account for 14% and 43% of their total salaries,
Based on Table 3 and Eq. (3), we estimate the LCOE of solar PV respectively. Taxes of solar PV power plants consist of value-added
in China. tax (VAT), additional tax and income tax. The preferential VAT rate
From Table 4, the levelized cost of solar PV power generation for biomass power projects is 8.5%; the rate of city maintenance
ranges from 0.818 to 1.337 CNY/kWh at 5% discount rate, and from and construction tax is 5%, and the rate of education surtax is 3%.
1.085 to 1.800 CNY/kWh at 10% discount rate. Most of China's solar
PV power plants are located in the resource-rich regions such as
3
Qinghai, Xinjiang and Gansu provinces in Northwest China. The National Energy Administration (2012) estimated that China's available
biomass resource is about 0.46 billion tons of coal equivalent (TCE) per year, of
levelized cost of solar PV power generation of Gonghe project in which the utilization rate is less than 5%. According to China's 12th Five-Year Plan
Qinghai province is 0.818 CNY/kWh at 5% discount rate, which is (FYP) for biomass energy, utilization of biomass will exceed 50 Mtce per year, and
the lowest among the above solar PV power plants. It is about the installed capacity of biomass will reach 13 GW in 2015.
X. Ouyang, B. Lin / Energy Policy 70 (2014) 64–73 69

Table 5
Investment costs of biomass power plants in China.

Plant name Capacity (MW) Estimated electricity Overnight construction Equivalent Interest payment Fuel costs Average O&M costs
generation (GWh/year) costs (million CNY) hours (h) (million CNY/year) (Million CNY/year) (CNY/kWh)

Houde 30 195 297.41 1950 9.83 60 0.061


Dangyang 25 160 204.94 1600 8.52 55 0.062
Hailun 24 164 260.89 1640 9.82 52.8 0.058
Baoquanling 30 195 287.68 1950 11.52 55 0.061
Huoqiu 30 225 310 2250 16.24 66 0.053

Table 6 renewable power generation projects is highly urgent and


The LCOE of biomass in China. necessary.
Plant name Tax-exclusive FIT The LCOE (CNY/kWh)
(CNY/kWh)
At 5% At 8% At 10% 4. Discussion
discount rate discount rate discount rate

