Professional Documents
Culture Documents
Mock exam
Operations and Supply Chain
Management
25.10.2018
Sample solution
a) Separate the terms "operations processes" and "supply chain processes". Give a brief
example of each process. (2 points)
Operations processes: Manufacturing and service processes that convert input goods
(resources) into products
Example: manufacturing cars
Supply Chain Processes: Processes that transport material and information from and to
manufacturing and service processes through the supply chain.
Example: logistics processes
b) Name the five phases of the product development process that you learned during the
lecture. (3 points)
Phase 0: Planning
Phase 1: Concept Development
Phase 2: System-level Design
Phase 3: Detail Design
Phase 4: Testing and Refinement
Phase 5: Production Ramp-Up
a) Specify the corresponding payment series (incoming and outgoing payments). (2 points)
Sale of the
Investment Revenues
machine
Time t t0 t3 t1 t2 t3
b) What is the net present value of the investment rounded to the nearest thousand euros? (2
points)
62,07
NPV = 62 T€
c) Is the investment profitable with respect to the result from b)? Explain. (1 point)
1), KW>0
NPV = 62.070 € > 0 execute!
a) The figure below shows the empty balance sheet of OSCM Ltd. First name the usual
subcategories of the two pages (marked with (a)). (1 point - 0.5 per complete pair of terms)
Balance Sheet
Assets Liabilities
Furniture 13.000 €
Cash 21.000 €
b) After an inventory, you receive details about the company. Please classify the items listed
below correctly in the balance sheet. How high is the equity? (6 points)
a) Set up the revenue and cost functions and enter the functions in the diagram below. Also
name the axes (boxes). (3 points)
profit zone
Cost function
Loss zone
Quantity X
b) How is the intersection of the two functions (revenue and cost function) called? (1 point)
Break-Even Point
c) Clearly mark (!) the profit zone and the loss zone in the chart. (1 point)
a) Name 4 criteria that are used for the choice of a legal form. (2 points)
Partnership / Corporation
Administration
Capital risk (limited/unlimited liability), Taxation
Auditing and disclosure requirements
Financing options (creditworthiness)
Foundation (Form: informal, entry in the commercial register; number of
shareholders, minimum contribution)
b) Name the characteristics of the two company forms “GmbH” and "AG" regarding the
given categories! (2 points)
Category GmbH AG
a) A factory has a maximum capacity of 4,000 units per day including overtime and daily
maintenance. At 3,500 units per day, the factory operates at a level where average costs
are minimal. Currently, 3,000 units per day are planned. How high is the capacity
utilization rate? Enter the formula for calculating the value. (1 point)
= 3000/3500 = 85,7%
b) Name and describe the different time horizons in capacity planning. What is the time
horizon for the decision to build a new production hall? (2 points)
c) There are two alternatives for the decision to increase capacity. The first alternative is
estimated at 1.000.000€ cost and a profit of 550.000€/450.000€ over the next 3 years
with strong/low growth, the second alternative at 800.000€ cost and a profit of
500.000€/400.000€ over the next 3 years with strong/low growth. Which alternative would
you choose? What is the expected profit? Assume an interest rate of 10%. The
probability for a strong growth is 55%, for a low growth 45%. (3 points)
Alternative 1:
Alternative 2:
a) What is the name of the type of production if a company produces already developed
products only after receiving the customer's request? Is the inventory risk high or low for
this type of production? (1 point)
Therefore, the service strategy, the employees and the support systems that serve
the customer and support the employees are built around it.
OSCM departments in the company are responsible for the service system
(equipment, etc.) and the management of the service staff.
c) The process types in production differ in individual characteristics. Assign the given
production processes the correct description. Only one answer is correct at a time. (1 point)
1: Site fabrication
2: Shop fabrication
3: Group fabrication
4: Flow production
5: Continous process
Number Description
d) Hybrid-electric vehicles currently make use of conventional drive systems such as the
internal combustion engine. In their production, the manufacture of crankshafts is an
important component. The crankshafts are to be manufactured in 4 process steps
(forging "f" drilling "d" forging "f" joining "j"). Roughly outline the hall layout with
typical machine arrangements and the material flow, if the production is aligned
according to the principle of Shop fabrication. (2 points)
e) The transport graph below (with adjacent key) of a Job Shop with manufacturing equipment
(ME) 1 to 5 is given. Fill out the transport cost matrix completely. (2 points)
A
5 1
B Letter Material flow costs
C
A 3 B
A 5
B A C
2 A+C 4 B 10
A C 30
ME 1 ME 2 ME 3 ME 4 ME 5
ME 1 30 30 10 5
ME 2 - 10 35 5
ME 3 - - 5 -
ME 4 - - - 5
ME 5 - - - -
f) Why should the cycle time not be greater than the customer takt? (1 point)
g) The figure below shows five workstations (AP) of a flow line. What is the efficiency of the
line? (2 points)
Efficiency = 75,8 %
Efficiency:
∑cycle time = 81,9 sec + 96,3 sec + 79 sec + 67 sec = 378,9 sec
Current number of stations*cycle time per station: 5 * 100 sec = 500 sec
Efficiency = (378,9/500)*100% = 75,8%
a) A flow chart of a warehouse is given which accepts orders from 7 am to 7 pm. How is the
bottleneck of a process chain defined? Which process represents the bottleneck of the
represented overall process? (1 point)
The bottleneck is "Pack orders" with a capacity of approx. 60 orders per hour.
