OVER VIEW OF

SAP PS Configuration
Pack
Published by Team of SAP
Consultants at SAPTOPJOBS
Visit us at www.sap-topjobs.com

Copyright 2010-12@SAPTOPJOBS

All rights reserved. No part of this publication may be reproduced, stored in


a retrieval system, or transmitted in any form, or by any means electronic
or mechanical including photocopying, recording or any information storage
and retrieval system without permission in writingfrom
SAPTOPJOBS
PS Configuration Overview

1. PROJECT SYSTEM STRUCTURE 4

1.1 Define Special Characters for Projects 8

1.2 Define Project Coding Mask 11

1.3 Define Field selection for Work Breakdown Structures 14

1.4 Define Validation 19

1.5 Maintain Substitution 24

2. DEFINE TIME PROFILES 29

2.1 Define Profiles for Time Scales 33

2.2 Define PRT Usage 36

3. ACTIVATE PROJECT MANAGEMENT IN CONTROLLING AREA 39

3.1 Maintain Value categories 42

3.2 Unit Costing 45

3.3 Create / Change Planning Profile 49

3.4 Maintain Budget Profile 54

3.5 Define Tolerance Limits 57

3.6 Maintain Progress Version 60

4. SCHEDULING TYPES 63

4.1 Parameters for Network Scheduling 66

4.2 Define Database Selection Profile 69


Hello Everyone,

A Ware Welcome To You All! We are really excited to offer the


complete SAP PS configuration pack to the SAP community. This
was a much- awaited pack and we are happy to present that to
you… As you are aware that our SAP FICO, PP/QM , SD, MM/WM
HR, and PM have already achieved the best selling status and have
received lots of accolades and really helped the consultants take
their SAP knowledge and career to the next level …I am very
confident that PS configuration package will go a step forward and do
much more than that……….

For those who have been on our list and who have bought from us
earlier you all know that we have over-delivered on each of our
configuration packs and we want to do the same thing with SAP P S
config pack too… For those who have visited our site for the first
time I would like to welcome you to our site and promise you that
we would do our best to ensure that your life at the clients place would
be very comfortable…

What I have done here is given you a brief of around 69+ pages
of content in PS pack so that you can have a feel of what it would be
like in terms of structure. The whole pack is extremely voluminous,
step by step guide this is just a feeler… So I hope you enjoy this…. So
lets dive right in….
1. Project System Structure

Planning of all activities in detail is an essential process in any


project irrespective of its size and volume. Right Project
planning helps to ensure the completion of project at right
time with right amount cost involved.

It is also essential to know the amount of resource and funds


required to execute the project and also the timings of its
requirement. In an organization many tasks like construction,
installation of large machinery etc.., are carried out as projects.

Project organization is a prime and foremost step in project


structuring. Project Organization in PS helps to

 Plan the project


 Monitor the project progress
 Control the project progress

Projects can be structured based on

 Work Breakdown Structure (WBS) element


 Work package – with activities

From Finance point of view, each project is identified as

 Externally financed project


 Internally financed project

Project System Organization: -


Project system has got the following parameters.

Project definition
WBS element
Networks
Activities

The above discussed PS module elements are assigned to the


existing organizational units. I.e. these are assigned to the
existing controlling area, company code, business area, profit
center and plant.

In short we can say that there is no independent org structure


for PS module like SD and MM. The PS parameters are
assigned to the existing organizational units at different levels.

Let us discuss the possible assignments of each PS elements


with existing org. structure.

Project Definition:

Project Definition is the process of defining the project with its


objective, Accounting information and logistic related
information.

Accounting information:-

Controlling Area
Company code
Business Area
Plant
Location
Profit center
Currency
Budget profile
Interest calculation profile
Planning profile
Investment profile
Result Analysis key
Logistic information

Network profile
WBS Scheduling profile
Person responsible
Start & End date
Factory calendar
Time unit

WBS Element: -

WBS element is a master data used for projects. The usage of


WBS is

 Organizes the project task in an order


 Process planning, cost planning, capacity planning
 Costing and controlling
 To know the amount of work involved in a project

WBS is created with reference to the project definition. The


data maintained under project definitions are copied into WBS

WBS Accounting information:-

 Currency – Copied from projection profile.