Houde 0.691 0.627 0.672 0.703 4.1. Mechanisms of electricity pricing and subsidies to RE in China
Dangyang 0.691 0.648 0.686 0.713
Hailun 0.691 0.651 0.698 0.731 4.1.1. Renewable electricity pricing
Baoquanling 0.691 0.585 0.628 0.658 4.1.1.1. Wind (onshore). In 1994, the former Ministry of Electric
Huoqiu 0.691 0.611 0.683 0.712
Power issued a regulation on grid-connected wind farms named
“Regulations on Management of the Integration of Wind Power Into
Power Systems”. This regulation required provincial electric power
The income tax rate is 25%. For biomass power projects in China, authorities to give priority to wind-generated electricity in the
power generation companies could enjoy income tax exemptions purchase of electricity. In 1999, the National Development and
in the first three years and the reduction of income tax by half for Reform Commission (NDRC) and the Ministry of Science &
the subsequent three years. The electricity generation costs of Technology (MST) issued an official notification to further support
biomass power plants in China are presented in Table 5. the development of RE, including a rule to set wind power price at a
Based on Table 5 and Eq. (3), estimates of the LCOE of biomass level that could repay interest-included capital cost plus a reasonable
in China are presented in Table 6. profit margin (NREL, 2004). In 2009, the NDRC issued a notice named
From Table 6, the levelized cost of biomass electricity ranges “Notice on Perfection of Policy Regarding Feed-in Tariff of Power
from 0.585 to 0.651 CNY/kWh at 5% discount rate, and from 0.658 Generated by Wind”, which set four different FIT levels for wind
to 0.731 CNY/kWh at 10% discount rate. The levelized cost of power in China based on conditions of wind resources and
biomass electricity of Baoquanling project in Heilongjiang pro- construction (NDRC, 2009).
vince is the lowest among the above biomass power plants, which
is 0.585 CNY/kWh at 5% discount rate, about 0.1 CNY/kWh lower
than the FIT (excluding tax). More importantly, the existing feed-in 4.1.1.2. Solar PV. Before the first nationwide FIT for solar projects
tariffs (excluding tax) can cover the LCOE of biomass power plants was announced, the Chinese government had sponsored two
at 8% discount rate. The LCOE of biomass power plants at 8% rounds of public tender for solar power projects since 2009.
discount rate is about 0.05 CNY/kWh, higher than that at 5% Most energy power companies were discouraged from investing
discount rate; and the LCOE at 10% discount rate is about in China's solar PV market due to the low bid price in auctions
0.03 CNY/kWh, higher than that at 8% discount rate. (ACORE, 2011). In 2011, the NDRC issued “Notice on Perfection of
A clear understanding of the relative cost-effectiveness and Policy Regarding FIT of Power Generated by Solar PV” to provide
feasibility of different energy technologies is imperative in deter- greater incentives for investors (NDRC, 2011). FIT of solar PV has
mining energy management policies for any country (Branker et been divided into two categories: (1) For those projects that have
al., 2011). Results in this paper show that, the LCOE of wind obtained the official approval before July 1, 2011 or have
(onshore) and biomass are lower than that of solar PV. Results in completed and have been put into commercial operation before
this paper are consistent with the previous studies such as OECD, December 31, 2011, the FIT would be CNY 1.15 per kWh (including
NEA/IEA (2010) and Elliston et al. (2013). Hence, the development tax); (2) for those projects that were approved after July 1, 2011 (or
of wind (onshore) and biomass in China has a comparative cost were approved before July 1, 2011 but did not complete the
advantage over the solar PV. Under three scenarios of discount construction before the end of 2011), the FIT would be CNY 1 per
rates, the LCOE of solar PV ranges between 0.818 and 1.800 CNY/ kWh, expect that in Tibet (the FIT of solar PV projects located in
kWh, the LCOE of wind (onshore) ranges between 0.473 and Tibet is 1.15 per kWh). Afterwards, “Notice on Improving the
0.827 CNY/kWh, and the LCOE of biomass ranges between 0.585 Development of Solar PV Industry by Utilizing the Price Leverage
and 0.731 CNY/kWh. Even so, solar energy still plays an important Effect” was announced by the NDRC, and the new FITs were
role in China's green innovation adoption (Li et al. 2011; Chung- differentiated for solar PV projects in different regions of China.
Ling Chien and Lior, 2011), and China is under pressure to prosper The FIT of solar PV would be 0.90 CNY/kWh for Class-I areas,
the photovoltaic (PV) solar energy industry (Chen et al., 2014). It is 0.95 CNY/kWh for Class-II areas, and 1.00 CNY/kWh for Class-III
worth noting that renewable technologies have high learning rates areas. In terms of academic research concerning this subject,
that could yield significant cost declines. Rapid cost reductions in Zhang and He (2013) conducted an analysis on China's solar PV
some renewable power generation technologies require up-to- incentive policies, particularly on the national FIT scheme. Zhang
date data for the evaluation of supportive policies for RE and a et al. (2013) reviewed the setting of categorized on-grid price of
dynamic cost analysis for policy amendment (IRENA, 2012a, renewable power. Zhang et al. (2014) examined four stages of
2012b). Therefore, establishing a timely data collection system of China's solar PV policy.
70 X. Ouyang, B. Lin / Energy Policy 70 (2014) 64–73