b) In the flowchart above, what is the current maximum number of customer orders the
warehouse can ship per hour without overtime? (1 point)
The maximum number of customer orders is the minimum {"Accept orders", "Combine
orders", "Pack orders"} with a capacity of approx. 60 orders per hour
c) What is the maximum number of customer orders you can make ready for dispatch if you
increase the capacity in the packing process to 120 orders per hour? At what points will
blockages and idle times occur? (2 points)
d) Which method cannot be used to shorten the residence time in a system? Please tick the
correct answer. (1 point)
Elimination of bottlenecks
x Pooling of activities
e) You perform a value stream analysis and count a stock of 100 components at a buffer
between two production steps. What is the average residence time of a component in the
buffer if an average of 20 components per hour reach and leave the buffer? Also enter
the formulas for the calculation. (1 point)
b) In the Failure Mode and Effects Analysis (FMEA), the risk of an error is quantified by the
Risk Priority Number (RPN). Specify the formula for calculating the RPN and name the
three factors that make up the risk priority number. (1 point)
c) If a process has a tolerance width of 2mm and a standard deviation of 0.2mm, how far
may the mean be from the target mean to achieve a Cpk value > 1? (1 point)
bar{x} – LSL > 3sigma = 0,6mm distance < 0,4mm from target mean
d) Determine the upper and lower control limits of a p-chart where 𝑝̅ = 0.05, n = 100 and z =
2. (2 points)
a) You operate a Kanban system in which 60 parts per hour are retrieved from the
downstream station. The replenishment time is 3 hours and one container can hold 30
parts. How many Kanban cards do you need if 10% is to be planned as a safety buffer? (1
point)
𝑫∗𝑳 ∗(𝟏+𝑺)
𝒌= = [60 parts/h * 3h * (1,1)]/ 30 parts = 6,6 = 7
𝑪
cards
b) A small company looking for a new production site supplies three production plants with
the following coordinates and demand volumes. Use the Centroid method to find a new
production site for the small company. (2 points)
𝜮𝒅𝒊𝒙∗𝑽𝒊 𝜮𝒅𝒊𝒚∗𝑽𝒊
𝑪𝒙 = 𝑪𝒚 =
𝜮 𝑽𝒊 𝜮 𝑽𝒊
Cx Cy
Peoria
Decatur
Joliet
a) Which supply chain strategy would you recommend for the product FiFi at the
beginning of the product life cycle? Categorize it according to the dimensions "supply
uncertainty" and "demand uncertainty". What is the goal of the chosen SC strategy?
(2 points)
Demand and supply uncertainty high Agile Supply Chain Rapid response to
conditions through flexibility and risk sharing
b) At a certain point in time, you have 1.89 weeks of supply in the system on a value
basis. The average inventory value is €5,897. What are the annual production costs?
(2 points)
a) Determine a forecast with a seasonality factor. You know the following information: (3
points)
Season 2: seasonality factor: 400/600 = 0,66; forecast season: 400 * 0,66 = 267
Season 3: seasonality factor: 800/600 = 1,33; forecast season: 400 * 1,33 = 533
b) You use the moving average method for your sales forecast. How does the number of
periods used affect the forecast? (2 points)
The fewer previous periods used for the forecast (smaller "n"), the weaker the sales
fluctuations of the individual periods are dampened. The more previous periods used for the
forecast (larger "n"), the more the sales fluctuations of the individual periods are dampened.
c) Determine a forecast using the exponential smoothing method for the following data for
periods 2 to 4 and a smoothing factor of 0.25. (3 points)
d) Determine the forecast errors with the key figures MAD and MAPE for all four periods. (3
points)
a) For the following demand data, determine the physical inventory at the end of the period,
the shortfall and the shortage and then calculate the α, β and γ service level. (3 points)
2 83 2 0 0
3 44 0 42 42
4 57 0 57 99
5 46 255 0 0
b) Label the following figure for the inventory with the respective descriptions (no
abbreviations)! Enter the formula for the available inventory below! (2 points)
Goods receipt
Reorder point
Inventory
Inventory Position
Inventory on hand
c) Determine the optimal order quantity (Qopt) for the Q-model as well as the lower order limit
(R) for a desired security of 95 % (z=1.64) and formulate the rule for triggering an order.
The following information is known: (4 points)
Rule: As soon as the inventory on hand becomes smaller or equal than the lower order
limit R, a purchase of 103 units is triggered.