Professional Documents
Culture Documents
GE Impact of Frequency Responsive Wind Plant Controls Pres and Paper
GE Impact of Frequency Responsive Wind Plant Controls Pres and Paper
Nicholas Miller
Kara Clark
Miaolei Shao
2
Nicholas W. Miller - GE Energy Consulting December 15, 2010
Frequency Response: Today’s Reality
• System governor response (primary response) has been declining
steadily in some parts of the US for many years: Subject of Sept 23,
2010 FERC Technical Conference and NERC Comments of October
14, 2010 [The work presented here was executed and documented
before the TC]
• This predates the rapid recent growth of wind generation in North
America
• Declining response results in deeper frequency (nadir) excursions for
system disturbances, increasing the risk of under-frequency load
shedding (UFLS) and cascading outages
• Concern is most acute at lighter load conditions
• economics favor fewer generators committed with less
governor response
• worst disturbances are not dependent on system load level
• The issue is getting considerable attention in many circles
3
Nicholas W. Miller - GE Energy Consulting December 15, 2010
4
Nicholas W. Miller - GE Energy Consulting December 15, 2010
Inertia vs. Governor 120,000
Response
Total Generation
Power (MW)
initial frequency decline 110,000
Frequency at
• At 40 seconds: 59.9
Frequency (Hz)
~3800 MW Governor Response 59.8
6
Nicholas W. Miller - GE Energy Consulting December 15, 2010
Adding Wind to WECC
• New wind added to reach 10 and 20% by Energy
• MW build-out by area based on Western Wind & Solar Integration
Study* (WWSIS)
• Physical location: at existing thermal plants
• Commitment & Dispatch: guided by WWSIS economic analysis.
• Gas CC usually on margin: mostly CC displaced by wind power
• on average +3 MW Wind power causes:
• 1 MW of other generation to be dispatched down
• 2 MW of other generation to be decommitted
10% Wind 20% Wind
Generation Rating Generation Rating
Area (MW) (MW) (MW) (MW)
Arizona 2,254 2,906 4,419 5,247
Colorado 802 2,186 1,745 4,284
Nevada 120 1,504 210 2,428
New Mexico 811 1,271 1,712 2,087
Wyoming 467 1,638 1,018 4,348
Rest of WECC 10,927 21,854 21,711 43,422
Total = 15,381 31,359 30,815 61,816
*http://www.nrel.gov/wind/systemsintegration/wwsis.html
7
Nicholas W. Miller - GE Energy Consulting December 15, 2010
15000
Reserve MW
10000
- 1MW Reserve
per +4MW Load
5000
0
~2,000 more reserve with
30% wind and solar
-5000
0 10000 20000 30000 40000 50000 60000
Load or Wind MW
Slide from WWSIS Study
8
Nicholas W. Miller - GE Energy Consulting December 15, 2010
Frequency Response to Loss of
Generation with Increasing Levels of Wind
• Wind 60.1
without any
60 frequency decline 10% Wind
Frequency (Hz)
59.8
59.7
• Nominal
response at 40 59.6
seconds: Minimum
~1.0%/0.1Hz 59.5
frequency lower
Meets NERC
Criteria
59.4
0 5 10 15 20 25 30 35 40
Time (seconds)
9
Nicholas W. Miller - GE Energy Consulting December 15, 2010
Control Concept:
• Use controls to extract stored inertial energy
• Provide incremental energy contribution during the
1st 10 seconds of grid events
• Allow time for governors and other controls to act
10
Nicholas W. Miller - GE Energy Consulting December 15, 2010
How does it work?
Mechanical Electrical P stator P conv
Torque, Tm Torque, Te F stator F network
Electrical power
delivered to grid
is completely
controlled by
power electronics
12
Nicholas W. Miller - GE Energy Consulting December 15, 2010
60.1
Wind Generation
20% Wind
Governor response
Frequency (Hz)
59.8 better (more headroom)
Inertial response reduces
and delays minimum
59.7
frequency 59.6
40mHz
Time (seconds)
20% Wind
20% Wind with WindINERTIA
Response in this case is 32,000
Power (MW)
control variable that 30,000
can be tuned.