The development of distributed solar PV power generation in China. In general, renewable electricity pricing mechanism in
system has also enjoyed strong support from the Chinese govern- China has been improved. However, the reform process is too slow,
ment. The State Council issued a regulation named “Opinion about and the existing mechanism still has problems such as slow
Improving the Healthy Development of Solar PV Industry” in July adjustment of price and the undifferentiated FIT for regions with
2013, and illustrated the general preferential policy for the different resource endowments (Table 7). For instance, the FIT
distributed solar PV power generation system. The detailed sup- mechanism of solar PV power generation has not been implemen-
port policies were then promulgated by relevant departments of ted until 2011. Under the price mechanism of franchise bidding,
the central government. Specifically, the Ministry of Finance issued bidding firms competed with each other for better solar energy
the “Notice Regarding Subsidies to the Distributed Solar PV Power resources instead of ensuring the profitability of investment in
Generation According to the Quantity of Power” in July 2013; in solar PV power projects (Lin, 2012). The vicious price competition
August 2013, the National Energy Administration (NEA) issued the in solar energy industry has resulted in the slow development of
“Notice on the Establishment of Demonstration Areas for Distributed solar PV in China. What's worse, the existing FITs for solar PV
Solar PV Power Generation”, and the NEA and China Development power generation in regions at different resource endowment
Bank announced the “Notice on Financial Services Support to the levels are undifferentiated. Before 2010, biomass power companies
Distributed Solar PV Power Generation”. had to overuse fossil fuels to ensure the break-even investments
due to the relative low FITs of biomass.
4.1.1.3. Biomass. The previous FITs for biomass, which were
established under the “Renewable Energy Law” in 2005, took 4.1.2. Subsidies to renewables through the FIT system
effect in 2006. The law stipulated a premium of CNY 0.25 per “Renewable Energy Law” regulated subsidies to renewable
kWh above the provincial average coal tariffs. As a result, standard energies in China through the FIT mechanism in 2005 (The
FIT of biomass reaches CNY 0.55–0.60 per kWh, which was Renewable Energy Law, 2005). In Chapter 5 of the Law, Article
considered sufficient to attract private investments (Martinot, 19 stipulates the principle of FIT for electricity generation by
2010). In 2010, NDRC issued “Notice on Perfection of Policy renewable energy; Article 20 stipulates the mechanism of full-
Regarding Feed-in-tariff of Power Generated by Biomass” (NDRC, acquisition and cost sharing. “Renewable Energy Law (Amendment
2010). The notice stipulated that the FIT for projects without Act)” in 2009 (The Renewable Energy Law, 2009) further improves
identified investors by bidding would be CNY 0.75 per kWh the subsidy mechanism through the FIT, including clauses con-
(including tax); and for projects that have identified investors by cerning full-acquisition, cost sharing and fund management of
tender, the FIT equals to the bid price, which would be lower than renewable energy (Fig. 2).
CNY 0.75 per kWh. The national surcharges on the sale price of electricity (Article
Ming et al. (2013) provided an overview of feed-in tariff policy 20 in Renewable Energy Law) failed to cover expenditures of
for renewable energy and analyzed the problems of feed-in tariff renewable power projects. A renewable energy fund including

Table 7
Renewable electricity pricing in China.

Renewable energy Price of approved projects Bid price Bid price plus the price Feed-in tariffs
by type of approved projects

Wind power (onshore) 0.3–1.2 CNY/kWh (1996–2003) 0.38–0.8 CNY/kWh (2003–2005) 0.4–0.65 CNY/kWh (2006–2009) 0.51–0.61 CNY/kWh (2009)
Solar PV power 4 CNY/kWh, 1.15 CNY/kWh 1.09 CNY/kWh (2009) 0.73–1.09 CNY/kWh (2009–2010) 1.15 CNY/kWh and 1
(2008–2009) CNY/kWh (early 2011);
0.90 CNY/kWh, 0.95
CNY/kWh, 1.00 CNY/kWh
(late 2011)
Biomass power Based on the project approval (2003); a 0.63 CNY/kWh (2006–2010) 0.55–0.65 CNY/kWh (before 2010) 0.75 CNY/kWh (2010)
premium of CNY 0.25 per kWh added to
the provincial average coal tariffs (2005)

Full acquisition + cost-sharing Full acquisition + cost-sharing


+ fund management

• Aticle 20: Power grid • Aticle 20 (amendment): The


companies are obliged to obey excess purchaing costs due to
the Aticle 19 to connect all higher renewable power
licensed renewable energy gernerartion costs than those
projects to the grid and of the conventional power will
purchase all electricity be retrieved via "power price
generated by renewable surcharges" on the sale price
energies. The Excess of electricity.
purchasing costs due to higher • Aticle 24 (new): A Renewable
renewable power generation development fund will be
costs than those of the established, which is
conventinal power will be composed of the annual
shared via the sale price. special funds from national
finance and surcharges on
electricity rates.

Fig. 2. Subsidy mechanism through the FIT of renewables in China.


