PROGRESS WORKS

ELECTRICAL TEAM TASKS & WORK PROGRESS - 26/04/2021


APRIL TARGET
WORK TO REMARKS
Minggu ke-4 BE DONE
TASKS 27/04/21 28/04/21 29/04/21 30/04/21
TEAM 1 1) Tunggu part - DB end of May
Lampu - SB-L1(50%), Lampu - Corridor (80%) -
Brandon 1) Fitting lampu luminaries, SSO Meeting Room, Chemical Lampu Level 3 - Control & trunking bracket yg Insulation & Continuity test 30/04/21 2) Belum siap - Balancing tank (ada formwork), MSB,
(Lamp & SSO) Level 3 - Gset, Surau M, Office(ada leaking - Jasni), 3m Corridor,
Store, Chemical Dosing, VIP Room (100%) sangkut dgn luminaries Control & VIP Room (100%)
Padli 2) DB fittings Surau F(100%)
SB.L2-L9 (80% siap)
dibuka
extend 2 hari (4/5/21)

TEAM 2 extend 1 week (10/5/21) - Lightning Protection


digging for lay tinned digging for lay tinned
Saiful 1) MSB Room - Lay cable, trunking & cable tray (7 days to be done) copper - between copper - between 3/4 brg on site
Sarip 2) Earthing 4 chambers for MSB Control Panel Laying tinned copper 70% building & ramp area. building & ramp area.
Laying tinned copper 100%
(50%) (70%) 05/05/21 Copper rod & chamber belum buat
3) Lightning Protection - 22 chambers Laying tinned copper 20% Laying tinned copper 80% 05/05/21 Copper rod & chamber belum buat
TEAM 3 extend 1 week (10/5/21) - Lightning Protection

Fazzel 1) MSB Room - Lay cable, trunking & cable tray (7 days to be done) digging for lay tinned lay tinned copper dari lightning protection 3/4 brg on site
copper - between building tiang ke tiang di junction box installation
Muslih 2) Earthing 4 chambers for MSB Control Panel Laying tinned copper 70% & ramp area (20%) competition pool (70%) - done 2 box (10%) 05/05/21 Copper rod & chamber belum buat
Jabir 3) Lightning Protection - 22 chambers Laying tinned copper 20% 05/05/21 Copper rod & chamber belum buat
TEAM 4 liaise dgn Hamid utk kerja hacking

Jaafar 1) Kiddies pool chambers to layer copper tape 03/05/21


Ilham 2) Underwater light - hacking opening light & G.I conduit painting under competition pool Install GI conduit, wiring point Install GI conduit, wiring point Install GI conduit, wiring point 03/05/21 extend 1 week (10/5/21)
(100%) & install conduit under & supply under competition & supply under competition & supply under competition
Anuar 3) Underwater light - wiring & fittings competition pool (80%) pool 50% done pool 80% done pool 70% done tunggu transformer 240-12VAC

TEAM 5
Salleh 1) J-Bolt for Compund & Street Light
Paint GI conduit Level 3 - 30/04/21
Basir 2) Tutup trench & simen d Bilik Genset Urgent (Ceiling board extend 1 hari (3/5/21)
installation)
3) Relocate conduit/trunking at balancing tank & re-
Ridsa 30% siap 60% siap 80% siap
arrange/rewiring cable to DB Canteen & DB P1 (roller shutter)

TEAM 6
Sulaiman 1) Level 1 GI conduit & wiring service bay 30% siap 50% siap 70% siap Sulaiman support team 4 30/04/21
extend 2 hari (4/5/21)
Erny 2) Flood light (4 tiang) & lampu under kiddies pool- wiring & fitting & 5 (Erny absent)
PROGRESS WORKS
ELECTRICAL TEAM TASKS & WORK PROGRESS - 03/05-09/05/2021
MAY
Week 1
TASKS 03/05/21 04/05/21 05/05/21 06/05/21 07/05/21
TEAM 1
Electrical insulation & Electrical insulation &
Brandon 1) Fitting lampu luminaries, SSO Electrical insulation & luminaries fitting Level 1 continuity test - meeting Fitting under kiddies pool continuity test - meeting
corridor (80%) & service room 100% surau M & F 6/8 (75%), Arrange GI pipe surau M & F (100%), fitting
continuity test (office)
Padli 2) DB fittings bay (70%), (0%) luminaries fitting Level & wiring to DB Office lamp under kiddies pool
1 corridor (100%) (100%)

