You are on page 1of 10

ARTICLE IN PRESS

Ocean Engineering 37 (2010) 454–463

Contents lists available at ScienceDirect

Ocean Engineering
journal homepage: www.elsevier.com/locate/oceaneng

Lake Sihwa tidal power plant project


Young Ho Bae a, Kyeong Ok Kim b, Byung Ho Choi c,
a
Daewoo E&C Co., Sihwa Lake Tidal Power Plant Project, Ansan 425-330, Republic of Korea
b
Korea Ocean Research & Development Institute, 1270 Sadong, Ansan 426-744, Republic of Korea
c
Department of Civil and Environmental Engineering, Sungkyunkwan University, 300 Chunchun-dong, Jangan-gu, Suwon 440-746, Republic of Korea

a r t i c l e in f o a b s t r a c t

Article history: A Tidal Power Plant (TPP) is being constructed in the middle section of the existing Lake Sihwa dike
Received 1 July 2009 located near the southern Incheon Port in Korea. The project, which will be completed in 2010, is to
Accepted 24 January 2010 harness the largest tidal energy in the Kyeonggi Bay in the eastern Yellow Sea. While noting the current
Available online 1 February 2010
progress in terms of plant construction, this paper outlines the overall project in the tidal regime and
Keywords: uses predictive local flow modeling. The results of two-dimensional finite element method simulations
Tidal power plant that predict the real-time tidal characteristics during the construction and after the completion of the
Sihwa Lake tidal power plant are presented, including a method to estimate the electricity output from the plant in
Tidal modeling the future.
& 2010 Elsevier Ltd. All rights reserved.

1. Introduction seawater exchange. The Korea Water Resources Corporation


(KOWACO, renamed as Kwater) has carried out a study on the
Lake Sihwa is located in the mid-western region of the Korean feasibility of the Sihwa tidal projects involving preliminary and
Peninsula in the Kyeonggi Bay where the coastline is irregular, execution designs. Fig. 1 shows the location of the Lake Sihwa
hosting numerous smaller bays and inlets of varying sizes and the Tidal Power Plant (TPP) construction site, indicating the mean
highest tides in the Yellow Sea. There are numerous possible spring tide of 7.8 m. Choi (1980) analyzed the tide at Incheon with
sites for building tidal power barrages to create reservoirs. During an extended harmonic analysis method. Thus, while one main
the 1930s, an intensive study on the feasibility of a tidal purpose of this project is to improve the water quality of Lake
power plant in southern Kanghwado was first performed by the Sihwa by seawater exchange, another main purpose is to provide
Chosun Governer’s Office (1930). In 1978, KORDI and Shawinigan an alternative, clean energy source (tidal energy) using a
Engineers performed extensive evaluations of the tidal power conventional tidal power generation method (Bernstein, 1965;
potential in this area to prioritize sites for development by the Bernstein et al., 1997) where an estuary is barraged with a dam, a
Korea Electric Company (1978). The most potential site was in the technique first suggested by Struben (1921). The volume of Lake
Asan Bay, where a port is currently being constructed. Instead, Sihwa is 323,769,000 m3 below EL.(+)0.0 m, and the surface area
Garolim Bay was designated as the tidal development site (KEPCO, is 42,441,000 m2. The possible capacity for power generation with
1993), and Lake Sihwa was created by constructing a dike in 1994 a one-way flood generation scheme is 147,040,000 m3 between
in order to secure agricultural and irrigation water for the region EL.( )5.0 m and EL.( )1.0 m.
and to develop industrial/agricultural lands near the metropolitan The tidal power plant, with a total project cost of approxi-
area. Along with the new 56.5 km2 freshwater lake, which is now mately USD 355 million, will be the first of its kind in South Korea
one of the largest tidal lakes in Korea, a total of 173 km2 of and the largest in the world since the construction of French La
reclaimed land was also created. Rance tidal power plant in 1965 (Gibrat, 1966). The project will
After the embankment was constructed, which was originally consist of a powerhouse containing 10 ‘bulb-type’ turbines with
designed to be a freshwater reservoir, severe water contamination direct driven generators, gates and other equipment (Fig. 2). The
occurred, resulting from an excessive inflow of polluted waste installed capacity of the turbines and generators is 254 MW
waters, mainly from an Ansan industrial complex. In order to (25.4 MW  10 bulb-type units with runner diameters of 7.5 m at
improve the water quality of the basin, the decision was to 64.29 rpm). The structure of the turbine and generator is
abandon the original freshwater reservoir scheme and allow monolithic with an open roof that utilizes natural light and
ventilation. Eight units of culvert (B 15.3 m  H 12.0 m) are
installed in the sluice gate. Dry work is provided by installing
 Corresponding author. Tel.: + 82 31 290 7534; fax: + 82 31 290 7549. stoplog on the front and back sides of the flood gate. The annual
E-mail addresses: bhchoi@skku.ac.kr, bhchoi.skku@gmail.com (B.H. Choi). energy output is expected to be about 552.7 GWh, given the

