Professional Documents
Culture Documents
Rencana Angs Pembayaran
Rencana Angs Pembayaran
No. Sertifikat test Bobot ( % ) Nilai Pemotongan PPN Pembayaran Komulatif Sisa Pembayaran Keterangan
(%) Progress P. Uang Muka Retensi Ke Kontraktor Pembayaran Progress
Progress Akum. ( Rp ) ( Rp ) ( Rp ) ( Rp )
1 Pembayaran No. 1 Direct Owner 20% DP 0.0000 - - - 5,200,000,000.00 5,200,000,000.00 20,800,000,000.00
2 Pembayaran No. 1 12.2974 3,197,324,000 639,464,800.00 159,866,200.00 2,397,993,000.00 239,799,300.00 2,637,792,300.00 7,837,792,300.00 18,162,207,700.00
3 Pembayaran No. 2 10.1809 2,647,034,000 529,406,800.00 132,351,700.00 1,985,275,500.00 198,527,550.00 2,183,803,050.00 10,021,595,350.00 15,978,404,650.00
4 Pembayaran No. 3 10.0397 2,610,322,000 522,064,400.00 130,516,100.00 1,957,741,500.00 195,774,150.00 2,153,515,650.00 12,175,111,000.00 13,824,889,000.00
5 Pembayaran No. 4 7.4820 1,945,320,000 389,064,000.00 97,266,000.00 1,458,990,000.00 145,899,000.00 1,604,889,000.00 13,780,000,000.00 12,220,000,000.00
6 Pembayaran No. 5 10.0000 2,600,000,000 520,000,000.00 130,000,000.00 1,950,000,000.00 195,000,000.00 2,145,000,000.00 15,925,000,000.00 10,075,000,000.00
7 Pembayaran No. 6 10.0000 2,600,000,000 520,000,000.00 130,000,000.00 1,950,000,000.00 195,000,000.00 2,145,000,000.00 18,070,000,000.00 7,930,000,000.00
8 Pembayaran No. 7 10.0000 2,600,000,000 520,000,000.00 130,000,000.00 1,950,000,000.00 195,000,000.00 2,145,000,000.00 20,215,000,000.00 5,785,000,000.00
9 Pembayaran No. 8 10.0000 2,600,000,000 520,000,000.00 130,000,000.00 1,950,000,000.00 195,000,000.00 2,145,000,000.00 22,360,000,000.00 3,640,000,000.00
10 Pembayaran No. 9 10.0000 2,600,000,000 520,000,000.00 130,000,000.00 1,950,000,000.00 195,000,000.00 2,145,000,000.00 24,505,000,000.00 1,495,000,000.00
11 Pembayaran No. 10 10.0000 2,600,000,000 520,000,000.00 130,000,000.00 1,950,000,000.00 195,000,000.00 2,145,000,000.00 26,650,000,000.00 (650,000,000.00)
Jakarta, 28 Mei 2018 Disiapkan Oleh,Manajemen Konstruksi PT. Quantity Surveyor Nusantara
Aedon Astama …………. Direktur
Rp. 26,000,000,000.00
PPN Pembayaran
Retensi Ke Kontraktor
( Rp )
- 5,200,000,000.00
159,866,200.00 2,397,993,000.00 239,799,300.00 2,637,792,300.00
132,351,700.00 1,345,810,700.00 134,581,070.00 1,480,391,770.00
130,516,100.00 788,869,900.00 78,886,990.00 867,756,890.00
97,266,000.00 (231,946,000.00) (23,194,600.00) (255,140,600.00)
130,000,000.00 (130,000,000.00) (13,000,000.00) (143,000,000.00)
130,000,000.00 (650,000,000.00) (65,000,000.00) (715,000,000.00)
130,000,000.00 (1,170,000,000.00) (117,000,000.00) (1,287,000,000.00)
130,000,000.00 (1,690,000,000.00) (169,000,000.00) (1,859,000,000.00)
130,000,000.00 (2,210,000,000.00) (221,000,000.00) (2,431,000,000.00)
130,000,000.00 (2,730,000,000.00) (273,000,000.00) (3,003,000,000.00)
25,572,072,760.00
Pemborong : PT. Griya Trada
26,000,000,000.00
SKEMA IDEAL
Pemberi Tugas : Mr. Suresh G. Vaswani RENCANA KEUANGAN KONTRAKTOR Nilai Kontrak Awal : Rp. 26,000,000,000.00
VO. Nilai Kontrak : Rp. 28,600,000,000.00
Paket Pekerjaan : Rp Nilai Kontrak Akhir : 26,000,000,000.00 28,600,000,000.00
No. Kontrak : STRUKTUR ARSITEKTUR MEP & FURNITURE Uang Muka : 5,200,000,000.00
Retensi Akhir : 001/SPP/SA.MEP/GT-BRW/VIII/2017
Waktu Pelaksanaan : 04 September 2017 s/d Agustus 2019
Pemby+PPN
22,100,000,000.00
28,600,000,000.00
-
66,175,850.00
79,933,100.00 2,218,773,700.00 tag 3
146,108,950.00 4,967,704,300.00 tag 1&2
2,364,882,650.00 14,913,522,000.00 tag 4&10
cek diterima GT next 22,100,000,000.00 OK….
SIMULASI. 1
Pemberi Tugas : Mr. Suresh G. Vaswani RENCANA KEUANGAN KONTRAKTOR Nilai Kontrak Awal : Rp. 26,000,000,000.00 Pemborong : PT. Griya Trada
VO. Nilai Kontrak : Rp. 28,600,000,000.00
Paket Pekerjaan : Rp Nilai Kontrak Akhir : 26,000,000,000.00 28,600,000,000.00
No. Kontrak : STRUKTUR ARSITEKTUR MEP & FURNITURE Uang Muka : 5,200,000,000.00
Retensi Akhir : 001/SPP/SA.MEP/GT-BRW/VIII/2017
Waktu Pelaksanaan : 04 September 2017 s/d Agustus 2019