29,000
Inertial energy
recovery
28,000
0 5 10 15 20 25 30 35 40
Time (seconds) 13
Nicholas W. Miller - GE Energy Consulting December 15, 2010
60.1
Tuning Inertial 60
20% Wind with WindINERTIA
59.9
Frequency (Hz)
59.8
increases by about
32,000
with wind)
29,000 Inertial energy recovery
moderated
28,000
0 5 10 15 20 25 30 35 40
14
Time (seconds)
Nicholas W. Miller - GE Energy Consulting December 15, 2010
60.1
Impact of Operating 60
No Wind
20% Wind
Response
Frequency (Hz)
59.8
59.7
20% Wind
When wind speed is high, 20% Wind with Tuned WindINERTIA
system response is
32,000
20% Wind with WindINERTIA, Different Operating Point
Power (MW)
Margin to UFLS improved
by ~80mHz
30,000
29,000
No energy recovery when wind
speed greater than rated
28,000
0 5 10 15 20 25 30 35 40
Time (seconds) 15
Nicholas W. Miller - GE Energy Consulting December 15, 2010
60.1
Governor Response 60
20% Wind
59.8
WindINERTIA to greatly
benefit system
30,000
Point Point B
1
A (Fb,Pbc) Point C All parameters can be
(F P ) (Fc,Pbc)
set/customized. Is easy
to selectively
0.8
enable/disable all
Active Power Output (pu)
60.1
Summary of
No Wind
20% Wind
Frequency
20% Wind with WindINERTIA, Different Operating Point
20% Wind, Curtailed
59.9
20% Wind, Curtailed with WindINERTIA
Performance
Frequency (Hz)
59.8
59.7
1%/0.1Hz 0 5 10 15 20
Time (seconds)
25 30 35 40
requirement 33,000
20% Wind
20% Wind with Tuned WindINERTIA
20% Wind with WindINERTIA, Different Operating Point
32,000 20% Wind, Curtailed
28,000
0 5 10 15 20 25 30 35 40
Time (seconds) 18
Nicholas W. Miller - GE Energy Consulting December 15, 2010
Conclusions
• Systems with high wind penetration can exhibit superior frequency
performance
• Presently available wind plants controls can contribute positively to
system frequency performance and can be tuned
• It is possible for systems with wind generation to experience degraded
frequency performance
• Statements that wind generation necessarily results in degraded
frequency performance are incorrect
• System frequency performance is, as always, dependent on
• power plant performance
• overall unit dispatch and commitment
• The addition of wind generation does not change the fundamental truth
that system operation must respect frequency response requirements
19
Nicholas W. Miller - GE Energy Consulting December 15, 2010
GE
Energy
Thank you!
Based on Paper Presented:
Québec City
October 2010
(with some additions and improvements)
nicholas.miller@ge.com
1
wind generation does not exhibit this inertial response. It is production of the wind plant is constrained to a value less
possible to program the wind plant controls to provide a than that available from the wind. During the period where
form of inertial response. The GE WindINERTIA™ this function is enabled, there is a loss of energy production
control feature is described below. due to an intentional under-utilization of the wind plant.
For large under-frequency events, the GE Grid over-frequency events are stressful to power
WindINERTIA™ inertial control feature temporarily components. Further, temporary high frequency swings can
increases the power output of the wind turbine in the range present a reliability concern. For example, in one recent
of 5% to 10% of the rated turbine power. The duration of well-publicized grid event [6], the high frequency
the power increase is on the order of several seconds. This backswing from a major grid disturbance caused power
plant trips and aggravated an already severe event. When
inertial response is essentially energy neutral, meaning that
enabled, the response of the wind plant control system will
the period of increased power is followed by a period of
rapidly reduce power output for the duration of the over-
decreased power. Below rated wind, stored kinetic energy
frequency event. This behavior is similar to that of
from the turbine-generator rotor is temporarily donated to governor control on thermal generation, except that it is
the grid, but is recovered later. At higher wind speeds, it is faster and allows deeper runback of power than is typical of
possible to increase the captured wind power, using pitch conventional thermal generation.
control, to temporarily exceed the steady-state rating of the The wind plant inertial control discussed in the previous
turbine. Under these conditions, the decline in rotor speed section, if enabled, will also respond to significant under-
is less and the energy recovery is minimal. frequency events. The total response of the WTG to these
Unlike the inherent response of synchronous machines, two signals is coordinated to respect the physical
inertial wind turbine generator (WTG) response is capabilities of the WTG.