0029-8018/$ - see front matter & 2010 Elsevier Ltd. All rights reserved.
doi:10.1016/j.oceaneng.2010.01.015
ARTICLE IN PRESS
Y.H. Bae et al. / Ocean Engineering 37 (2010) 454–463 455

Fig. 1. Location of the Lake Sihwa tidal power plant construction site with tidal datum planes.

61.10

Gantry Crane (1,500kN)

Gantry Crane (500kN)


EL(+)8.00
EL(+)8.00
H.H.W
EL(+)5.366
O/H Crane (500kN) EL(+)2.00
13.00

Controlled
M.S.L
EL(-)1.20 Water Level
7.00
EL(-)0.024
EL(-)1.00
29.00

L.L.W EL(-)5.00
EL(-)5.645
8.00

21.90
14.90

EL(-)13.00
8.00

EL(-)19.90
EL(-)21.00
1.40

EL(-)23.30
5.50

EL(-)26.50

43.30
1.00

EL(+)18.00
10.00

Gantry Crane (500kN)


9.00

EL(+)8.00
EL(+)8.00
H.H.W
EL(+)5.366
12.00

EL(+)2.00
Controlled
M.S.L
Water Level
6.00

EL(-)0.024
24.00

EL(-)1.00
EL(-)4.00 EL(-)4.00
L.L.W
EL(-)5.645
21.00
12.00

12.00

EL(-)16.00
3.00
3.00

EL(-)19.00

Fig. 2. Schematic of the turbo-generator and sluice gate.

selected mode of power generation and maintaining a water level Kwater is the governmental water authority of the Republic of
below EL.(  )1.0 m in Lake Sihwa. The power plant is designed for Korea and acts as the project developer and owner. Daewoo E&C,
single effect flood generation that can be operated in one leading the Korean joint venture with other construction
direction, from the sea to the lake, allowing up to 60 billion contractors, is the project’s main contractor. VA Tech Hydro,
tons of seawater to be circulated annually. Austria will carry out the detailed design for the turbine/
ARTICLE IN PRESS
456 Y.H. Bae et al. / Ocean Engineering 37 (2010) 454–463

generator equipment, serving as the technology provider, while repeatedly been the subject of discussions during the past few
also providing supplies and services for electro-mechanical years. Regularly flushing the Sihwa Lake with seawater using a
elements of the plant. tidal power plant was finally identified as an acceptable remedy.
Since local industrial facilities take processed water from the It is expected that the project will be completed by 2010, and
lake and release wastewater into it, the Lake Sihwa zone has the Lake Sihwa tidal power plant will open up a new chapter in

Tourist Area TBN & GEN 10 Units Connecting Structure Sluice Gate 8 Units Green Zone

Fig. 3. A perspective view of the plant after completion.

Fig. 4. Work procedure of the major construction stage (1) before construction, (2) silt protection, (3) cofferdam and diversion roads construction, (4) dewatering, (5)
excavation for drywork, (6) Gantry Crane for temporary wharf*, (7) transport of turbo-generator*, (8) installation of turbo-generator, (9) construction of road over sluice
gates, (10) detachment of diversion roads, (11) removal of cellular cofferdam, (12) operational test of turbo-generator. (*This original plan was changed to use special
carrier to transport machineries between erection bay and crane sites.)
ARTICLE IN PRESS
Y.H. Bae et al. / Ocean Engineering 37 (2010) 454–463 457

