Actividad 

Predecesora  To Tm Tp TE
A ---- 0 1 2 1
B A 3 6 9 6
C B 6 9 18 10
D B 4 4 4 4
E B 2 3 4 3
F C, D, E 6 9 12 9
G C  2 3 10 4
H E 3 4 11 5
I G 0 3 6 3
J H 6 6 6 6
K F, I, J 3 4 11 5
L K 3 4 5 4
M K 6 10 20 11
N L 8 12 22 13
O M, N 6 10 20 11
P O 15 25 47 27

VARIANZA DEL PROYECTO 46.44

DESVIACION DEL PROYECTO 6.82

TIEMPO RUTA CRITICA 86

RUTA CRITICA A,B,C,F,K,L,N,O,P

incio
0
varianza RUTA CRITICA

0.11 SI
1.00 SI
4.00 SI
0.00
0.11 SI
1.00
1.78
1.78
1.00
0.00
1.78 SI
0.11 SI
5.44
5.44 SI
5.44 SI
28.44 SI

ES EF ES
A B
0 1 1
LS LF LS
1 6
0 1 1
H= H= H=
0 0 0
ES EF ES
C
7 17 17
LS LF LS
10
7 17 19
H= H= H=
0 0 2

EF ES EF ES
D
7 7 11 17
LF LS LF LS
4
7 13 17 17
H= H= H= H=
0 6 6 0
ES EF ES
E
7 10 10
LS LF LS
3
14 17 15
H= H= H=
7 7 5
EF ES EF
G I
21 21 24
LF LS LF
4 3
23 23 26
H= H= H=
2 2 2

EF
F
26
LF
9
26
H=
0
EF ES EF
H J
15 15 21
LF LS LF
5 6
20 20 26
H= H= H=
5 5 5
ES EF
L
31 35
LS LF
4
31 35
ES EF H= H=
K
26 31 0 0
LS LF
5
26 31
H= H=
0 0 ES EF
M
31 42
LS LF
11
11
37 48
H= H=
6 6
ES EF
N
35 48
LS LF
13
35 48
H= H= ES EF
O
0 0 48 59
LS LF
11
48 59
H= H=
0 0
ES EF
P
59 86 FIN
LS LF 86
27
59 86
H= H=
0 0