Professional Documents
Culture Documents
Load Oriented
Manufacturing Control
(LOMC)
Teknik Industri – Fakultas Rekayasa Industri
Referensi: Wiendahl, H. P. (1995): Load-Oriented Manufacturing Control, Springer-Verlag Berlin Heidelberg, New York
2
2
3
• Planning, measuring, and monitoring lead time is one of the essential tasks of
production scheduling and control.
• It has not yet been possible to find an equally accepted classification of
manufacturing lead time, despite numerous attempts.
• It becomes absolutely necessary first of all to give a clear and uniform definition
of manufacturing lead time and its components, in order, first, to standardize
the methods of data recording and enable the data evaluation to be programmed,
and, second, to permit a comparison between different factories and job shops.
3
4
4
5
5
6
• Using the term 'lead time', we have to distinguish between planned and actual
values.
• Planned lead time as allowance and actual lead time as flow time.
• The time from the issue of materials to parts' or components' arrival at an
intermediate store or at the assembly department is commonly called the order
lead time (it should rather be called order lead time period or time interval or time
span)
• The time needed for one operation is the smallest unit, it is called the operation
lead time.
6
7
By Heinemeyer, each
operation is split into five
more components on the
operational level:
• Waiting after processing
• Transportation
• Waiting before processing
(Queuing)
• Setup and
• Processing
7
8
8
9
10
11
11
12
12
13
13
14
14
15
15
16
17
18
Throughput Diagram
• The throughput diagram is the basis for describing the input and output events
of a work center.
• It is shown that the four objectives of production control - inventory, lead time,
utilization and lateness - can be graphically represented over time in this
diagram.
• The basic relationship between mean lead time, mean inventory and mean
utilization is derived from this diagram.
• The flow of orders through a whole shop is also represented by means of the
throughput diagram.
18
19
19
20
20
21
21
22
22
23
23
24
24
25
25
26
Procedure (1/6)
• On the figure we can see sections of the input and output curves from the recent
past, and the future ideal throughput diagram for the next period.
• Further, a medium-term scheduled performance (PEm ) was assumed, to which a
scheduled output (OUT) corresponds.
• Finally, an assumed scheduled mean lead time (TLM) must be achieved.
• Since, in the ideal throughput diagram, the input and output curves are parallel,
the scheduled mean inventory (Im) is constant over the entire schedule period
(P).
26
27
Procedure (2/6)
• The real initial inventory, however (called the 'leftover inventory (lLO), in the figure),
deviates from the planned mean inventory: in the figure it is shown to be larger
than the latter.
• Thus, the work to be released is not the planned input INP but rather Load Limit
LL minus Leftover Inventory ILO.
• The sum of the planned mean inventory and the planned output is called the
load limit (LL); the difference between the load limit and the leftover inventory
is called the release (REL).
• The method developed from this is called load-oriented order release.
• Unlike conventional capacity scheduling methods, this method does not try to
schedule single orders along the scheduled output curve with an accuracy to the
day or the hour, but performs a period-by-period balance on the basis of the
27
expected inputs and outputs.
28
Procedure (3/6)
• One important characteristic of this method is obvious: only one account is kept
for each work center, and this is updated in every period.
• Thus, the conventional method of keeping several accounts for several future
periods is no longer necessary.
• The account corresponds exactly to the funnel, and observing the processes on
this account allows us to draw a precise throughput diagram for this work center.
28
29
Procedure (4/6)
29
30
Procedure (5/6)
30
31
Procedure (6/6)
• The first step in the release process is the
backward scheduling of all issued shop
orders which have not yet been released.
• Finite loading, which is the next step, will
ensure that only those orders beyond the
present schedule period that use no more
than the remaining capacities up to the
load limit will be released.
• The next step in load-oriented order
release is to evaluate whether the urgent
orders will actually meet the scheduled
inventory conditions at the individual work
centers after their release.
31
32
32
33
33
34
36