alternative energy development as South Korea plans to sig- continental shelf since the 1980s (Choi, 1981) to study how large
nificantly increase spending on alternative energy sources in the coastal dikes could change the tidal patterns. These studies have
forthcoming years. It has been claimed that the project will help shown that the changes to the Kyeonggi Bay will be limited in
restore the Lake Sihwa ecosystem and water quality through the scope. This paper gives a general description of the project and
continuing seawater exchange during plant operation. However, it construction through August 2009.
is well known that flood generation schemes, which are usually
adopted to secure land within the lake for development, have the
disadvantage that the useable volume of water between the low 2. Construction of the tidal power plant
tide and mid tide in the lake is much less than that created by an
ebb generation scheme that utilizes the volume of water available The construction of a Tidal Power Plant (TPP) requires
between mid tide and high tide. Furthermore, a large portion of temporary circular cell cofferdams to enable dry work. The TPP
the intertidal areas are permanently exposed with flood genera- construction on Lake Sihwa is similar to the conventional La
tion schemes, resulting in a rapid change from marine ecosystem Rance project except that there is no precast concrete caisson
to a freshwater ecosystem, contrary to the claims that a marine structure. The Lake Sihwa cofferdams were built without
ecosystem can be preserved (Baker, 1991). Meanwhile, Prandle supporting rangers, and their stability is provided solely by the
(1984) has shown that a two-way mode can be operated at a more cell filling. While the standard length of a circular cell cofferdam is
constant head where the flushing regime in the enclosed tidal 28 m, the required length is up to 31.5 m for the Sihwa project due
basin remains closer to the undisturbed state, but this aspect to the water depth and ground conditions. The circular cell
cannot be exploited due to practical engineering realities. A cofferdam at Sihwa consists of 29 primary cells and 28 spandrel
perspective view of the Lake Sihwa tidal power plant after its walls; welded distribution piles connect the primary cells and
completion is shown in Fig. 3. The TPP consists of a (1) turbine and spandrel walls. The construction of a circular cell was performed
generator, (2) sluice gate, (3) connecting structure, (4) wing wall, offshore with the aid of a control desk. The flat sections were
(5) road, (6) tourist site, (7) administration facilities and (8) lifted by crane from a pontoon and driven to the required depth at
erection bay and central control room. the site with the aid of vibrating hammer. Fig. 4 shows the major
Along with technical studies on tidal power plants on the stages of the construction project.
western Korean coast, several numerical tidal models have been First, the silt protection, cellular cofferdam and diversion
developed for the entire Yellow Sea and East China Sea roads were constructed. Then dewatering and excavation were

Fig. 5. Photograph showing the construction progress of Sihwa tidal power plant.
ARTICLE IN PRESS
458 Y.H. Bae et al. / Ocean Engineering 37 (2010) 454–463

performed for dry work, and the main concrete structures for and topographical features. Rather than refining a dynamic grid
power plants and sluices were constructed. Then the turbo- nesting technique that retains the finite difference scheme, we
generators and sluice gates were installed after unloading from a decided to adopt a finite element technique that provides more
temporary wharf to the erection bay. These machines were then flexibility and allows a regular coastline and bathymetry to be
transported by a special carrier to a gantry crane and a hydraulic fitted with elements of an arbitrary size, shape and orientation
crane. This construction schedule was necessary considering the (in particular, barrier positioning). Fig. 6 shows the mesh used for
non- the Yellow Sea and the East China Sea continental shelf (YS)
uniform settlement of the railway foundation and to ensure that model.
the gantry crane would be installed by July 2009. After a new road Earlier works (Choi, 1981) have shown that the proposed tidal
is constructed over the sluice gates, the diversion roads will be barrage schemes can impose a significant effect on the local tides
detached. Then the cellular cofferdam will be removed, and the of Kyeonggi Bay, but these changes are limited to the Kyeonggi
turbo-generators will be tested for normal TPP operation. Bay and do not extend seawards. Notably, the barrage at Asan Bay
The construction of the circular cell cofferdam has been may disturb the quarter-wavelength resonating system, thus
completed. Immediately after dewatering and excavation in reducing the tidal amplitudes. A previous study (Choi, 1981) has
October 2007, concrete structures have also been constructed to
house the turbines and gates inside the cofferdam. Fig. 5 shows the
photographs of the construction through December 2008. It is
expected that the Sihwa project will be completed in 2010. The
cofferdam will be maintained during the next two years or so, and 38°00’N
the real-time tide prediction for the localized TPP construction site
will be able to predict the electricity that can be generated and the
tidal level at the outside and inside of the dike wall.