Can be changed only if company code
currency is different from controlling
area and there must NOT be any
budget, commitments exist for the
WBS element.
 Company code
 Business area
 Profit center
 Plant
Network: -

Network represents flow of task in a project. Tasks performed


with WBS such as planning, controlling etc. can be done with
network also. The structure of the network is similar to that of
production order and maintenance order.

Network can be assigned to

 Project definition
 WBS
 Time sheet entry

Activities: -

Activities indicate the sequence of any process. Activities


contains

Duration
Start and finish
Requirement of resources
Cost requirements

Activities can be

Internally processed
Externally processed
Service related
General cost activities

Now let us see what is there in the configuration for PS


structure.

The project definition contains various profiles from costing


point of view. We shall start from WBS structure.
Define Special Characters for Projects

BACKGROUND

This configuration setting enables to define how the project


number is coded for editing.

Following parameters are controlled in this setting to edit the


project number.

 Length of the key for project coding - Max. five


 Mandatory length of the project coding – whether all five
must be filled or not.
 Special characters allowed for entering WBS

SCENARIO

Define special character for projects.

INSTRUCTION

Follow the Menu Path: IMGProject System  Structures 


Operative Structures Work Breakdown Structures (WBS) 
Project Coding Mask  Define Special characters for Projects

Click or

use OPSK in the command field and press Enter.


Maintain fields as explained below
Field Name Value and Description of field
Length of key for coding of the project
definition and WBS elements.
Possible entries are

E.g.5 indicates maximum


It must be set carefully before creating any
projects.

We will proceed with 1 in our example.


Key used to specify project coding and
WBS element must of same length as it is
defined here.
E.g. Leave it blank not to restrict the length
of project coding and WBS element.
To help entering the WBS element in the
work break down structure, this special
key is defined.
E.g. Enter ". To enter a new WBS element
under WBS element, it is enough to enter "
and new number. E.g. say new number is
30, then system will maintain the number
with all prefixes and the number 30.
Special character used to limit the
segments in the coding.
E.g. / to limit with the character / between
the segments.
Check in this tick box will allow only the
coded project numbers within the project
system.
E.g. tick the check box.
This field is used for automatic number
assignment.
E.g. Leave it blank.

Click

Click

Impact of this configuration in Master Data /


Transaction

Project numbering will be as per this project special character


setting.
Define Project Coding Mask

BACKGROUND

This configuration setting enables to create masks for editing


the project number.

Project coding mask is helpful to simplify the complex project


numbers. It is also used to indicate the position of the WBS
element.

SCENARIO

Discuss the project coding mask. Ex: /000-XXX-000/XXXX

INSTRUCTION

Follow the Menu Path: IMGProject System  Structures 


Operative Structures Work Breakdown Structures (WBS) 
Project Coding Mask  Define Project Coding Mask

Click

Or Enter OK02 in the command field – press Enter.

Click

Maintain fields as explained below


Field Name Value and Description of field
Length of key for coding of the project
Note:- Here the project id can be maximum
of 1 digit as we have set up the PL field in
the above setting as 1.
Define the coding mask for project
definition
0 (zero) – only numeric characters
X – alpha numeric characters
Maintain description of coding mask
Tick in this check box will not enable the
new request for WBS element, project
definition or appropriation request to be
created with this masking code.
Tick in this check box will not allow
creating coding mask for standard project
or WBS element.

Click

Click

Impact of this configuration in Master Data /


Transaction

Project coding mask created here will be used while creation


project definition, WBS element or appropriate request.
Define Field selection for Work Breakdown Structures

BACKGROUND

This configuration setting enables to define the WBS field


selection.

Through this configuration setting it is possible to make a field


mandatory, optional, hide or view only.

It is required to make certain field to make mandatory


according to the business requirement.

SCENARIO

Make Project Description field as mandatory for company code


3000

INSTRUCTIONS

Follow the Menu Path: IMGProject System  Structures 


Operative Structures Work Breakdown Structures (WBS) 
User Interface Settings  Define Field Selection for Work
Breakdown Structures

Click
Double click

Double click on Description field


Click on

Click

Enter the company code as “1000”

select radio button

Double Click to influence any of one fields


Click

Double click

Similarly as explained above, field selection can be done for


WBS element also.

Note:- the procedure is same for Network field selection as well.

