PERHITUNGAN VOLUME PEKERJAAN MASJID

I. PEKERJAAN PENDAHULUAN
1 Pembersihan Lapangan dan Perataan : 23.00 m x 20.00 m = 460.00 m2 460.00 m2
2 Pemasangan Bowplank 23.00 m + 23.00 m + 20.00 m + 20.00 m = 86.00 m1 86.00 m1

II. PEKERJAAN TANAH DAN PONDASI


1 Galian Tanah Pondasi 212.80 m3
Pondai P1 2.00 m x 2.00 m x 0.95 m x 56.00 bh = 212.80 m3
= 212.80 m3

2 Pondasi Cerucuk dia. 15 cm - 12 meter 832.00 btg


Pondai P1 1.00 brs x 52.00 klm x 16.00 bh = 832.00 btg
= 832.00 btg

3 Urugan Pasir di bawah pondasi 21.50 m3


Pondai P1 1.60 m x 1.60 m x 0.15 m x 56.00 bh = 21.50 m3
= 21.50 m3

4 Lantai Kerja Beton K-125 7.17 m3


Pondai P1 1.60 m x 1.60 m x 0.05 m x 56.00 bh = 7.17 m3
= 7.17 m3
5 Pelat Pondasi Beton Bertulang
Pondasi P1
Beton K-225 38.86 m3
1.60 m x 1.60 m x 0.25 m x 56.00 bh = 35.84 m3
0.60 m x 0.60 m x 0.15 m x 56.00 bh = 3.02 m3
= 38.86 m3

Tulangan 2,564.30 kg
D 16 mm Berat = 1.579 kg/m
1.92 m x 2.00 = 3.84 m
0.17 m x 2.00 = 0.34 m
0.10 m x 2.00 = 0.20 m
= 4.38 m x 6.00 bh x 56.00 bh = 1,471.68 m1
0.52 m x 1.00 = 0.52 m
0.32 m x 2.00 = 0.64 m
0.10 m x 2.00 = 0.20 m
= 1.36 m x 2.00 bh x 56.00 bh = 152.32 m1
= 1,624.00 m1

1,624.00 m1 x 1.579 kg/m = 2,564.30 kg

Bekisting 132.16 m2
2.00 m x 0.25 m x 4.00 bh x 56.00 bh = 112.00 m2
0.60 m 0.15 m x 4.00 bh x 56.00 bh = 20.16 m2
= 132.16 m2

6 Kolom Pondasi Beton Bertulang


Kolom Pondasi P1 (400 mm x 400 mm)
Beton K-225 8.51 m3
0.40 m x 0.40 m x 0.95 m x 56.00 bh = 8.51 m3
= 8.51 m3

Tulangan 2,613.05 kg
D 16 mm Berat = 1.579 kg/m
1.99 m x 1.00 = 1.99 m
0.30 m x 1.00 = 0.30 m
= 2.29 m x 12.00 bh x 56.00 bh = 1,538.88 m1
1,538.88 m1 x 1.579 kg/m = 2,429.89 kg
 8 mm Berat = 0.395 kg/m
0.32 m x 4.00 = 1.28 m
0.05 m x 2.00 = 0.10 m