4. Identify the critical path. 6.

Assume that the company wants to complete the project in 26


Paths: weeks. What crashing decisions do you recommend to meet the
1-2-3-5-6 (10+8+10+3) = 31 weeks *critical path desired completion time at the least possible cost?
1-2-4-5-6 (10+7+10+3) = 30 week If the company wants to complete the project in 26 weeks, the
crash decisions I’d recommend are 2-3, 2-4 and 3-5.
5. What is the project's expected completion time and cost?

Initial Stage 7. How much will be the total project cost after the crashing
Paths: decisions?
1-2-3-5-6 (10+8+10+3) = 31 weeks *critical path Path:
1-2-4-5-6 (10+7+10+3) = 30 weeks 1-2-3-5-6 (10+6+7+3) = 26 weeks
Projected Time: 31 weeks Projected Time: 26 weeks
Activities Crashed: none Activities Crashed: 2-3, 2-4, 3-5
Project Cost: P400,000 Project Cost: P500,000

Second Stage
Paths:
1-2-3-5-6 (10+6+10+3) = 29 weeks
1-2-4-5-6 (10+7+10+3) = 30 weeks *critical path
Projected Time: 30 weeks
Activities Crashed: 2-3
Project Cost: P430,000

New Stage Table


Paths:
1-2-3-5-6 (10+6+10+3) = 29 weeks *critical path
1-2-4-5-6 (10+6+10+3) = 29 weeks *critical path
Projected Time: 29 weeks
Activities Crashed: 2-3, 2-4
Project Cost: P440,000