3. Hydro-regime update and forecast SIHWA BARRAGE


37°30’N
3.1. Numerical model

Investigations on the tides in the East Asian Seas started during


the late 1970s with the formulation of a two-dimensional model
for basic studies of tidal propagation in the Yellow Sea and the
East China Sea continental shelf (Choi, 1981). These works were
followed by a series of studies aimed at predicting tidal changes 37°00’N
due to tidal barriers for potential tidal power exploitation, land
reclamation and port development, using a combination of the
Yellow Sea model and estuarine tidal models. This study employs
a modeling technique that converts the model equations into
discrete form and performs the calculations over spatially
unstructured meshes. This has been established as a main 126° 00’E 126° 30’E 127° 00’E
component of the regional ocean tide simulator, providing a
more accurate representation of the coastlines, coastal structures Fig. 7. Amplitude of disturbance waves due to the barrages.

Fig. 6. Mesh of the Yellow Sea and the East China Sea continental shelf (YS) model.
ARTICLE IN PRESS
Y.H. Bae et al. / Ocean Engineering 37 (2010) 454–463 459

shown that if the barrage is in a dead or impermeable mode, there negligible. Fig. 7 shows that a disturbance wave produced at the
will be only slight changes to the tides compared with the barrage would travel seawards and lose amplitude at the open
barrage’s operational (permeable) mode. circular boundary of the Kyeonggi Bay entrance.
Since the Sihwa barrages are located on the fringe of the path A localized compact model was then developed to investigate
of major tidal propagation into the Bay, their effect on the tide is the behavior of water levels and currents given the power
generation scheme and its mode of daily operation; the model
incorporates the open boundary at the Kyeonggi Bay entrance.
INCHEON With this simulator design, detailed meshes of the coastal and
estuarine regions can be resolved, and the computations can be
Predicted
4 Calculated managed with parallel structures. Using a time-stepping approach
(Luettich et al., 1992), the method can accommodate the transient
2 response of non-periodic forces (e.g., wind) in addition to tides,
M.S.L (m)

unlike the harmonic approach. The external mode equations were


0 initiated using parametric relationships for the bottom friction and
momentum dispersion. The key features of the external mode
-2 solution include a generalized wave-continuity equation (Lynch
and Gray, 1979; Kinnmark, 1985) and finite element discretization.
-4 The model used 21 tidal prediction components (M2, S2, K1, O1,
N2, K2, P1, Q1, M1, J1, OO1, 2N2, MU2, NU2, L2, T2, Mf, Msf, Mm, Ssa
5 Feb 10 Feb 15 Feb 20 Feb 25 Feb and Sa) at the open boundary to simulate the tides in detail and in
2009 real time, while using a modified internal boundary at the turbine
and gates. This modified internal boundary allowed the water to
Fig. 8. Comparison of measured and simulated water levels at the Incheon Port. flow from one side of the internal boundary to the other, where

Sea water level


Basin water level a b c

Sea water level

T urbine: close
Gate: close
M.S.L.

Minimum Net T urbine: open


Head: 2m Gate: open MSL(-)1.00m
T urbine: open
Gate: close

Optimum
Basin water level
Net Head

T urbine: close
Gate: close

Stand Stand
by by
Generate Drain

Fig. 9. Three types of tidal power generation: (a) single effect operation (ebb), (b) single effect operation (flood) and (c) double effect operation. Also, a detailed diagram of
a single effect operation (flood) for the Sihwa TPP.
ARTICLE IN PRESS
460 Y.H. Bae et al. / Ocean Engineering 37 (2010) 454–463

the flow depends on a characteristic formula that accounts for variables, the data table becomes too large, particularly when high
variations in the current. Fig. 8 gives a comparison of the accuracy is required. Furthermore, the computational time increases
measured and simulated water levels at the Inchon Port. for parameters with multiple variables. For parameters with
multiple variables, the values can be pre-approximated with a
3.2. Methodology of tidal power generation polynomial raised to the power m in the form