dependent on active controls. The design has sufficient
margin over the turbine operating range to meet the IV. OPERATIONS WITH HIGH WIND PENETRATION
equivalent energy (kW-sec) contribution of a synchronous
In response to the rapid growth of wind and solar
machine with 3.5 sec pu inertia for the initial 10 seconds.
generation in North America, a number of jurisdictions
Overall, the inertial control feature is designed to provide
commissioned studies to determine potential operational
similar functional response to that of a synchronous impacts [7-11]. Overall, the studies have repeatedly found
machine. However, there are important differences. Unlike that large modern power grids can accommodate substantial
the inherent response of a synchronous machine, the amounts of wind and solar generation reliably and
response is not exactly the same under all operating economically, with appropriate changes in practice, rules
conditions. The control is also asymmetric. It only and infrastructure
responds to low frequencies. A different controller, as These studies showed that the addition of wind and solar
discussed below, handles high frequency response generation displaces thermal generation in an economically
separately. And, the control only responds to large events – dispatched system. Whether that thermal generation is gas-
those for which inertial response is important to maintain fired or coal-fired depends upon the relative cost of those
grid stability, and for which seriously disruptive two fuels. Regardless of the fuel, the displacement of
consequences, like under-frequency load shedding (UFLS), thermal generation has two components. Some of it is de-
may result. The continuous small perturbations in committed, and some of it is dispatched at a lower level.
frequency that characterize normal grid operation are not Many factors and constraints, both economic and
passed through to the controller. The inertial control feature physical, affect unit commitment and dispatch decisions. In
uses the energy stored in the rotor to provide an increase in a system with high wind and solar penetration, the
power only when needed. Hence, this feature does not operational flexibility of the remaining generation portfolio
is key to accommodating the variable renewable generation.
adversely impact annual energy production.
Operational flexibility includes such attributes as quick start
B. Governor Frequency Response capability, fast ramp rates, and minimum unit turndown.
It is also possible to implement active power management Specific quantitative results from one such study, the
functions in wind plants to provide a response similar to a Western Wind and Solar Integration Study (WWSIS) [11],
governor response. One type of active power control formed the basis for the analysis described in the next
offered as part of the GE WindCONTROL™ wind plant section. First, a WWSIS study scenario was used to define
control system is closely akin to governor controls for the overall study conditions – i.e., load level, generation
thermal and hydro generation. It responds to significant commitment and dispatch. Specifically, the In-Area
deviations in grid frequency, increasing or decreasing power scenario, which uses local wind resources to serve local
output in response to low or high grid frequency events, load, at 10% wind penetration was selected. Second, the
respectively. To accomplish this, the control alters the WWSIS showed that for every 3 MW of additional wind
active power control reference targeted by the turbine production, there is on average a 2 MW reduction in thermal
controls. The command for this response emanates from the unit commitment and a 1 MW reduction in thermal unit
wind plant level, and is delivered to each individual WTG dispatch. This 2/3 de-commitment, 1/3 re-dispatch
through the plant SCADA system. In order to allow for an approach is a basic assumption incorporated into the
increase of wind plant active power output in response to an analysis. Considerable variation in dispatch and
under-frequency condition, some active power production commitment will occur, as it does today in low renewable
must be kept in reserve [5]. Therefore, the maximum power systems. However, this average commitment and dispatch
3
approach is one that is supported by the extensive Table 1. WWSIS Objectives for 10% Wind Case.
operational analysis performed in the WWSIS.
Area Wind Generation Wind Rating
V. WESTERN US EXAMPLE SYSTEM (MW) (% of Rating) (MW)
Arizona 2,211 78 2,850
As part of its support for the Western Electricity Colorado 880 37 2,400
Coordinating Council’s (WECC) Renewable Energy Nevada 108 8 1,350
Modeling Task Force (REMTF), GE Energy investigated New Mexico 862 64 1,350
the impact of significant wind penetration on frequency
Wyoming 471 29 1,650
response of the WECC system.