TEAM 2
sambung earthing
Saiful 1) MSB Room - Lay cable, trunking & cable tray (7 days to be done) Muslih & Sarip - junction box (86%) -
CUTI CUTI sambung earthing Sarip 1/2 day kurang 2 box
Sarip 2) Earthing 4 chambers for MSB Control Panel junction box (40%)
3) Lightning Protection - 22 chambers
MSB earthing (copper
TEAM 3 rod & chamber) 90%,
Copper Rod & earth Copper Rod & earth Copper Rod & earth
Fazzel 1) MSB Room - Lay cable, trunking & cable tray (7 days to be done) MSB earthing (copper MSB earthing (copper
chamber (27%) - 6 nos chamber (54%) - 12 nos chamber (81%) - 18 nos
Muslih 2) Earthing 4 chambers for MSB Control Panel rod & chamber) 50% rod & chamber) 90% (total 22 nos), earthing
(total 22) (total 22 nos)
SESB transformer
Jabir 3) Lightning Protection - 22 chambers
TEAM 4
Jaafar 1) Kiddies pool chambers to layer copper tape GI conduit installation GI conduit installation GI conduit installation
GI conduit installation ABSENT
Ilham 2) Underwater light - hacking opening light & G.I conduit (35%) (45%) (65%)

Anuar 3) Underwater light - wiring & fittings


TEAM 5
Arrange GI, trunking to
Salleh 1) J-Bolt for Compund & Street Light Arrange GI, trunking to
DB (100%), Fitting
DB, Fitting SSO/switch,
Basir 2) Tutup trench & simen d Bilik Genset SSO/switch, Mock up @
point AC for Mock up @
Meeting Room,
Meeting Room (2days to
rearrange cable from rearrange 3 cable from
3) Relocate conduit/trunking at balancing tank & re-arrange cable rearrange cable from complete)
Ridsa 90% siap SESB to DB P1 & L1 MSB to DB Shop
to DB Canteen & DB P1 SESB to DB P1 & L1
(100%)
TEAM 6
Sulaiman 1) Level 1 trunking service bay 70% siap Rearrange GI conduit &
Erny Absent, GI conduit
ABSENT wiring under kiddies pool
Erny 2) Flood light (4 tiang) - wiring & fitting 20% siap & wiring service bay
(roller shutter)
PROGRESS WORKS
MAY TARGET
WORK TO REMARKS
Week 1 BE DONE
08/05/21 09/05/21
1) Tunggu part - DB
Re arrange GI Conduit
switch center L1. L2, L3 2) Belum siap - Balancing tank (mid May start), MSB,
Gset, Surau M, Office, SB.L2-L9 (3 NOS UNDONE - blm
& replace sso single to wiring
twin sso

sambung earthing
junction box

lay tinned copper,


Copper Rod & earth
chamber (81%) - 18 nos 09/05/21
(total 22 nos), earthing
SESB transformer

GI conduit order
GI conduit installation
under competition pool 09/05/21
(14 day tb done)

Confirm blk kedudukan pole ikut drain - Siti

GI conduit installation
09/05/21
service bay
ELECTRICAL TEAMS ATTENDANCE
MAY
ST SN MN TU WE TH FR ST SN MN TU WE TH FR ST SN MN TU WE TH FR ST SN MN TU WE TH FR ST SN MN
NO. NAMA 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1 Saiful / X X X X 1/2 /
2 Fazzel X / / / / / /
3 Ilham X / / / / X /
4 Brandon / / / / / /
5 Padli / / / / / /
6 Muslih X / / / / / X
7 Ahmad Salleh / / / X X / /
8 Sulaiman / / X / / /
9 Basir 1/2 / / / / X
10 Jaafar / / / / / X /
11 Musa (Erny) / / / X / X /
12 Ridsa / / / / / /
13 Anuar / / / / / X /
14 Sarip X X X 1/2 / 1/2
15 Jabil / / / / 1/2 / /

Legends: Normal
RD Rest Day
PH Public Holiday 13 & 14 - AIDILFITRI, 26 - WESAK, 30, 31 & 1 - KEAMATAN
ELECTRICAL OUTSTANDING WORKS
No. TASK DESCRIPTION REMARKS PIC TARGET
Salleh liaise Abg Hamid (form work etc), Fitter -
Install J-Bolt for Compund & Street Light Basir & Ridsa
Salleh
loop-in, loop-out modular junction box, cut-
1 BQ Item N out fuses, hinged type service door, concrete DB - 63A DP MCCB, MCBs, 40A DP contactors,
A/M selector switch, timer switch with 24hrs 29/05/21
foundation base with cable entry pipes and spring reserve, looping wire. SPD
other necessary accessories Fazzel
SUBMAIN - Hot Dipped Galv. Steel Trunking from
MSB-NE to CP-SL