Impact of this configuration in Master Data /


Transaction
When creating project definition CO area become mandatory
entry
Define Validation

BACKGROUND

This configuration setting enables to define validation.

Use validations to check values and value combinations that


users enter in the Project System. Validation can be carried
out at various points in time.

Following are the steps to be carried-out:


 Enter a name for the validation.

 The application area is proposed by the system.

 Enter a call-up point when the validation should be


carried out.

 Create a validation step or select an existing one.

 Select the field that you want to use for the validation.

 Enter a prerequisite and specify how the validation


should be carried out.

 For each validation step enter a prerequisite, a check and


a validation message. The message is issued when the
prerequisite is met and when the value does not check.

SCENARIO

Discuss validation defining.

INSTRUCTION
Follow the Menu Path: IMGProject System  Structures 
Operative Structures Work Breakdown Structures (WBS) 
Maintain Validations

Click

Click the required object to create validation E.g.

Click

Enter validation name. e.g. ZLEGL02 and text as “check profit


center”

Click
Click to enter any prerequisite

Double click

Click

Click

Enter the project definition to which the check is to be


applicable.

Double Click
double click

Click

Click

Enter the value which must be maintained as profit center for


project definition with W

Click

Double Click

Enter message type

Enter message number.

Message variable entered if the message contains any variable.

Example: -

Message:- "Acount $ is not allowed in company code $"

Output field 1: BSEG-HKONT (=400000)


Output field 2: BSEG-BUKRS (=0001)

Click

Message appear at the bottom


Maintain Substitution

BACKGROUND

This configuration setting enables to define substitution.

Use substitutions to replace values and value combinations in


the Project System. In addition you can define several
interdependent substitution statements for future use.

Following are the steps to be carried-out:


 Enter a name for the Substitution.

 The application area is proposed by the system.

 Enter a call-up point when the substitution should be


carried out.

 Create a substitution step or select an existing one.

 Select the field that you want to use for the substitution.

 Enter a prerequisite and specify how the substitution


should be carried out.

SCENARIO

Discuss substitution defining.


INSTRUCTION

Follow the Menu Path: IMGProject System  Structures 


Operative Structures Work Breakdown Structures (WBS) 
Maintain Substitution
Click

Click on the object where the substitution is to be created. E.g.


whether on project definition or on WBS element

Click to create rule or click to create


substitution

Enter substitution key and text

Click
Enter the step number and text

Double click

Double click

Click

Click

Enter the finish date

Click
Double click

Click

Select the field person responsible

Click

Select the appropriate radio button. E.g.

Click
Enter the required value

Click
2. Define Time Profiles

BACKGROUND

This configuration setting enables to define the time profiles.

Time profile is used to specify various working time periods


used in the project planning board.

Time profile contains the evaluation period and planning


period.

Evaluation period is the time frame for working with and


displaying data in the project planning board. Beyond the
evaluation period, it is not possible to work with and display
the data in the planning board.

Planning period is used to define the time frame for carrying


out current planning in the project planning board.

 If the start date is beyond the current date, the planning


period begins with the start date.

If the start date is earlier than the current date, the


planning period begins with the current date.

SCENARIO

Discuss the time profile.


INSTRUCTION

Follow the Menu Path: IMGProject System  Structures


 Project Planning Board  Define Time Profiles

Click
Click

Maintain fields as explained below


Field Name Value and Description of field
Key identifying the time profile. Enter key
and description. E.g.

Key indicates the type of entry to be made.


I.e. Monthly, yearly. Select from available
entries
E.g. L to indicate years
for Enter start date. E.g. 0. Indicates start
evaluation period from 0 years
Start date is the date of the first day of the
period to which the data required to be
evaluated.
System determines the first date with entry
here along with entry type.
E.g. today is 14.01.2005
Type of entry: G
Start: -10
Finish : +20

This generates an evaluation period from


04.01.2005 to the 03.02.2005.
For Enter finish date. E.g. 2 indicates
evaluation evaluation allowed for next two years.
period.

Similarly maintain the entries as shown below for planning


period.
Click

Click

Click

Impact of this configuration in Master Data /


Transaction

Time profile defined here can be assigned to the project


planning board in the subsequent settings.
Define Profiles for Time Scales

BACKGROUND

This configuration setting enables to define Time scale


profile.