Rest of WECC 10,838 50 21,676
A. Base Case
C. Wind Cases
A standard WECC power flow and dynamic dataset for
From a power flow perspective, there is no difference
2010 light summer conditions was used. This database
between a wind generator and a thermal generator. Both are
represented relatively light load conditions (65-75% of
modeled as a conventional source with a specified real
summer peak) in the early morning hours (2 am to 5 am).
power output, a reactive power range, and a bus voltage to
Therefore, it represented a credible system condition for
regulate. For simplicity, it was assumed that wind
high levels of wind penetration.
generation was located at the same bus where displaced
To streamline this analysis and provide a clearer
conventional generation was located. Therefore, the same
comparison between various cases, all relay models were
WECC 2010 light summer power flow provided the initial
removed from the dynamic data. It may be desirable for
conditions for all of the dynamic simulations. The addition
future analysis to consider load shedding as an additional
of wind, and the associated de-commitment and re-dispatch
performance metric.
of thermal generation, was implemented by modifying the
Since the focus of the simulations is short-term dynamic
dynamic data alone. The load and interface flows remained
performance, no long-term models (e.g., AGC or Automatic
unchanged. This approach ensures that the performance
Generation Control) were included.
differences are associated with a change in generation
Many of the load models included a frequency dependent
technology and not due to a change in generation location.
component.
Based on the WWSIS results, the addition of every
In WECC, many generators are base-loaded, and the
3 MW of wind generation was accomplished with a 2 MW
effect of this operating condition is captured in the
de-commitment and a 1 MW reduction in other generation.
corresponding governor models by appropriate parameter
As an example, assume that 500 MW of wind production
settings (i.e., base load flag).
with a rating of 750 MW needs to be accommodated and
B. Wind Scenarios there are two thermal generators that could be displaced.
The standard WECC database described above became One thermal unit is a 600 MVA plant with 500 MW output
the reference case. Some wind generation is, of course, and the other is a 1,200 MVA plant with 1,000 MW output.
included. For this analysis, however, the reference case is The total output of the thermal units is 1,500 MW and the
also called the no-wind case – short hand for a case with no total rating is 1,800 MVA. For 500 MW of additional wind
additional wind. Selected areas and zones in the WECC production, the 2/3 de-commitment objective is 333 MVA,
database were aggregated to approximate the study areas and the 1/3 re-dispatch objective is 167 MW.
used in the WWSIS. These study areas, in turn, First, the dynamic model of the 600 MVA thermal plant
approximated the states of Arizona, Colorado, Nevada, New is replaced by a 750 MW rated wind plant model with
Mexico, and Wyoming. 500 MW of output. This constitutes a thermal de-
As noted above, the WWSIS In-Area scenario at 10% commitment of 600 MVA. Second, the MVA in the
wind penetration was selected as a starting point. dynamic model of the second thermal unit (1,000 MW,
Production simulation results for an entire study year were 1,200 MVA) is increased to 1,467 MVA. This represents a
screened to identify a time period with the best match to the transfer of 267 MVA of thermal commitment to this unit.
power flow in terms of load level, season, time of day, and As a result, the net thermal commitment is reduced by
generation dispatch in the Arizona, Colorado, Nevada, New 333 MVA: -600 MVA at the first plant and +267 MVA at
Mexico, and Wyoming study areas. A midnight in July was the second plant. In other words, the original total thermal
identified. The aggregate wind production and wind MVA has been reduced by 333 MVA, from 1,800 MVA to
nameplate rating in each study area during that time period 1,467 MVA.
defined the objective in the development of the 10% wind Consider the above changes from the perspective of the
case, as shown in Table 1. Wind output as a % of rating is thermal plant dispatch, rather than commitment. The total
also shown. This relative output varies widely across the thermal plant output was originally 1,500 MW. The de-
areas, from 8% in Nevada to 78% in Arizona. commitment of 333 MVA results in an equivalent reduction
The objective in the development of the 20% wind case in actual output, or an interim thermal output of 1,167 MW.
was to simply double the wind production and rating of the Then, the 167 MW re-dispatch is implemented, giving a
10% case. final total thermal output of 1,000 MW on the second unit.