Wiring for remote relay switching of


Hacking Slab & Wall for GI Conduit
underwater light underwater pool lighting from control room Fitter - Jaafar & Anuar
to DB-UW, using 1 x 2c –2.5mm2
2 Ilham 29/05/21
step-down transformer in weather-proof UV-resistant non-metallic junction box, minimum
BQ Item E, Item F 2.5mm2 fixed and flexible wirings from transformer to light fittings, fixings, brackets,
earthing to protective conductor, above-water lamp access type fitting

i) Fitting Cable at MSB Room Install cable tray, trunking, wiring, fitting Muslih
cable
To supply, install and test the complete
3 ii) Earthing System at MSB Room earthing system for MSB'E' , MSB'NE' and Fitter - Jabir & Sarip Fazzel 29/05/21
PFCB
BQ Item B
Hacking slab for GI ducting from Electrical PIT
to CP-SL SUBMAIN - Hot Dipped Galv. Steel Trunking from
4 MSB-NE to CP-SL
Fitter - Sulaiman & Erny Saiful 15/05/21
BQ Item N
Install tinned copper at Competition &
Kiddies Pool
Equipotential bonding to steel base plate of
i) From ground to pole 15/05/21
support poles
Equipotential bonding of upper steel
ii) From pole to slab (stump) structure pipe members to tinned copper 15/05/21
tape from roof
5 Equipotential bonding to roof structure steel Fitter - Jabir & Sarip Saiful

iii) From stump to roof base plate using 1/4" thick mild steel plate
weld to base plate, bolted bronze bonding
plate
iV From chamber to chamber Equipotential bonding to main electrical 29/05/21
system earth.
copper tape bonding conductor from test
v) From wall to earth chamber joints to corresponding earth chambers
15/05/21

No. TASK DESCRIPTION REMARKS PIC TARGET


Equipotential bonding of mild steel railing
vi) From MS Railing to chamber surrounding competition and kids pools using 29/05/21
approved pipe clamp

5 vii) From Competition Pool to Ground Equipotential bonding of steel reinforcement Fitter - Jabir & Sarip Saiful 15/05/21
bars surrounding structure (walls and floor)
viii) From Kiddies Pool to Ground to Earth. 15/05/21

BQ Item G
3m Wide Corridor 17/05/21
Changing Room Male 20/05/21
Changing Room Female 23/05/21
Toilets & Disable toilet 26/05/21
Medical Treatment 28/05/21
6 Wiring Level 2 (BQ Item E) Security Fitter - Basir & Ridsa Brandon 03/06/21
Ticket Counter 03/06/21
Shop 05/06/21
Kitchen 06/06/21
Canteen, Main Lobby 12/06/21
Equipment & Utility Room 07/06/21
Fittings
i) Switch & SSO (BQ Item E) Level 1, 2 & 3 Fitter - Sulaiman & Erny Padli 29/05/21
7
ii) Lamp & Luminaries (BQ Item F) Level 1, 2 & 3 29/05/21
iii) DB (BQ Item C) Level 1, 2 & 3 Fitter - Jaafar & Anuar Brandon 06/06/21

8 Opening 24 Nos Underwater light (BQ Item F) Competition Pool Fitter - Jaafar & Anuar Ilham 15/06/21

Severed Underground Cable to Water


9 Hacking & Fitting cable 10mm2 at transfer Transfer Pump House CP­TP was cut and no Fitter - Jabir & Sarip Fazzel 29/05/21
pump (BQ Item Q 4)
longer full length

10 Install & Wiring Lighting under Competition & Fitter - Sulaiman & Erny Muslih 15/05/21
Kiddies Pool (BQ Item F)
11 Laying cable 6mm2 for CL near kiddies pool mini floodlight with adjustable bracket (for Fitter - Sulaiman & Erny Fazzel 15/05/21
(BQ Item F) & fitting pan and tilt)

No. TASK DESCRIPTION REMARKS PIC TARGET


Opening for trunking at level 3 (Control
12 RFTI Fitter - Basir & Ridsa Brandon 15/05/21
Room) to Catwalk (BQ Item F)

13 Fitting Isolator for STP incoming cable (BQ Fitter - Basir & Ridsa Saiful 15/05/21
Item C)