Time scale profile defines the properties of all possible


scales.

The possible time scale headings are

 Yearly split
 Quarterly split
 Monthly split
 Weekly split
 Daily split
 Hourly split
 Minute split
 Shift split

For each time scale heading maximum and minimum time


scale must be maintained.

SCENARIO

Discuss the profile for time scale.

INSTRUCTION

Follow the Menu Path: IMGProject System  Structures


 Project Planning Board  Define Profiles for Time Scales

Click
Click to create new entries.

Note:- it is always suggested to copy from the existing


standard entry.

Select any standard row. E.g. second row

Click

Enter the new time scale profile. E.g. ZPS_PROAAA


As the standard setting is sufficient nothing much to
change other than specifying the bar chart width in mm for
minimum and maximum.

Click

Click

Click

Impact of this configuration in Master Data /


Transaction

Profile for time scale defined here will be used in the project
planning board setting.
Define PRT Usage

BACKGROUND

This configuration setting enables to define the PRT usage.

Production Resource Usage controls the usage of PRT in


different task list and applications.

It is possible to allow the usage of PRT only in networks.

SCENARIO

Discuss the PRT usage setting.

INSTRUCTION

Follow the Menu Path: IMGProject System  Production


Resource Tool  General Data  Define PRT Usage

Click
Click to create new entries, SAP standard usage is
sufficient to work with. Let us discuss the standard usage
003.

Select usage 003

Double Click in the left side


Maintain the task list type under the usage.

Click

Click

Click

Impact of this configuration in Master Data /


Transaction

When creating the PRT, usage can be defined as per the


settings here.
3. Activate Project Management in Controlling
Area

BACKGROUND

This configuration setting enables to activate project


management in controlling area.

This setting also enables to activate the commitment


management for a controlling area.

SCENARIO

Discuss activation of project management in controlling area.

INSTRUCTIONS

Follow the Menu Path:- IMGProject System  Costs 


Activate Project Management in Controlling Area

Click
Available controlling areas are displayed at right side. Select
the desired row

To the desired controlling area activate the projects( )


and commitments management ( )
Note:- There could be other settings related to CO module, like
assigning the company code to controlling area etc.. but here
the point of activating project management only explained.

Click
Maintain Value categories

BACKGROUND

This configuration setting enables to define value categories.

Value categories are required for

 Updating project information database


 Calculating interest on projects
 Defining reports
 Updating quantities in project info.

SCENARIO

Discuss maintenance of value categories.


INSTRUCTIONS

Follow the Menu Path:- IMGProject System  Costs 


Value Categories  Maintain Value categories

Click

Enter the controlling area

Click

Click
Enter the value category. E.g. Z01

Enter the description for value category maintained.

Select the relevant radio button as explained below.

E.g. Cost radio button to the purpose of posting of costs or


outgoing payments.

Revenues to the purpose of posting revenues and incoming


payments

SKFw.Tt to the purpose of posting statistical key figure with


total characteristic value

SKF FVA to the purpose of posting statistical key figure with


fixed value characteristic
Click
Unit Costing

Unit costing will be where you have information on sources of


supply, quantities, and prices. Plan overall or annual values
for unit costing.

Costing variant is to combine all the controlling parameters for


costing. Costing variant represents the link between the
application and customizing because all costing run must
reference a costing variant as they are made and stored.

The costing variant controls the following parameter.

 Costing variant contains the valuation variant and


costing type.
 Valuation variant controls price to pickup for material,
subcontracting and external processing.
 Valuation variant contains the costing sheet also (over
head calculation)

BACKGROUND

This configuration setting enables to define the variants for


Unit costing.

SCENARIO

Define / discuss costing to create variant.

INSTRUCTIONS

Follow the Menu Path:- IMGProject System  Costs 


Manual cost planning in WBS  Unit Costing  Create
Costing Variant.

Or Enter OKKT in the command field – press Enter.


Maintain the fields as explained below
Field Description
This field sets how the cost to
be estimated based on the
materials, Production orders
with controlling, Internal
orders and sales orders.

Based on the type of business scenario costing variant is


created.