The final dynamic model includes the 750 MW rated
wind plant model with 500 MW of output, and a single
thermal plant with an output of 1,000 MW and a rating of
1,467 MVA. Thus, there is no need to modify the power
4
flow. In general, the thermal plants have the correct The frequency response of the system is shown in Figure
loading, the correct MVA and inertia, and the correct range 2. Several buses across WECC are plotted. The frequency
between dispatch and maximum power (i.e., “headroom”) behavior, which is typical of large events, has two major
available for governor action. components: a common frequency as well as more
The final 10% wind case is summarized in Table 2. The oscillatory components that are evidence of inter-area or
20% wind case was developed using the same de- other power swings. In this figure, the black trace is for the
commitment/re-dispatch approach for exactly twice the Malin 500 kV substation. While this frequency trace still
wind in the 10% case. includes some of the oscillatory behavior, the common
mode, which reaches a relative minimum of about 59.52 Hz
Table 2. Actual Wind in 10% Wind Case.
at about 10 seconds, is dominant. The 9-second interval
Area Wind Generation Wind Rating from the beginning of the event to minimum frequency is
(MW) (% of Rating) (MW) representative of many large power systems.
Arizona 2,254 78 2,906 While swing modes are important for system stability, it
Colorado 802 37 2,186 is this common mode that is of most concern in discussions
Nevada 120 8 1,504 about system frequency response. In the subsequent results,
New Mexico 811 64 1,271 the frequency at Malin will be shown for comparison
Wyoming 467 29 1,638 purposes.
Rest of WECC 10,927 50 21,854 Minimum frequency is used as the key performance
metric in this analysis, since it can be correlated to tripping
D. Disturbance thresholds in UFLS schemes.
Tripping all three generating units at the Palo Verde 120,000
excursion on the WECC system. While this multi-unit Inertial Response Total Load
Governor Response
event of 4,100 MW is outside of normal design basis events 115,000
subset of the synchronous generators has both active Figure 2. Frequency Response to Loss of Generation,
governors and room to move. At any given time, some No-Wind Case.
conventional generators will be operating without active
governors (e.g. nuclear power stations) or at maximum
power (e.g. valves wide open). These units do not VI. PERFORMANCE
contribute to governor response. A dotted curve is sketched
in the figure to show the approximate aggregate response of A. Performance without Frequency Responsive Controls
all the generators with active governors and headroom. By As wind generation displaces synchronous generation,
the end of the simulation, this governor response has overall system inertia will decrease due to de-committed
contributed about 3,700 MW. synchronous machines. The synchronous machines that
remain committed, but which are dispatched to lower power
5
levels, continue to contribute to the inertial response of the The impact on system frequency can be better understood
system. In general, those units will also have more range to by examining the active power response of the wind
increase power in response to governor control. The impact turbines, as shown in Figure 5. The wind power for the
of these two effects can be observed in Figure 3, which 20% wind case without WindINERTIA control (blue trace)
shows frequency for the base (orange trace), 10% (blue is flat, as expected. The inertial control (green trace)
trace) and 20% (green trace) wind scenarios. Initially, the increases the output of the wind plants substantially. It
reduction in net system inertia causes the system frequency reaches a maximum about 5 seconds into the event, just as
to decline more rapidly. This can be seen in the first few the system frequency is experiencing a high rate of decline.
seconds of the 10% and 20% wind traces. The decline of Extra power is delivered for about 13 seconds, after which
frequency is countered by governor action. Qualitatively, the power drops below the initial level. As discussed above,
there are fewer governors with more room to move as the the energy extracted from the rotating energy of the wind
wind penetration increases. The net result is that the turbines must be recovered from the grid to reaccelerate the
minimum frequency of the swing decreases with increasing WTGs to normal speed. The active synchronous machine
wind power, and the longer-term response is somewhat governors have had time to respond at this point. Therefore,
better. the system frequency minimum, which is the critical
60.1 performance metric, is better.
No Wind 33,000
60 10% Wind
20% Wind
20% Wind
59.9
20% Wind with WindINERTIA
32,000
Frequency (Hz)
59.8
31,000
Power (MW)
59.7
59.6 30,000
59.5
29,000
59.4
0 5 10 15 20 25 30 35 40
Time (seconds)
28,000
0 5 10 15 20 25 30 35 40
Figure 3. Frequency Response to Loss of Generation Time (seconds)
59.8
fewer turbines running at this operating point, the maximum
59.7 power is lower (pink trace vs. green trace). However, since
the wind speed is above rated, there is power available from
59.6
the wind to supply the incremental electric power. At about
20 seconds, the inertial control returns the total wind power
59.5
to pre-disturbance levels. It does not need to recover the
59.4
incremental energy delivered to the grid. The wind has
0 5 10 15 20
Time (seconds)
25 30 35 40
supplied that energy via turbine pitch control.
