2021.05.08 Electrical Work Progress
Fazzel 1) MSB Room - Lay cable, trunking & cable tray (7 days to be done) digging for lay tinned lay tinned copper dari lightning protection 3/4 brg on site
copper - between building tiang ke tiang di junction box installation
Muslih 2) Earthing 4 chambers for MSB Control Panel Laying tinned copper 70% & ramp area (20%) competition pool (70%) - done 2 box (10%) 05/05/21 Copper rod & chamber belum buat
Jabir 3) Lightning Protection - 22 chambers Laying tinned copper 20% 05/05/21 Copper rod & chamber belum buat
TEAM 4 liaise dgn Hamid utk kerja hacking
TEAM 5
Salleh 1) J-Bolt for Compund & Street Light
Paint GI conduit Level 3 - 30/04/21
Basir 2) Tutup trench & simen d Bilik Genset Urgent (Ceiling board extend 1 hari (3/5/21)
installation)
3) Relocate conduit/trunking at balancing tank & re-
Ridsa 30% siap 60% siap 80% siap
arrange/rewiring cable to DB Canteen & DB P1 (roller shutter)
TEAM 6
Sulaiman 1) Level 1 GI conduit & wiring service bay 30% siap 50% siap 70% siap Sulaiman support team 4 30/04/21
extend 2 hari (4/5/21)
Erny 2) Flood light (4 tiang) & lampu under kiddies pool- wiring & fitting & 5 (Erny absent)
PROGRESS WORKS
ELECTRICAL TEAM TASKS & WORK PROGRESS - 03/05-09/05/2021
MAY
Week 1
TASKS 03/05/21 04/05/21 05/05/21 06/05/21 07/05/21
TEAM 1
Electrical insulation & Electrical insulation &
Brandon 1) Fitting lampu luminaries, SSO Electrical insulation & luminaries fitting Level 1 continuity test - meeting Fitting under kiddies pool continuity test - meeting
corridor (80%) & service room 100% surau M & F 6/8 (75%), Arrange GI pipe surau M & F (100%), fitting
continuity test (office)
Padli 2) DB fittings bay (70%), (0%) luminaries fitting Level & wiring to DB Office lamp under kiddies pool
1 corridor (100%) (100%)
TEAM 2
sambung earthing
Saiful 1) MSB Room - Lay cable, trunking & cable tray (7 days to be done) Muslih & Sarip - junction box (86%) -
CUTI CUTI sambung earthing Sarip 1/2 day kurang 2 box
Sarip 2) Earthing 4 chambers for MSB Control Panel junction box (40%)
3) Lightning Protection - 22 chambers
MSB earthing (copper
TEAM 3 rod & chamber) 90%,
Copper Rod & earth Copper Rod & earth Copper Rod & earth
Fazzel 1) MSB Room - Lay cable, trunking & cable tray (7 days to be done) MSB earthing (copper MSB earthing (copper
chamber (27%) - 6 nos chamber (54%) - 12 nos chamber (81%) - 18 nos
Muslih 2) Earthing 4 chambers for MSB Control Panel rod & chamber) 50% rod & chamber) 90% (total 22 nos), earthing
(total 22) (total 22 nos)
SESB transformer
Jabir 3) Lightning Protection - 22 chambers
TEAM 4
Jaafar 1) Kiddies pool chambers to layer copper tape GI conduit installation GI conduit installation GI conduit installation
GI conduit installation ABSENT
Ilham 2) Underwater light - hacking opening light & G.I conduit (35%) (45%) (65%)
sambung earthing
junction box
GI conduit order
GI conduit installation
under competition pool 09/05/21
(14 day tb done)
GI conduit installation
09/05/21
service bay
ELECTRICAL TEAMS ATTENDANCE
MAY
ST SN MN TU WE TH FR ST SN MN TU WE TH FR ST SN MN TU WE TH FR ST SN MN TU WE TH FR ST SN MN
NO. NAMA 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1 Saiful / X X X X 1/2 /
2 Fazzel X / / / / / /
3 Ilham X / / / / X /
4 Brandon / / / / / /
5 Padli / / / / / /