X. Ouyang, B. Lin / Energy Policy 70 (2014) 64–73 71

surcharges on electricity rates and annual special funds under the Table 9
Ministry of Finance was established under the “Renewable Energy Additional required subsidies of solar PV through the FIT system in 2011.
Law (Amendment Act)” in 2009. Therefore, the subsidy mechanism
Regions in China Electricity Additional required subsidies (billion CNY)
through the FIT has been improved by the combination of cost generation
sharing and fund management. In short, the FIT system subsidizes (thousand At 5% At 8% At 10%
renewable power generators by paying a fixed, additional amount GWh) discount rate discount rate discount rate
of money for per unit electricity generation, above the on-grid
Other 0.81 0 0.108 0.206
electricity price for desulfurized coal-fired power. Tibet 0.1 0.028 0.056 0.074
Total in 2011 0.91 0.028 0.164 0.280

4.2. Estimates of required subsidies through the FIT system

Although the FIT system of renewables in China has been


Table 10
improved significantly, several deficiencies still exist. Firstly, Additional required subsidies of biomass through the FIT system in 2011.
feed-in tariffs (FITs) of solar PV and biomass energy are not
differentiated for regions at different resource endowment levels. Location Electricity Additional required subsidies (billion CNY)
generation
Secondly, the current FITs of solar PV are based on high quality
(thousand At 5% At 8% At 10%
resources in China, which do not take the relatively much higher GWh) discount rate discount rate discount rate
costs of low quality resources into account. Thirdly, FITs of renew-
ables need to be classified by resource conditions and be dynami- Nationwide 0.086 0 0 0.001
cally adjusted to reflect the adjustment of LCOE of renewable
energies. In conclusion, the FIT system of renewables need to play
of wind electricity in China, wind power plants located in regions
a more effective role in supporting the deployment of RE in China.
with low quality resources will face higher generation costs, and
In order to evaluate the support level of the current subsidy
more subsidies are thus needed.
mechanism, we estimate the additional required subsidies to
renewables through the FIT system.
4.2.2. Solar photovoltaics
The installed capacity of solar PV in China reached 3300 MW in
4.2.1. Wind (onshore) 2011. According to the data from SERC, grid-connected solar power
In Section 3, we estimated the LCOE of wind (onshore) at generation amounted to 0.914 billion kWh. Based on its proportion
different discount rates. The additional required subsidies to wind in China's total installed capacity, we estimate the grid-connected
power (onshore) are equal to the amount of generated electricity solar power generation of Tibet was 0.1 billion kWh in 2011.
multiplied by the difference between the LCOE and the FIT Table 9 shows the additional required subsidies of solar PV for
(excluding tax). In this paper, provincial power generation data China in 2011.
are taken from the “Annual Report of Electricity Regulation” in With a discount rate of 5%, there were no additional required
2011 issued by the State Electricity Regulatory Commission (SERC) subsidies of solar PV in China except Tibet in 2011. The additional
(SERC, 2011). The amounts of wind power generation (onshore) required subsidies increased when the LCOE was discounted at a
are calculated by the authors. Table 8 presents the additional higher rate. Moreover, the additional required subsidies of solar PV
required subsidies of wind (shore) in 2011. in Tibet were relatively much fewer due to the smaller amount of
The total additional required subsidies of wind (onshore) in electricity generation. To summarize, the additional required
2011 were 1.05, 9.23 and 14.76 billion CNY at the discount rates of subsidies of solar PV in 2011 were 0.028, 0.164 and 0.280 billion
5%, 8% and 10%, respectively. Additional required subsidies in four CNY with discount rates of 5%, 8% and 10%, respectively.
areas at different wind resource endowment levels show an
increasing trend with the decline in quality of wind resource. 4.2.3. Biomass
The additional required subsidies of wind (onshore) (Class IV) in The current FITs of biomass are not differentiated in accordance
2011 were the highest, which were predicted to be 0.81 billion with resource endowments. Biomass power technology confronts
CNY at 5% discount rate, accounting for 77% of the total additional the problem of resource collection (e.g., the collection of agricul-
required subsidies of wind power in China; and 6.72 billion CNY at tural wastes), which is costly and transport-intensive (Martinot,
10% discount rate, accounting for 35% of the total additional 2010). Under the previous FIT system, biomass power plants have
required subsidies of wind power at 10% discount rate. The above to overuse fossil fuels to ensure the break-even investment. The
data imply that the levelized cost of wind (onshore) electricity not pricing mechanism for biomass has been improved since 2011.
only increases with the increase in discount rate, but also increases Table 10 shows that the current FIT of biomass effectively satisfied
with the decline in wind resource quality. With the development the development needs for biomass, and the additional required
subsidies were only 0.001 billion CNY in 2011 at 10% discount rate.
Table 8
Currently, the installed capacity as well as the amount of
Additional required subsidies of wind (onshore) through the FIT system in 2011.
electricity generation of biomass is small in China. As shown in
Category of wind Electricity generation The additional required subsidies Table 10, the FITs can cover the LCOE of biomass with discount
resource area (thousand GWh) (billion CNY) rates of 5% and 8%. The additional required subsidies of biomass
were predicted to be 0.001 billion CNY at 10% discount rate in 2011,
At 5% At 8% At 10%
discount discount discount
implying that the current FIT of biomass is reasonable.
rate rate rate

