Welded Beam page : 1

CONSUMABLE Total 71 190


electrode 96 kg 20.000 1.920.000
shielding 7 botol 185.000 1.295.000 SUMMARY
energy 796 kWh 1.500 1.194.690 Material 9.000
machine time 302 hours 1.000 302.183 Consumable 2.523
oxygen 9 botol 50.000 450.000 Manpower 1500
LPG 50 kg 1 botol 850.000 850.000 Sandblast 1200
grinder 7" 6 pcs 15.600 93.600 Delivery 500
primer coat 10 kg 60.000 600.000 Erection 1500
top coat 15 kg 65.000 975.000 TOTAL : 16.223
thinner 7 ltr 38.000 266.000
7.946.473 2.523
MANPOWER
man power overtime = 0% normal overtime
cutting 11 0 18.958 202.850
grinding 31 0 16.250 503.750
fitting 87 0 24.375 2.108.438
welding 46 0 24.375 1.109.355
drilling 19 0 16.250 308.750
painting 32 0 18.958 606.667
alignment 50 0 24.375 1.218.750
supervisor 27 0 32.500 892.813