Professional Documents
Culture Documents
END-OF-SEMESTER EXAMINATION
SEMESTER 2, 2016/2017 SESSION
INSTRUCTIONS TO CANDIDATES
DO NOT OPEN UNTIL YOU ARE ASKED TO DO SO.
Answer FOUR (4) Questions only.
Answer ALL the Questions in Part A and any THREE (3) Questions in Part B
REFERENCE(S) ALLOWED
The Rules of Court 2012
APPROVED BY
PART A
Amino Power (M) Sdn Bhd, a company incorporated in Malaysia and having its
registered address at No.1, Jalan Anggerik, Shah Alam, Selangor, is in the business of
selling engineering equipment and products. Another company, Megah Alam (M) Sdn
Bhd, is the main contractor of a project known as “Constructing and Completing High
Tech City Centre at Lot PT 12345 in the District of Kemuning, Shah Alam, Selangor.”
By way of a letter dated 1 November 2013, Megah Alam Sdn Bhd appointed Amino
Power Sdn Bhd as a nominated sub-contractor to supply, deliver, install, test and
commission generators installation services for the project for the sum of RM20 million
over a period of three years. It was agreed between the parties that the payment term
should be 10% down payment, 70% upon delivery to the site before installation, 10%
Pursuant to the contract, Amino Power (M) Sdn Bhd supplied and installed 10 generators
as requested by Megah Alam (M) Sdn Bhd. The progress claims were submitted to the
project’s mechanical and electrical engineer, Dynamic Engineers Sdn Bhd, and the
architect, Architect Jerneh Sdn Bhd, for the certification of the work done. As at 1st
November 2016, Dynamic Engineers and Architect Jerneh Sdn Bhd certified the value of
the works as RM18 million. Since RM2 million had been paid as the down payment,
2
Amino Power (M) Sdn Bhd claimed a balance sum of RM16 million from Megah Alam
(M) Sdn Bhd but the company refused to pay for the work done and certified.
After several reminders sent to Megah Alam (M) Sdn Bhd, Amino Power Sdn Bhd
received a payment of RM10 million with a reply from the company stating that they
were only eligible to pay RM10 million for the works done due to the following reasons:
ii) Five of the generators supplied were not functioning well for several months after
the installation. Even after the service had been done by Amino Power (M) Sdn
Bhd, the default still occurred. Megah Alam Sdn Bhd had to incur additional cost
iii) Megah Alam (M) Sdn Bhd had to pay for the late payment interest to the owner of
the project, that is, the State of Selangor due to the delay caused by Amino Power
Sdn Bhd.
Amino Power (M) Sdn Bhd contended that Megah Alam (M) Sdn Bhd had no right to
1) Amino Power Sdn Bhd had issued a letter asking for eight (8) months extension
period due to unforeseen technical issues and the shortage of manpower. It was
also stated in the letter that if there was no reply from the company within one (1)
month from the date the letter was issued, the company was deemed to agree on
the extension period. There was no reply issued from Megah Alam (M) Sdn Bhd.
3
2) It is agreed in the term of the contract that any complaint on the malfunction of
the machines must be made within three (3) months from the installation date.
There was no complaint made by Megah Alam (M) Sdn Bhd within this specified
period.
Dissatisfied with the conduct of Megah Alam (M) Sdn Bhd in deducting the amount of
payment, Amino Power Sdn Bhd seeks your legal advice pertaining to several issues in
this case.
QUESTION 1
a) Whether there is a cause of action for the company (Amino Power Sdn Bhd) to
(1 ½ Marks)
b) If there is a cause of action, identify the court and the district where it is located at
which the case should be filed in and the considerations that should be taken into
(1 Mark)
4
c) List the documents that should be used to commence this case, their content, and
(1 Mark)
d) The procedure involved in order to inform the other party and the court of the
facts of the disputes that arose between the parties, the legal issues therein, and the
(2 Marks)
QUESTION 2
a) Discuss the steps that the defendant in the proceeding should take after being
served with the documents in Questions 1(c) and 1(d) above and the effect(s) of
non-compliance.
(1 ½ Marks)
b) Discuss the application that is most appropriate for the plaintiff to apply in order
also explain the legal point(s) the other party should raise or argue in order to
(3 Marks)
5
QUESTION 3
a) Assume that the court has dismissed the application and the parties proceed to
ii. Determine the relevant documents that could be used to support the
Plaintiff's case, and how these documents should be brought into the trial.
(1 ½ Marks)
b) At the Pre-Trial Case Management, the Plaintiff informed the court that they
would call two witnesses to testify. Explain the procedure for calling and the
(1 ½ Marks)
c) After a full trial the court ordered the Defendant to pay the outstanding sum to the
Plaintiff but the Defendants still refused to pay. Advise the Plaintiff on the
options available to force the Defendant to accordingly comply with the court
order.
(2 Marks)
OR
6
c) Explain the step/s the Defendant may take should it disagree with the court’s
decision and the necessary documents it should file. While awaiting the outcome
of the course of action so taken, determine the step(s) it may take to stop the
(2 Marks)
7
PART B
QUESTION 1
a) briefly explain the meaning of a cause of action and its importance in ensuring the
b) discuss the factors that determine the jurisdiction of a High Court in Malaysia and
the ground(s) upon which the argument of ‘forum inconvenience’ can be raised;
(5 Marks)
QUESTION 2
Briefly explain the procedure governing a civil litigation involving an action that begins
by writ starting from the commencement of the action until the pronouncement of the
judgment in open court. Your answer must clearly state the duty and responsibility of the
parties to the suit and the court involved at each trial stage based on the Rules of Court
2012.
(5 Marks)
8
QUESTION 3
a) discuss the circumstances when a party to an action can apply for a mareva
injunction,
b) how the order for mareva injunction or the nature of the order should be stated in
c) explain the conditions that must be fulfilled in order to obtain the order
successfully,
d) the basis upon which the order may be opposed to by the other party.
(5 Marks)
QUESTION 4
a) Explain the rules governing amendment of statement of claim with leave of court
b) Discuss the different rules governing an amendment that is made at the early stage
(5 Marks)
9
QUESTION 5
a) State the procedure governing appeal from subordinate courts to the High Court.
b) State the basis upon which the judge at the High Court may interfere with the
(5 Marks)
10