Class I 16.76 0.05 1.71 2.85 5. Conclusions and policy implications


Class II 16.15 0 1.80 2.94
Class III 11.92 0.19 1.40 2.25 Renewable energy is mainly deployed in the field of power
Class IV 31.18 0.81 4.31 6.72
Total in 2011 76.01 1.05 9.23 14.76
generation in China. An accurate cost estimation of renewable
electricity generation is the basis of making effective support
72 X. Ouyang, B. Lin / Energy Policy 70 (2014) 64–73

policies in China. This paper adopts the EGC Spreadsheet model to make timely policies to promote the sound development of
estimate the LCOE of renewables based on the data of 17 power renewable industry on the basis of rational distribution of
plants located in different regions of China. Results indicate that resources. In particular, the development of RE in China must be
the LCOE of wind power (onshore) in China ranges from 0.473 to undertaken in order. The construction of long-distance and large-
0.827 CNY/kWh at 5% to 10% discount rates and the additional capacity power transmission based on ultra high voltage (UHV)
required subsidies are predicted to be 1.05–14.76 billion CNY in technology in China must be launched as soon as possible.
2011. The LCOE of solar PV in China ranges from 0.818 to Otherwise, the large-scale development of RE would not only
1.800 CNY/kWh at 5–10% discount rates, and the additional bring about a heavy financial burden, but also lead to the waste of
required subsidies are predicted to be 0.028  0.280 billion CNY money and resources. Network difficulties have existed in China
in 2011. The LCOE of biomass in China ranges from 0.585 to for many years. China's power grid construction has lagged behind
0.731 CNY/kWh at 5–10% discount rates and additional required the investment in conventional power generation projects. The
subsidies were only 0.001 billion CNY in 2011 at 10% discount rate. rapid expansion of installed capacity of renewable energy has not
The fixed capital investment is an important factor affecting the been matched by grid connection (Zhang and Li, 2012). As a result,
LCOE of renewables. However, due to the uncertainty of invest- the grid connection of renewable power has formed a significant
ment profit margin, financial institutions have little motivation to barrier for the large-scale renewables electricity deployment. Due
invest in the capital-intensive RE projects. Therefore, supportive to the failure of grid connection, the scale of “abandoned wind”
government policies, including policy-related loans, subsidized has showed an increasing trend in recent years, and a large
loans, tax deductions and exemptions and direct subsidies, are amount of solar energy in Western China has also been wasted.
necessary and crucial. In conclusion, in order to solve the problem Considering the characteristics of intermittent power generation
of high cost of RE, the Chinese government should provide from clean energy, the construction of smart grid is the prerequi-
subsidies in the short term; and more importantly, reform the site for the large-scale development of RE in China. Therefore,
electricity pricing mechanism in the mid-and long term to make supportive policy for the development of RE in China should be
RE competitive in energy market. adapted and targeted.
Subsidies to renewable power generation in the short-term are
mainly implemented through the feed-in-tariff (FIT) system.
Hence, it is of great importance to estimate the LCOE of RE based Acknowledgments
on the data of different power plants in different regions of China.
The United States experience sets a good example for China in The paper is supported by Newhuadu Business School Research
establishing a comprehensive database of RE power plants and in Fund, the China Sustainable Energy Program (G-1305-18257),
estimating the LCOE by different technologies. Plant-based infor- National Social Science Foundation of China (Grant No. 12&ZD059),
mation system has not been established in China, resulting in the and Ministry of Education (Grant No. 10 JBG 013). The authors
backwardness of FIT system of RE. Although the Chinese govern- appreciate Shiying Pan and Yanan Ma for the help of English
ment has gradually increased FIT to ensure the stable income of language editing.
renewable power companies, foreign and private investors still
lack confidence due to the relatively low or even negative profit References
margins. We must consider the unique characteristics in the
pricing of RE power in China. On one hand, due to the technolo- ACORE, 2011. U.S.–China quarterly market review. Available at: 〈http://www.acore.
