Comments:-
1. The submitted Schematic Diagram is accepted as a conceptual wise, however Contractor responsibility to
submit the remaining non-approved layout drawings for the other floors.
2. Power connection loop from RBS to the Sounder Base to be indicated on the drawing (no. of connected
sounder base to be considered as per the capacity of the RBS).
3. Contractor to adhere to relevant Local and International Regulations’.
4. Final Approval subject to the final acceptance after inspection by the Local Authority QCDD.