Date : 5th September 2019

Project : Place Vendome _ HOTELS


Description : H3 Fire Detection & Alarm Schematic Diagram
Reference No. : CRC/MUD-VM/SD/ELV-1773 Rev. 01

Status : B “Approved With Comments”

Drawing Ref.: CRC-VM-H3-E-FA-0421A Rev. 01.


CRC-VM-H3-E-FA-0421B Rev. 01.

Comments:-

1. The submitted Schematic Diagram is accepted as a conceptual wise, however Contractor responsibility to
submit the remaining non-approved layout drawings for the other floors.
2. Power connection loop from RBS to the Sounder Base to be indicated on the drawing (no. of connected
sounder base to be considered as per the capacity of the RBS).
3. Contractor to adhere to relevant Local and International Regulations’.
4. Final Approval subject to the final acceptance after inspection by the Local Authority QCDD.

For Meinhardt (Singapore)

Reviewed by: _______________


MOHAMED FATHY
Project Manager