gical limitations, RE generation costs are much higher than those org/wp-content/uploads/2011/12/ACORE_QMR-fall2011_FNLhipdf [accessed 5.
25.13]〉.
of the conventional energies, if the environmental costs of fossil Branker, K., Pathak, M.J.M., Pearce, J.M., 2011. A review of solar photovoltaic
fuels are not taken into account. Therefore, RE is unable to levelized cost of electricity. Renew. Sustain. Energy Rev. 15, 4470–4482.
compete with traditional fossil fuels in electricity market. On the Chen, H.H., Lee, A.H., Chen, S., 2014. Strategic policy to select suitable intermedi-
aries for innovation to promote PV solar energy industry in China. Appl. Energy
other, environmental impacts of the development and utilization 115, 429–437.
of RE are much smaller than those of fossil fuels. The above- China Meteorological Administration, 2009. Detailed survey and evaluation of wind
mentioned characteristics should be reflected in the FIT to effec- energy resources has made new progress. Available at: 〈http://www.gov.cn/
jrzg/2009-12/31/content_1501282.htm〉 (in Chinese) (accessed 25.05.13.).
tively support the development of RE.
Chung-Ling Chien, J., Lior, N., 2011. Concentrating solar thermal power as a viable
In the long run, the Chinese government must rationalize the alternative in China's electricity supply. Energy Policy 39 (12), 7622–7636.
electricity pricing mechanism, otherwise the development of RE Congressional Budget Office, 2012. Federal financial support for the development
would be subject to the constraints of power tariffs (Lin and Li, and production of fuels and energy technologies. Available at: 〈http://www.cbo.
gov/sites/default/files/cbofiles/attachments/03-06-FuelsandEnergy_Brief.pdf〉
2012). Most well developed renewable projects in China are (accessed 25.05.13.).
located in areas with superior resources. However, the subsequent Couture, T., Gagnon, Y., 2010. An analysis of feed-in tariff remuneration models:
development of RE will inevitably face two awkward situations: implications for renewable energy investment. Energy Policy 38 (2), 955–965.
CWEA, 2012. China's installed capacity of wind power in 2012. China Wind Energy
first, lower quality of resource endowments; and second, decreased Association. China Renewable Energy Society (CRES), Beijing, China.
subsidies from the government. Dinica (2011) argued that national- Darling, S.B., You, F.Q., Veselka, T., Velosa, A., 2011. Assumptions and the levelized
contextual factors such as geographic, infrastructural and resource cost of energy for photovoltaics. Energy Environ. Sci. 4, 3133–3139.
Dinica, V., 2011. Renewable electricity production costs—a framework to assist
factors also have a strong influence on renewable electricity policy-makers' decisions on price support. Energy Policy 39 (7), 4153–4167.
production costs. Even if the cost of RE can be reduced through Elliston, B., Macgill, I., Diesendorf, M., 2013. Least cost 100% renewable electricity
the localization of equipment production, the overall energy costs scenarios in the Australian National Electricity Market. Energy Policy 59,
270–282.
will be pushed up by the large-scale development of RE. Further- European Commission, 2008. Commission Staff Working Document, Brussels.
more, it is impossible for the Chinese government to provide long- Available at: 〈http://ec.europa.eu/energy/climate_actions/doc/2008_res_working_
term subsidies to RE. If the electricity price in China could not be document_en.pdf〉 (accessed 25.05.13.).
Flores, N.E., Carson, R.T., 1997. The relationship between the income elasticities of
rationalized, or the government kept subsidizing the electricity
demand and willingness to pay. J. Environ. Econ. Manag. 33 (3), 287–295.
generated from fossil fuels, the development of RE in China would Huo, M.L., Zhang, D.W., 2012. Lessons from photovoltaic policies in China for future
be constrained by electricity price. development. Energy Policy 51 (12), 38–45.
Although the development of RE is inevitable for China, we IEA, 2011. World Energy Outlook 2011. International Energy Agency, Paris, France.
IRENA, 2012a. Renewable power generation costs. Available at: 〈http://www.irena.
should promote it at the minimum cost. The standard of minimum org/DocumentDownloads/Publications/Renewable_Power_Generation_Costs.
cost requires the government to take corresponding measures and pdf〉 (accessed 25.05.13.).
X. Ouyang, B. Lin / Energy Policy 70 (2014) 64–73 73

