Concreto Cimentacion
Concreto Cimentacion
90
ϑt = 2 kg/cm2
ϑt = 2 - 0.24 - 0.08 - 0
ϑt = 1.68 kg/cm2
L= 285714.29 = 534.52
530 = 540 cm
5.70
1.50
qu = 1.2 400 + 1.6 80
0.9 29.64
5.20 0.9 1.50
qu = 20.51 Ton/m2
d = 100 - 10
d = 90 cm
CHEQUEAR CORTANTE
Vu= qu L1 Lo
Vu= 20.51 5.70 1.50
Vu= 175.38 Ton
# Vc = 0.53 1 + 2 210 L1 d
B
Vu= qu L2 Lo
Vu= 20.5128 5.20 1.50
Vu= 160.00 Ton
# Vc = 0.53 1 + 2 210 L2 d
B
Vc = 678.95 Ton
Vc > Vn
678.95 > 213.33 CUMPLE
CHEQUEAR PUNZONAMIENTO
# Vc = 1.06 210 bo d
Vc = 857.14 Ton
Vc > Vn
857.14 > 746.67 CUMPLE
CALCULO DE ESFUERZO
5.20
2.40
Mu = 307.2 Ton-m
Mn = Mu = 307.2 = 341.33 Ton-m
0.9 0.9
1.00
5.20
ASUMIR a= 90 X 5%
a= 4.5
CALCULAR: As = 341.3 x 10 5
4200 x 90 - 4.50
2
As = 92.62 cm2
a = 4.19 cm
= 0 kg/cm2
= 0.08 kg/cm2
= 0.24 kg/cm2