C1 to C2 (CH 177 to 222)

Personnel:

1) 1 x Excavator Operator
2) 1 x Banksman
3) 1 x Lifting Supervisor
4) 1 x Rigger Signal Man
5) 1 x Supervisor
6) 3 x General Worker
7) Temp welder (for cutting of Strut)

Facilities

1) ECM tank/ pond


2) Temporary Material Storage
3) Cube House (Cube tank/mould)
4) Rest Area
5) Toilet

Equipment

1) Generator
2) Excavator
3) Concrete bucket/ pump
4) Lifting rack (with Lifting Chain & Belt)
5) Temp gas cutter (for cutting of strut)