Click on new entries


In Control Tab maintain the field as explained below
Field Description
This field requires how the
cost estimate to be used. Ex:
unit cost est. for proj
This field specifies the prices
the system selects to valuate
the quantity structure of a
cost estimate with quantity
structure or of the order, or to
valuate the costing items of a
unit cost estimate. Ex:
Planned valuation –orders.
This field sets how the date
control of a cost estimate is
handled. Ex: Mod.std cost est.
dates
Click on the assignment tab

Click on to verify the variant. To verify the variant – variant


to be saved.

Click Save .

If the Variant is ok – system will give message

Impact of this configuration in Master Data /


Transaction

Based on the business scenario use the costing variant


Create / Change Planning Profile

BACKGROUND

This configuration setting enables to create / change planning


profile. Planning profile is required to plan the cost methods.

Following controls are available in the planning profile.

Time frame – can specify which values are the to planned and
their fiscal years.

Value display - to display the decimal places and decimal


factor

Detail planning – values for cost element planning ,activity


Input planning and cost planning.

Planning profile is used

 For all WBS elements or only on planning elements ,


 Bottom-Up planning within hierarchical planning ,
 Automatic revenue planning.

Based on the settings one can decide whether the system


updates plan revenues on the corresponding billing elements.

Profile can be Cost planning for investment programs or


investment measures, and for appropriation requests.

SCENARIO

Define / Discuss Planning profile.

INSTRUCTIONS
Follow the Menu Path:- IMGProject System  Costs 
Planned Costs  Manual cost planning in WBS 
Hierarchical Cost Planning  Create / Change Planning
Profile.

Or Enter OPSB in the command field – press Enter.

Click on the new entries or copy the existing plan based on


the business scenario.

Maintain the fields as explained below


Field Description
This sets the control
parameter for the planning.
In the Manual Planning -
when the Bottom up planning
indicator is set, the system
automatically carries out the
total up function in structure
planning for costs and
revenues each time you save
and check data. The structure
plan value for the higher level
WBS item is the total of all the
plan values for the WBS
elements directly below it.
To ensure that the structure
plan values for the whole
project structure are uniform,
must access the structure
planning for the whole project
and check and save the
values.
This field sets cost planning is
possible in only those WBS
elements are defined as
Planning elements. Can carry
the cost planning in any WBS
elements when the indicator is
set.
This field require the time
frame in future – means how
far can far.
Based on the scenario can
mention Past and start time
frames.
This field sets the values
required in total and annual
years.
This field sets whether any
decimal places and its scaling
factor required for the
planning profile.
This field sets the cost
element group as primary
costs where goods brought in
externally like raw materials ,
operating supplies ,
services ,etc based on the
chart of accounts. Ex:
OAS_PRIM
This field sets to summarize
cost elements of the same
types in reports. Ex:
OAS_REVEN
This field specifies the cost
center group of sender
for which activity types
are planned. EX: H1400
This field sets each activity
type in this group can appear
as a sender activity type in
activity input planning. EX:A1
This field sets a group of
stastical key figure used in
reporting to process multiple
key figures in a
single transaction. EX:
STAT_9000
This field sets how the cost
estimate is performed and
valuated. EX: INV1
This field sets the exchange
rate in the system and value
dates determines daily
exchange rates applies
For currency translation. EX:
001
This field sets the types of
planning currency based on
Controlling area currency /
object currency / Translation
currency. EX: Controlling area
currency.
This field sets how the
revenue planning should
happen automatically through
quotation or sales order..
This field requires to enter the
type of revenue element for
billing plan to WBS element.
Click Save .

Impact of this configuration in Master Data /


Transaction

Based on the planning profile – one can carry out Cost


Planning by entering values in the cost plan column using
CJ30 transaction code.
Maintain Budget Profile

BACKGROUND

This configuration setting enables to control the budget for the


Project.

SCENARIO

Define / Discuss budget profile.

INSTRUCTIONS

Follow the Menu Path:- IMGProject System  Costs 


Budget  Maintain Budget Profiles.

Or Enter OPS9 in the command field – press Enter.

Click on new entries or copy the existing profile based on the


Business scenario.