IRENA, 2012b. Renewable energy technologies: cost analysis series-Solar photo- China. Available at: 〈http://www.gov.cn/zwgk/2011-08/01/content_1917358.
volatics. IRENA Working Paper 1 (4/5). Available at: 〈http://www.irena.org/ htm〉 (accessed 25.05.13.).
DocumentDownloads/Publications/RE_Technologies_Cost_Analysis-SOLAR_PV. NREL, 2004. Renewable energy in China. Available at: 〈http://www.nrel.gov/docs/
pdf〉 (accessed 25.05.13.). fy04osti/35789.pdf〉 (accessed 25.05.13.).
Jenner, S., Groba, F., Indvik, J., 2013. Assessing the strength and effectiveness of NREL, 2013. System Advisor Model (SAM) version 2013.1.15. Washington, D.C.
renewable electricity feed-in tariffs in European Union countries. Energy Policy Available at: 〈https://sam.nrel.gov/〉 (accessed 25.05.13.).
52 (1), 385–401. OECD, NEA/IEA, 2010. Projected Costs of Generating Electricity: 2010 edition.
Jiang, Z.J., Lin, B.Q., 2012. China's energy demand and its characteristics in the Organisation for Economic Co-operation and Development, Nuclear Energy
industrialization and urbanization process. Energy Policy 49, 608–615. Agency/International Energy Agency, Paris, France.
Khatib, H., 2010. Review of OECD study into “Projected costs of generating Qi, T., Zhang, X., Karplus, V.J., 2014. The energy and CO2 emissions impact of
electricity—2010 Edition”. Energy Policy 38 (10), 5403–5408. renewable energy development in China. Energy Policy 68, 60–69.
Klein, A., Held, A., Ragwitz, M., Resch, G., Faber, T., 2008. Evaluation of different Roth, I.F., Ambs, L.L., 2004. Incorporating externalities into a full cost approach to
feed-in tariff design options: best practice paper for the international feed-in electric power generation life-cycle costing. Energy 29 (12–15), 2125–2144.
cooperation, Fraunhofer ISI, under the National Development and Reform Schuman, S., Lin, A., 2012. China's Renewable energy law and its impact on
Commission, IEA, 2011. Energy technology roadmap: China wind power
renewable power in China: progress, challenges and recommendations for
development roadmap 2050. Available at: 〈http://www.iea.org/publications/
improving implementation. Energy Policy 51 (12), 89–109.
freepublications/publication/china_wind.pdf〉 (accessed 25.05.13.).
SERC, 2011. State Electricity Regulatory Commission.Annual Report of Electri-
Lesser, J.A., Su, X.J., 2008. Design of an economically efficient feed-in tariff structure
city Regulation in 2011. Available at: 〈http://www.serc.gov.cn/jggg/201208/
for renewable energy development. Energy Policy 36 (3), 981–990.
Li, A.J., Lin, B.Q., 2013. Comparing climate policies to reduce carbon emissions in P020120817333010586438.pdf〉 (accessed 25.05.13.).
China. Energy Policy 60, 667–674. Singh, P.P., Singh, S., 2010. Realistic generation cost of solar photovoltaic electricity.
Li, A.J., Zhang, A.Z., 2012. Will carbon motivated border tax adjustments function as Renew. Energy 35 (3), 563–569.
a threat? Energy Policy 47, 81–90. Tegen, S., Hand, M., Maples, B., Lantz, E., Schwabe, P., Smith, A., 2012. 2010 Cost of
Li, A.J., Zhang, A.Z., Cai, H.B., Li, X.F., Peng, S.S., 2013. How large are the impacts of Wind Energy Review. National Renewable Energy Laboratory, Colorado, USA.
carbon motivated border tax adjustments on China and how to mitigate them? The Renewable Energy Law, 2005. The renewable energy law of the People's
Energy Policy 63, 927–934. Republic of China. Available at: 〈http://www.gov.cn/fwxx/bw/gjdljgwyh/con
Li, W., Song, G., Beresford, M., Ma, B., 2011. China's transition to green energy tent_2263069.htm〉 (accessed 25.05.13.).
systems: the economics of home solar water heaters and their popularization The Renewable Energy Law (Amendment act), 2009. The renewable energy law of
in Dezhou city. Energy Policy 39 (10), 5909–5919. the People's Republic of China (Amendment act). Available at: 〈http://www.gov.