Frequency (Hz)
0 5 10 15 20 25 30 35 40
59.8
Time (seconds)
59.7
Figure 6. Impact of Operating Point on Frequency
Response to Loss of Generation. 59.6
33,000
59.5
20% Wind
20% Wind
28,000 31,000
Power (MW)
0 5 10 15 20 25 30 35 40
Time (seconds)
30,000
Figure 7. Impact of Operating Point on Incremental
Power from WindINERTIA after Loss of Generation.
29,000
other system resources reflects how the system would likely Synchronous machines inherently contribute some of their
be operated. This is not to say that all other credible stored inertial energy to the grid. GE wind plants with
operating conditions will necessarily result in improved WindINERTIA control provide a functionally similar
system frequency response. Rather, these cases show that it response.
is technically and economically possible, with controls The longer-term frequency response and recovery is
commercially available today, to have better system driven by the governor action of the committed and
frequency response with high levels of wind generation. dispatched synchronous machines. Wind does not
60.1 No Wind
20% Wind
contribute to these primary reserves unless market structures
60 20% Wind with WindINERTIA encourage it to do so. At relatively low penetration levels,
20% Wind with WindINERTIA, Different Operating Point
20% Wind, Curtailed
the benefits of requiring or using active power management
59.9
20% Wind, Curtailed with WindINERTIA capabilities, such as governor response, may not outweigh
the cost. This is nothing new, and no different from other
Frequency (Hz)
59.8
types of generating resources that run “flat out” under the
59.7 present structure. There is a system cost associated with
providing this capability from any generating resource. The
59.6
role of the system operator is to make sure that the response
59.5
is there, and that the least expensive resource that can do so,
is doing so. Under some conditions, wind may be the
59.4
0 5 10 15 20 25 30 35 40
economic choice. GE wind plants with governor control
Time (seconds) provide just this type of response.
This analysis has shown that WindINERTIA has a
Figure 10. Summary of Frequency Performance. substantial impact. The minimum frequency is improved,
33,000 not degraded, with significant levels of wind generation. It
20% Wind
20% Wind with WindINERTIA is technically and economically possible, with controls
20% Wind with WindINERTIA, Different Operating Point
32,000 20% Wind, Curtailed
commercially available today, to have better system
20% Wind, Curtailed with WindINERTIA
frequency response with high levels of wind generation.
Ultimately, grid codes may be modified to include some
31,000
type of inertial response requirement. The development of
Power (MW)
http://www.balch.com/files/upload/FRCC_Interim_Report_6_3_08.pd
f
[7] California Energy Commission’s Intermittency Analysis Project Study
“Appendix B - Impact of Intermittent Generation on Operation of
California Power Grid”
http://www.energy.ca.gov/2007publications/CEC-500-2007-
081/CEC-500-2007-081-APB.PDF
[8] Bai, X., Clark, K., Jordan, G., Miller, N., Piwko, R., Zimberlin, J.,
"The Effects of Integrating Wind Power on Transmission System
Planning, Reliability, and Operations", March 2005,
http://www.nyserda.org/publications/wind_integration_report.pdf.
[9] Van Zandt, D., Freeman, L., Gao, Z., Piwko, R., Jordan, G., Miller,
N., Brower, M., “Ontario Wind Integration Study”, October 2006.
[10] Walling, R., Banunarayanan, V., Chahal, A., Freeman, L., Martinez,
J., Miller, N., Van Zandt, D., Walling, M., Walling, R., “Analysis of
Wind Generation Impact on ERCOT Ancillary Services
Requirements”, March 2008.
[11] GE Energy. May 2010. “Western Wind and Solar Integration Study:
February 2008 – February 2010,” NREL Report No. SR-550-47434.
[12] EirGrid Grid Code, Version 3.1 May 2008, Section WFPs 1.5.x.x.7
XI. BIOGRAPHIES