Maintain fields as explained below


Field Description
This field sets type profile type
and description. Ex: 1000
This field sets the time frames
which can in past, future or
start and enable total and
annual values. Ex: enable in
Future - 3
This field sets WBS element
using this budget profile can
only be budgeted if the WBS
element or a WBS element
above it in the hierarchy is
assigned to a program
position of an investment
program with the correct
program type. Ex: 1000.
This field sets type of control
that should be available while
budgeting and how the
activation type should be. i.e
Automatic activation during
budget allocation.
EX : 1 –means automatic
allocation during budget
activation.
This field sets a WBS element
using this budget profile can
only be budgeted if the WBS
element or a WBS element
above it in the hierarchy is
assigned to a program
position of an investment
program with the correct
program type. Ex: 1000.

Based on the type of business scenario use the control


parameters for network scheduling

Click Save .

Impact of this configuration in Master Data /


Transaction

Based on the business scenario define and use the control


parameters.
Define Tolerance Limits

BACKGROUND

This configuration setting enables to give tolerance limit for


the budget profile.

The Tolerance range /limits the budget if any project overruns


the allocated cost / money.

Activate availability control for a certain budget profile. Can


specify one or more tolerance limits for each activity group for
a budget profile.

Selected actions (warning, warning with mail to person


responsible for project, error message) are triggered when
these limits are reached.

Tolerance limit for all activity groups can be chosen as activity


group ++ which make entry easier. Tolerance limit for all
activity groups can be used if it is not required to define a
separate tolerance limit for each activity group.

It is possible to define a limit for a specific activity group in


addition to a tolerance limit defined for all activity groups.
This additional tolerance limit has priority over the generally
valid tolerance limit.

SCENARIO
Define / Discuss Tolerance limits.

INSTRUCTIONS

Follow the Menu Path:- IMGProject System  Costs 


Budget  Define Tolerance Limits.
Click on new entries if the controlling area belong to the
Controlling does not exists. If exists define the tolerance limits.

Field Description
This field tells about the
controlling area. Ex: 2000
This field sets the budget
profile to the controlling area.
Ex: 1000
This field tells about target
group of the activity type. Ex:
++ indicates that target group
belongs to all activity types.
This field sets activity type.
Ex: 1 /2 / 3.

This field sets how much the


usage should be for the said
budget profile.
This field tells about difference
between the assigned funds
and the budget exceeds the
absolute variance, availability
control triggers the
appropriate action.
This field tells about the
controlling area currency.

Click Save .
Impact of this configuration in Master Data /
Transaction

Based on the business scenario define the budget tolerance


limits.
Maintain Progress Version

BACKGROUND

This configuration setting enables to define the progress


version.

Progress version is required to create control data for


calculating the % of completion and the earned value.

Note:- This is to be done in discussion with CO team

SCENARIO

Discuss progress version .

INSTRUCTIONS

Follow the Menu Path:- IMGProject System  Progress 


Progress Analysis  Maintain Progress Version

Click

Click to create new entry


Maintain the fields as explained below
Field Description
Key identifying the controlling
area. Enter controlling area
Key identifying the progress
version. Enter progress
version and description
Key identifying the plan
version. Note:- the CO version
must have exclusive use 03
i.e. earned value analysis.
Earned value is calculated by
applying the % of completion
of the cost amount. This
defines which cost amount is
to be used. Available entries
are
Value used for weighting in
the aggregation of the % of
completion. Possible entries
are

Key identifying the type of


planning to be used. Available
entries are

This key to determine whether


either:
 the earliest date is set to
the latest date of the
activity or
 The latest date is set to
the earliest date of the
activity.
Tick in this check box will
enable the system to use the
system uses an existing
method if the method is not
maintained.

Click
4. Scheduling Types

BACKGROUND

This configuration setting enables to define the scheduling


types to the projects.

Scheduling types governs the way scheduling is to be


performed.

SCENARIO

Define / Discuss scheduling types.

INSTRUCTIONS

Follow the Menu Path:- IMGProject System  Dates 


Scheduling  Define scheduling types.

Or Enter OPJN in the command field – press Enter.


Field Description
This indicator sets the
scheduling type as Forward
for orders and Networks
means schedules from the
start date.
This indicator sets the
scheduling type as backward
for orders and Networks –
means schedules from the
Finish date.
This indicator sets the
capacity requirements to
calculate. Distributed across
the periods based on the types
of dates.

This indicator sets as today’s


date for scheduling.
This indicator sets the time to
enter the basic dates for the
production orders.