Lin, B.Q., 2012. Energy Shortage in China: A Rethinking. Science Press, Beijing, cn/flfg/2009-12/26/content_1497462.htm〉 (accessed 25.05.13.).
China, Beijing, China (in Chinese). Thiam, D.R., 2011. An energy pricing scheme for the diffusion of decentralized
Lin, B.Q., Li, A.J., 2011. Impacts of carbon motivated border tax adjustments on renewable technology investment in developing countries. Energy Policy 39
competitiveness across regions in China. Energy 36 (8), 5111–5118. (7), 4284–4297.
Lin, B.Q., Li, A.J., 2012. Impacts of removing fossil fuel subsidies on China: how large Wang, W.G., Zheng, G.G., 2012. Green Book of Climate Change—China's Policies and
and how to mitigate? Energy 44 (1), 741–749. Actions for Addressing Climate Change 2012: Climate FInancing and Low-
Mabee, W.E., Mannion, J., Carpenter, T., 2012. Comparing the feed-in tariff Carbon Development. Social Sciences Academic Press, Beijing, China (in
incentives for renewable electricity in Ontario and Germany. Energy Policy Chinese).
40 (1), 480–489. Wiser, R., Barbose, G., Peterman, C., Darghouth, N., 2009. Tracking the Sun—II: The
Martinot, E., 2010. Renewable power for China: past, present, and future. Front. Installed Costs of Photovoltaics in the US from 1998–2008. Report, Lawrence
Energy Power Eng. China 4 (3), 287–294. Berkley National Laboratory. Available at: /http://emp.lbl.gov/sites/all/files/
Ming, Z., Ximei, L., Na, L., Song, X., 2013. Overall review of renewable energy tariff
REPORT%20lbnl-2674e.pdfS (accessed 02.04.14.).
policy in China: evolution, implementation, problems and countermeasures.
Wu, Y.N., Xu, R.H., 2013. Current status, future potentials and challenges of
Renew. Sustain. Energy Rev. 25, 260–271.
renewable energy development in Gansu province (Northwest China). Renew.
Moore, S., Durant, V., Mabee, W.E., 2013. Determining appropriate feed-in tariff
Sustain. Energy Rev. 18 (2), 73–86.
rates to promote biomass-to-electricity generation in Eastern Ontario, Canada.
Zhang, P.D., Yang, Y.L., Shi, J., Zheng, Y.H., Wang, L.S., Li, X.R., 2009. Opportunities
Energy Policy 63, 607–613.
National Energy Administration, 2012. The 12th Five-Year Plan on the development and challenges for renewable energy policy in China. Renew. Sustain. Energy 13
of biomass (in Chinese). Available at: 〈http://www.gov.cn/zwgk/2012-12/28/ (2), 439–449.
content_2301176.htm〉 (accessed 25.05.13.). Zhang, S., He, Y., 2013. Analysis on the development and policy of solar PV power in
NDRC, 2009. Notice on perfection of policy regarding feed-in tariff of power China. Renew. Sustain. Energy Rev. 21, 393–401.
generated by wind. National Development and Reform Commission, China. Zhang, S., Andrews-Speed, P., Zhao, X., He, Y., 2013. Interactions between renewable
Available at: 〈http://www.sdpc.gov.cn/zcfb/zcfbtz/2009tz/t20090727_292827. energy policy and renewable energy industrial policy: a critical analysis of
htm〉 (accessed 25.05.13.). China's policy approach to renewable energies. Energy Policy 62, 342–353.
NDRC, 2010. Notice on perfection of policy regarding feed-in tariff of power Zhang, S., Li, X., 2012. Large scale wind power integration in China: analysis from a
generated by biomass. National Development and Reform Commission, China. policy perspective. Renew. Sustain. Energy Rev. 16 (2), 1110–1115.
Available at: 〈http://www.ndrc.gov.cn/zcfb/zcfbtz/2010tz/t20100728_363362. Zhang, S.H., 2011. Analysis of Operation Cost and Cost Reduction Method of Wind
htm〉 (accessed 25.5.13.). Power, China Wind Power. China Wind Power Group Limited, China.
NDRC, 2011. Notice on perfection of policy regarding feed-in tariff of power Zhang, S., Andrews-Speed, P., Ji, M., 2014. The erratic path of the low-carbon
generated by solar PV. National Development and Reform Commission, transition in China: evolution of solar PV policy. Energy Policy 67, 903–912.

You might also like