The Sihwa tidal power plant is designed as a flood generating Electric generation during flood
system, taking advantage of the difference in the tide levels between Q ¼0 ð0 o DH o 1:07Þ
the sea and the artificial lake. Flood generating systems create power Q ¼ 150:433  DH þ 113:248179 ð1:07 r DH o1:95Þ
from the incoming tide, i.e., the water flowing from the sea to a Q ¼ 18:1077  DH þ 371:3606 ð1:95 r DH o 5:69Þ
basin. When the high tide enters, water flows through the turbines
Q ¼ 1767:8881346:5186  DH ð5:69 r DH o 7:43Þ
to create electricity. Separate gates beside the turbines are designed
þ 20:9571  DH2
to open during the ebb phase. When the low tide enters, the gates
are raised, and the water flows out. The turbines operate in a sluicing
Power generated (Megawatts):
mode during the ebb phase, and no energy is produced.
P ¼ 1:7256þ 0:3161  H þ 1:2465 ðDH o 5:64Þ
The characteristics and methods of TPP computer simulations are
H2 0:0907  H3
shown in Fig. 9. An analysis of the optimum energy modes of a TPP
P ¼ 22:29 ðDH Z 5:64Þ
should include the actual conditions under which the TPP operates,
such as parameters defining its hydraulic and power equipment,
Discharge (through sluice gate):
hydraulic engineering structures, basin and power system. Such
considerations necessitate a large number of data to be inputted into Q ¼ 800  DH ð0 o DH o 0:05Þ
the computer. Some of these parameters can be obtained by Q ¼ 600  DH þ10 ð0:05 r DH o 0:1Þ
experimental measurements, which by nature contain some errors. Q ¼ 250  DH þ 45 ð0:1r DH o0:3Þ
The values of the function for arguments other than those Q ¼ 59:56939963þ 231:1052218  DH ð0:3r DH o2:5Þ
specified in the table are computed by linear interpolation. Usually it 94:5018523  DH2 þ 26:29460961
is advisable to use this method for parameters that are the function DH3 2:754795024  DH4
of one variable because when a function in the model contains two Q ¼ 839  DH0:3855 ðDH Z 2:5Þ.

Fig. 10. FEM mesh (a) at the cellular cofferdam for Sihwa tidal power generation on December 2005, (b) on January 2007 and (c) at completed construction.
ARTICLE IN PRESS
Y.H. Bae et al. / Ocean Engineering 37 (2010) 454–463 461

where Q is the discharge in m3/s, H the head in meter, DH the 3.3. Prediction of tidal environments of the Lake Sihwa tidal power
head difference between outside sea and the basin and P the plant
generated power by turbine during flood in Megawatts.
The approximation of the parameter and the polynomial In this study, two compact finite element mesh systems are
degree required are both determined with a computer program. established. Fig. 10 shows the finite element mesh of the Sihwa
This program has a criterion for a minimum rms deviation for TPP site while the project was under construction, where the tidal
approximating polynomial based on the values of the original prediction will still be implemented after the project has been
parameter (KOWACO, 2004) at the points of approximation. The completed; the mesh resolution around the turbine and
discharge characteristic of a TPP generating unit is specified for discharging gate is approximately 15 m.
four modes of operation: FT (forward turbine), BT (backward After completion of the Sihwa TPP, 10 turbines and 8 gates will
turbine), FP (forward pumping), and BP (backward pumping). The operate in conjunction with the established gate near Daebu Island
reversible double-effect generating unit design allows operation in order to discharge the water inside the basin, and the turbines
in the FT mode to be easily changed to operation in the BP mode will only generate power during a flood tide. Inside the basin, the
(and from BT to FP) without altering the direction of rotation. water surface elevation will be kept under EL.( )1.0 m. It is well
Therefore, only two polynomials, one for the modes FT and BP and known that the flood tidal generation method has a considerably
another for the modes BT and FP, are required to approximate the low efficiency and that the EL.( )1.0 m limitation causes the
discharge characteristic. intertidal ecosystem to change to the land ecosystem. However,
In order to make multiple variable TPP computations feasible, this type of power generation can create useful building ground.
the mathematical model is used to provide computer-aided Fig. 11 shows a snapshot of the tidal flow of the cellular
recalculations from the equations. These recalculations are based cofferdam construction site with a real-time tide velocity of
on the law of proportionality, and they provide the discharge approximately 0.3 m/s. Fig. 12 shows the real-time tidal flow after
characteristics of the TPP generating unit specified in the source completion for discharging (left) and generation (right). This
data in terms of the diameter and rotational speed. simulator is designed to provide the field engineer with a compact

Fig. 11. Snapshot of the tidal flow of the cellular cofferdam construction site.

