H = 2.50 m
F"c = 210 kg/m2
S/c = 400 kg/m2
Fy = 4200 kg/cm2
P = 0.25
Muro = 0.25
PASO TRAMO 1
L 1.50
N°P = = = 6
0.25 0.25
PASO TRAMO 2
L 1.50
N°P = = = 6
0.25 0.25
contrapaso
H - 0.25
CP =
P
2.50 - 0.25
CP = = 0.188
12
CP = 0.188 m
PRIMER TRAMO
calculo de "t"
t = Ln o Ln
20 25
Ln = Lo + N° pisos -2 * P
Ln = 1.25 + 4 * 0.25
Ln = 2.25
2.25 = 0.11
20
t= t= 0.11 + 0.09
2.25 = 0.09 2
25
t= 0.10 m
cos Φ = 0.80
METRADO DE CARGAS
1.95 tn/m
1.45 tn/m
A B
1.375 1.25
RA RB
2.625
∑24▒ 〖𝑀
𝐴 =0 〗
2
1.45 * 1.375 + 1.95 * 1.25 * ( 1.375 + 0.625 ) - RB 2.625 =
2
RB = 2.38 Tn RA = 2.05 Tn
1.45 tn/m
A Mx
2.05
2
2.05 X - 1.45 X - Mx = 0
2 2
Mx = 2.05 X - 1.45 X …........................
2
2.05 - 1.45 X - Vx = 0
Mx = Mmax cuando Vx = 0
2
Mmax = 2.05 1.42 - 1.45 1.42
2
Mmax = 1.45 Tn-m
´-Mmax = ´+Mmax
3
´-Mmax = 0.43 Tn-m
SEGUNDO TRAMO
calculo de "t"
t = Ln o Ln
20 25
Ln = Lo + N° pisos -2 * P
Ln = 1.25 + 4 * 0.25
Ln = 2.25
2.25 = 0.11
20
t= t= 0.11 + 0.09
2.25 = 0.09 2
25
t= 0.10 m
cos Φ = 0.80
METRADO DE CARGAS
1.95 tn/m
1.45 tn/m
A B
1.375 1.25
RA RB
2.625
∑24▒ 〖𝑀
𝐴 =0 〗
2
1.45 * 1.375 + 1.95 * 1.25 * ( 1.375 + 0.625 ) - RB 2.625 =
2
RB = 2.38 Tn RA = 2.05 Tn
1.45 tn/m
A Mx
2.05
2
2.05 X - 1.45 X - Mx = 0
2 2
Mx = 2.05 X - 1.45 X …........................
2
2.05 - 1.45 X - Vx = 0
2
Mmax = 2.05 1.42 - 1.45 1.42
2
Mmax = 1.45 Tn-m
´-Mmax = ´+Mmax
3
´-Mmax = 0.43 Tn-m
DISEÑO DE ESCALERA
= 1.03
"a= " "Asxf
´y" /"0.85xf´cxb"
ITERANDO
Acero minimo
Asmin = 0.0018*b*d = 0.0018 * 125 * 7 = 1.58 cm2 <
Separacion:
Cuantia maxima
Cuantia
p= As = 5.31
b*d 125 7
Cuantia minima
Separacion:
N! de varillas:
As Φ 3/8" = 0.39
Ast
USAR:
Φ 3/8" cada 0.39 m
1.25
1.25
1.5
0
cm
As = 5.31 cm2 OK CUMPLE!!
DISEÑO ESCALERA DE 2 TRAMOS
H = 2.50 m
F"c = 210 kg/m2
S/c = 400 kg/m2
Fy = 4200 kg/cm2
P = 0.25
Muro = 0.25
PASO TRAMO 1
L 1.50
N°P = = = 6
0.25 0.25
PASO TRAMO 2
L 1.50
N°P = = = 6
0.25 0.25
contrapaso
H - 0.25
CP =
P
2.50 - 0.25
CP = = 0.188
12
CP = 0.188 m
PRIMER TRAMO
calculo de "t"
t = Ln o Ln
20 25
Ln = Lo + N° pisos -2 * P
Ln = 1.25 + 4 * 0.25
Ln = 2.25
2.25 = 0.11
20
t= t= 0.11 + 0.09
2.25 = 0.09 2
25
t= 0.10 m
cos Φ = 0.80
METRADO DE CARGAS
1.95 tn/m
1.45 tn/m
A B
1.375 1.25
RA RB
2.625
∑24▒ 〖𝑀
𝐴 =0 〗
2
1.45 * 1.375 + 1.95 * 1.25 * ( 1.375 + 0.625 ) - RB 2.625 =
2
RB = 2.38 Tn RA = 2.05 Tn
1.45 tn/m
A Mx
2.05
2
2.05 X - 1.45 X - Mx = 0
2 2
Mx = 2.05 X - 1.45 X …........................
2
2.05 - 1.45 X - Vx = 0
Mx = Mmax cuando Vx = 0
2
Mmax = 2.05 1.42 - 1.45 1.42
2
Mmax = 1.45 Tn-m
´-Mmax = ´+Mmax
3
´-Mmax = 0.43 Tn-m
SEGUNDO TRAMO
calculo de "t"
t = Ln o Ln
20 25
Ln = Lo + N° pisos -2 * P
Ln = 1.25 + 4 * 0.25
Ln = 2.25
2.25 = 0.11
20
t= t= 0.11 + 0.09
2.25 = 0.09 2
25
t= 0.10 m
cos Φ = 0.80
METRADO DE CARGAS
1.95 tn/m
1.45 tn/m 1.45 tn/m
A B
1.375 1.25 1.375 RB
RA 4
∑24▒ 〖𝑀
𝐴 =0 〗
( )
1.95 tn/m
1.45 tn/m
A Mx
3.21
2 POR SIMPLE SIMETRIA
3.21 X - 1.45 X - Mx = 0
2 2 RA = RB = 1.45
Mx = 3.21 X - 1.45 X …........................ 2
2
RA = RB = 3.21
3.21 - 1.45 X - Vx = 0
2
Mmax = 3.21 2.22 - 1.45 2.22
2
Mmax = 3.55 Tn-m
´-Mmax = ´+Mmax
3
´-Mmax = 1.07 Tn-m
DISEÑO DE ESCALERA
= 2.53
"a= " "Asxf
´y" /"0.85xf´cxb"
ITERANDO
Acero minimo
Asmin = 0.0018*b*d = 0.0018 * 125 * 7 = 1.58 cm2 <
Separacion:
Cuantia maxima
Cuantia
p= As = 15.08
b*d 125 7
Cuantia minima
Separacion:
N! de varillas:
As Φ 3/8" = 0.39
Ast
USAR:
Φ 3/8" cada 0.39 m
1.25
1.25
1.5
0
MPLE SIMETRIA
4.00 = 2.00
2
cm
As = 15.08 cm2 OK CUMPLE!!