Based on the type of business scenario use the scheduling


type.

Click Save .

Impact of this configuration in Transaction

When performing the scheduling in the project, scheduling will


be carried out as per the setting maintained here.
Parameters for Network Scheduling

BACKGROUND

This configuration setting enables to define parameter for


network scheduling.

Network scheduling contains settings for

 Dates adjustment
 Type scheduling to be performed
 Control to allow start day in the past
 Reduction type

This setting is performed for the combination of Plant, order


type and Production scheduler.

SCENARIO

Define / Discuss control parameters of scheduling.

INSTRUCTIONS

Follow the Menu Path:- IMGProject System  Dates 


Scheduling  Specify Parameters for Network scheduling.

Or Enter OPU6 in the command field – press Enter.


Field Description
Key identifying the plant.
E.g. 1000
Key identifying order type.
E.g. PS05
Key identifying the production
scheduler.
E.g. *
This control determination of basic
dates to the element or to its
dependant requirements during
lead time scheduling.
Type of scheduling to be applied to
this order type or network type.
Indicates whether the past start
date is allowed. If it is to be
allowed, enter the number of days.
E.g. Leave it blank.
Tick in this check box
automatically schedule the network
on saving.
Tick in this check box displays
scheduling log automatically during
each scheduling
e.g. Leave it blank
Tick in this check box considers the
exact time of break during
scheduling.
e.g. Leave it blank
Tick in this check box will not
consider the partially confirmed
operations.
E.g. Leave it blank
This tick mark to schedule the
component on latest scheduled
date.
Indicates what reduction type is to
be employed
Number of reduction level to be
applied.

Click Save

Impact of this configuration in Master Data /


Transaction

During network creation, scheduling will be done according to


the settings maintained here.
Define Database Selection Profile

BACKGROUND

This configuration setting enables to define Database selection


profile.

This is the process of picking up the desired objects and fields


from the database for information analysis purpose.

Note: - Standard SAP setting will be sufficient in most of the


cases. Let us discuss the standard setting and understand.

SCENARIO

Discuss the Database selection profile.

INSTRUCTION

Follow the Menu Path: IMGProject System Information


system  Selection  Define Database Selection Profile

Click
Field Name Value and Description of field
Tick in this check box will enable only last
person who made changes only to make
further changes
Tick in this check box will pickup its
superior objects also. E.g. WBS elements
are selected as objects, but it will pickup
its project definition also.
Changes can be made only through the
configuration setting if this check box is
ticked.
Tick in this check box will pickup project
definition from the database
If not ticked, project can not be made as a
selection criteria as project definition does
not appear in the selection screen.
Tick in this check box will pickup sales
order and customer quotation for selection
Tick in this check box will pickup material
component from Database.
Tick in this check box will pickup WBS
element
Tick in this check box will pickup
hierarchy of sub element of WBS.
Tick in this check box will stipulate
network and orders assigned to WBS.
Tick in this check box will pickup network
assigned to WBS element
Tick in this check box will pickup the
production order, process orders assigned
to WBS

Similarly all check boxes which are ticked are selected from
the data base.

Click

Click

Impact of this configuration in Master Data /


Transaction

Information system when displaying the objects, it will pickup


data from database as per the configuration maintained here.

That’s it then… The entire PS configuration pack comes


in 7 voluminous power packed CDS f u l l o f m e a t y c o n t e n t and
each sub module in SAP PS is broken into Configuration, End
user and Power point. There are tons of bonuses which you get
along with this pack including complete Integration documents,
PS Interview questions and answers and a boatload of step by
step guides……… You can take advantage of the special offer by
visiting the site at

http://www.sap-topjobs.com/SpecialPP/sapps20071123.html
All our packs are shipped thru FedEx and reaches you in three
days time. One more thing this configuration pack is compatible with
version 4.7, version 5.0 and 6.0 So you really do have to worry about
the version at all.. We have taken care of that… Also all future
version changes will be provided as free updates to you. So you can
sit back relax and play the music ….

What I want from you now is to do yourself a favour by bringing


the brains and wisdom of SAP PS Experts with more than
12+yrs of implementation experience to your drawing room today.
Do it right now my dear friend and take your SAP career to the
next level…. You will love it I promise you….