Fig. 12. Snapshot of the flow velocity at the Sihwa tidal power generation plant during discharging (left) and generation (right)
ARTICLE IN PRESS
462 Y.H. Bae et al. / Ocean Engineering 37 (2010) 454–463

Fig. 13. Computed energy (up) and water level (down) at sea side (dashed line) and basin side (dotted).

prediction system that gives the tide forecast and generation and the data become the initial conditions for the hot-start model
capabilities after the project’s completion. In particular, the simulation.
operator can easily use a GUI-based MATLAB or SMS to present Fig. 13 shows the water surface level inside and outside the
the numerical model results on a PC. The simulator demands a basin, where the computed electricity depends on the net head.
model leading time for a cold-start; thus, the simulator saves the The actual height and time of high water at the TPP site can vary
water elevation and velocity data once a day in the last timestep, significantly due to meteorological effects. The effect of these
ARTICLE IN PRESS
Y.H. Bae et al. / Ocean Engineering 37 (2010) 454–463 463

parameters on the energy output from the TPP is short term and Acknowledgements
thus often unimportant, although prediction of such surges a few
hours in advance is important for the operation of a TPP. This paper was supported by Samsung Research Fund,
Sungkyunkwan University, 2009.

4. Conclusion

One of the biggest advantages of the Lake Sihwa TPP is that the
References
barrage construction was already completed by a previous
unsuccessful Sihwa freshwater reservoir project. The major
Baker, A.C., 1991. Tidal Power. Institution of Electrical Engineers, Peter Peregrinus
constraint on this project is the tidal energy scheme, which is a Ltd., London 250 pp.
single basin flood generation scheme where the land reclamation Bernstein, L.B., 1965. Tidal Energy for Electric Power Plants. Israel Program for
is limited by the lake’s water level. Scientific Translations, Jerusalem 344 pp.
Bernstein, L.B., Wilson, E.M., Song, W.O., 1997. Tidal Power Plants. Korea Ocean
The reliability of the generator can only be guaranteed by an
Research and Development Institute, Ansan, Korea.
experienced operator who follows operation and maintenance Choi, B.H., 1980. Analysis of tide at Incheon. Korean Ocean Research Development
procedures. It is necessary that the operator is familiar with the Institute. Report 80-01.
content of this model in order to compare the calculations with the Choi, B.H., 1981. Effect on the M2 Tide of tidal barriers in the west coast of Korea.
Korean Ocean Research Development Institute. Report 81-01.
real situation. As mentioned above, the advantage of the compact Chosun Governer’s Office, 1930. Tidal Power. Bureau of Communication. (in
Sihwa tidal simulator is its ease of use for application in the field. Japanese).
The operators are only required to check the model start and end Gibrat, R., 1966. L’energie des Marees. Presses Universitaires de France, Paris.
Kinnmark, I.P.E., 1985. The Shallow Water Wave Equations: Formulation, Analysis
time and the value of the optimum net head and minimum net and Application. Lecture Notes in Engineering, vol. 15. Springer-Verlag,
head from the hill chart, and they then input these data into the TPP New York 187 pp.
control file. The only other check points are the characteristic curves Korea Electric Company, 1978. Korea Tidal Power Study—Phase I. KORDI, KIST.
Shawinigan Engineering Co. 180 pp.
of the turbine and sluice gate. In future studies, the sea surface Korea Electric Power Corporation (KEPCO), 1993. Feasibility Study on Garolim
elevation induced by the wind and waves will be considered in the Tidal Power Development. Korea Ocean Research and Development Institute,
next versions of the simulator. In Korea, the Sihwa TPP is currently Ansan, Korea.
KOWACO, 2004. Basic Design Report for Sihwa Lake Tidal Power Construction.
leading alternative energy efforts, and several coastal cities plan to 750 pp.
construct additional TPPs; for example, TPPs are planned for Luettich, R.A., Westerink, J.J., Scheffner, N.W., 1992. ADCIRC: an advanced three-
Garolim and Incheon Bays. It is important to predict the real sea dimensional circulation model for shelves, coasts, and estuaries, report 1:
theory and methodology of ADCIRC-2DDI and ADCIRC-3DL. Dredging Research
surface elevation change in order to ensure that the correct capacity
Program Technical Report DRP-92-6, US Army Engineers, Waterways Experi-
is chosen in the feasibility study for this type of TPP simulator. The ments Stations, Vicksburg, MS. 137 pp.
model proposed in this paper still require further development but Lynch, D.R., Gray, W.G., 1979. A wave equation model for finite element tidal
it helps put the Lake Sihwa TPP on the forefront of power plant computations. Comput. Fluids 7, 207–228.
Prandle, D., 1984. Simple theory for designing tidal power schemes. Adv. Water
technology along with adopted design and construction technology Resour. 7, 21–27.
allowing for further use of TPPs. Struben, A.M.A., 1921. Tidal Power. Sir Isaac Pitman & Sons, Ltd., London.

You might also like