Registered Name of Business The Farm at San Francisco, Inc.
Production Cycle January 1, 2020 - July 31, 2020
Production Type Vegetable
Progress JANUARY FEBRUARY MARCH APRIL MAY JUNE JULY
Person-in- Tasks (Completed/O W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W Charge ngoing) Duration 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 Select good quality seeds in accordance with PNS, NSQCS, BPI Aning 1-2 days 1.2 Prepare seedtray and potting media Ka-Jojo, Ka- Julio 1-2 days 1.3 Cultivate and maintain seedlings Ka-Jojo, Ka- Julio 10-15 days 1.4 Prepare land for vegetable planting Ka-Jojo, Ka- Julio 2-3 days 1.5 Transplant seedlings to plots Ka-Jojo, Ka- Julio 2-3 days 1.6 Manage and cultivate vegetables Ka-Jojo, Ka- Julio 2-5 months 1.7 Harvest vegetables Ka-Jojo, Ka- Julio 1-2 weeks 1.8 Package for distribution David 1 week 1.9 Deliver to merchants David 2-3 days