6 Muslih X / / / / / X
7 Ahmad Salleh / / / X X / /
8 Sulaiman / / X / / /
9 Basir 1/2 / / / / X
10 Jaafar / / / / / X /
11 Musa (Erny) / / / X / X /
12 Ridsa / / / / / /
13 Anuar / / / / / X /
14 Sarip X X X 1/2 / 1/2
15 Jabil / / / / 1/2 / /
Legends: Normal
RD Rest Day
PH Public Holiday 13 & 14 - AIDILFITRI, 26 - WESAK, 30, 31 & 1 - KEAMATAN
ELECTRICAL OUTSTANDING WORKS
No. TASK DESCRIPTION REMARKS PIC TARGET
Salleh liaise Abg Hamid (form work etc), Fitter -
Install J-Bolt for Compund & Street Light Basir & Ridsa
Salleh
loop-in, loop-out modular junction box, cut-
1 BQ Item N out fuses, hinged type service door, concrete DB - 63A DP MCCB, MCBs, 40A DP contactors,
A/M selector switch, timer switch with 24hrs 29/05/21
foundation base with cable entry pipes and spring reserve, looping wire. SPD
other necessary accessories Fazzel
SUBMAIN - Hot Dipped Galv. Steel Trunking from
MSB-NE to CP-SL
i) Fitting Cable at MSB Room Install cable tray, trunking, wiring, fitting Muslih
cable
To supply, install and test the complete
3 ii) Earthing System at MSB Room earthing system for MSB'E' , MSB'NE' and Fitter - Jabir & Sarip Fazzel 29/05/21
PFCB
BQ Item B
Hacking slab for GI ducting from Electrical PIT
to CP-SL SUBMAIN - Hot Dipped Galv. Steel Trunking from
4 MSB-NE to CP-SL
Fitter - Sulaiman & Erny Saiful 15/05/21
BQ Item N
Install tinned copper at Competition &
Kiddies Pool
Equipotential bonding to steel base plate of
i) From ground to pole 15/05/21
support poles
Equipotential bonding of upper steel
ii) From pole to slab (stump) structure pipe members to tinned copper 15/05/21
tape from roof
5 Equipotential bonding to roof structure steel Fitter - Jabir & Sarip Saiful
iii) From stump to roof base plate using 1/4" thick mild steel plate
weld to base plate, bolted bronze bonding
plate
iV From chamber to chamber Equipotential bonding to main electrical 29/05/21
system earth.
copper tape bonding conductor from test
v) From wall to earth chamber joints to corresponding earth chambers
15/05/21
5 vii) From Competition Pool to Ground Equipotential bonding of steel reinforcement Fitter - Jabir & Sarip Saiful 15/05/21
bars surrounding structure (walls and floor)
viii) From Kiddies Pool to Ground to Earth. 15/05/21
BQ Item G
3m Wide Corridor 17/05/21
Changing Room Male 20/05/21
Changing Room Female 23/05/21
Toilets & Disable toilet 26/05/21
Medical Treatment 28/05/21
6 Wiring Level 2 (BQ Item E) Security Fitter - Basir & Ridsa Brandon 03/06/21
Ticket Counter 03/06/21
Shop 05/06/21
Kitchen 06/06/21
Canteen, Main Lobby 12/06/21
Equipment & Utility Room 07/06/21
Fittings
i) Switch & SSO (BQ Item E) Level 1, 2 & 3 Fitter - Sulaiman & Erny Padli 29/05/21
7
ii) Lamp & Luminaries (BQ Item F) Level 1, 2 & 3 29/05/21
iii) DB (BQ Item C) Level 1, 2 & 3 Fitter - Jaafar & Anuar Brandon 06/06/21
8 Opening 24 Nos Underwater light (BQ Item F) Competition Pool Fitter - Jaafar & Anuar Ilham 15/06/21
10 Install & Wiring Lighting under Competition & Fitter - Sulaiman & Erny Muslih 15/05/21
Kiddies Pool (BQ Item F)
11 Laying cable 6mm2 for CL near kiddies pool mini floodlight with adjustable bracket (for Fitter - Sulaiman & Erny Fazzel 15/05/21
(BQ Item F) & fitting pan and tilt)
13 Fitting Isolator for STP incoming cable (BQ Fitter - Basir & Ridsa Saiful 15/05/21
Item C)