Semaines 4 5 6 7 8

ventes 200 200 200 200 200

1 2 3 4 5 6 7 8
PF BB 200 200 200 200 200
AD 100 50 00 100 50 00
BN 100 150 200 100 150
PF OP C2 C1 150 150 300 150 150
AD 100 50 300
Délais 1 1 2
LOT 150 120 400

BB(C2) 1 2 3 4 5 6 7 8
= C2 BB 300 300 600 300 300
OP(PF AD 50 110 50 50 110 50
) BN 250 190 550 250 190
X2 OP 360 240 600 360 240

BB(C1) -1 1 2 3 4 5 6 7 8
= C1 BB 360 390 750 660 390 150
OP(PF)x1 AD 300 340 350 00 140 150 00
+
BN 60 50 400 660 250 00
OP(C2) x1
OP 400 400 400 800 400 00
4 5 6 7 8 9 10 11 12 13 14 15
PF BB 85 100 0 110 120 90
AD 230 145 45 45 85 115 25
BN -- --- --- 65 35 ---
OP 150 150

BB(SE1) 4 5 6 7 8 9 10 11 12 13 14 15
= SE1 BB 150 150
OP(PF) x1 AD 60 30 00
BN 90 120
OP 120 120

BB(SE2) 4 5 6 7 8 9 10 11 12 13 14 15
= SE2 BB 300 300
OP(PF) x2 AD 50 50 50
BN 250 250
OP 300 300

BB(C1) 4 5 6 7 8 9 10 11 12 13 14 15
= C1 OP(SE1) 120 120
OP(SE1) x3 OP(SE2) 300 300
+
BB 360 960 600
OP(SE2) x2
AD 0 00 00 00
BN 360 960 600
OP 360 960 600

BB(C2) 4 5 6 7 8 9 10 11 12 13 14 15
= C2 BB 120 720 600
OP(SE1) x1 AD 65 25 25 65
+
BN 55 695 575
OP(SE2) x2
OP 80 720 640