Designing Sydney’s
ane Cove Tunnel
he progession of the USS823M Lane
‘Cove Tunnel Project has been rapid,
following planning approval in 2002.
‘Tenders were submitted in January of
20083 and following a period of bidding
‘and negotiations, the New South Wales Government
entered into an agreement withthe Lane Cove Tunnel
Consortia in December 2003 to design, construct,
finance, operate and maintain the project as a toll
road. A joint venture of Australian contractors, Thiess
‘and John Holland are delivering the project under a
dosign-construct contract. Parsons Brinckerhoff (PB)
js the lead designer for the tunnels and the cil
structural components ofthe project.
Inadditon to the tunnoling work, the project spans
‘over 8km of surface roadway improvements through a
congested roadway corider, passing through
residential and industvial areas in north west Sydney.
{igure 1), The benefits ofthe project includ reduced
travel time, reduced congestion, improved public
transport and improved neighbourhood amenities for
pedestrians and bicycle users.
“The scheme design begen in December 2009 and is
now at a mature stage. Tunnel design will be
‘completed before Christmas 2004
The project is being delivered under a rigorous
‘quality assurance program involving both internal anc
extemal review by the Roads and Trafic Authority
(FA) and an independent verifier. The frst temporary
‘access tunnel design was approved in time for
‘construction to begin in May 2004 from the western
fend and the second in July from the eastern end. The:
first permanent tunnel design was approved in time for
‘mainline tunnel construction to bagn in August
By mid-September adkitional design had been
approved and four roadheaders are now operating at
three locations. Altogether, seven SOOkw roadheaders
are scheduled to excavate the tunnels, two Mitsui SLB
200 and five Voest Alpine ATM105 (figure 2). The
‘mechanised tiling end instalation of rockbolts is
performed by either an Atlas Copco Boltoc LD unit or
‘8 Boomer 135/352.
‘Tunnel design overview
‘The 3,6km long east-bound and west-bound tunnels
comprise the signature features of the Lane Cove
‘Tunnel Project. However, a labyrinth of additional
Underground ventilation and emergency egress
tunnels are also required to meet stringent operational
congested mode and emergency scenarios.
‘The eastbound tunnel provides two traffic lanes in a
cross sectional area ranging trom 53.271-58.40m°,
‘rom the western driven portal to point just east of
Stringyberk Creek. Here the tunnel widens to 76.26m?
‘to accommodate three traffic lanes for a distance of
1500m, and then a lane diverges as an exit ramp to
the Pacile Highway, whist the two main lanes
PROJECT REPORT - AUSTRALIA
‘continue {0 the eastem portal. The exit ramp will be
some 450m long, and comprises two trafic lanes.
The westbound tunnel starts as a 53.27n-68.49m®
two lane tunnel from the east portal, and is then joined
(efter a distance of approximately 600m) by an entry
ramp from the Pacific Highway. Folowing the junction
vith the entry ramp, the tunnel becomes a 76.26m"
three lane cariageway all the way to the west portal
“The entry ramp will be approximately 350m long, enc
‘comprises one trafic lane with a 2m wide emergency
stopping lane.
Pedestrian cross passages/emergency egress are
provided at a maximum spacing of 120m, in
accordance with the project egress requirements. The
‘ross sectional dimensions of the passages are about
‘5m wide by 3.9m high. Two vehicular cross passages,
with fe rated role shutter, are provided at one-third
distances in the tunnel for access for emergency
Vehicles during an incident. These cross passages are
sized to allow a single uit tuck to negotiate a U-turn
from one tunnel te the othor in one pass.
‘Two ventilation tunnels wil connect the main tunnols
to ventilation stacks located at Marden Siroct and
Skius Road. These entiation tunnels will be
approximately 60m" and 90m? in cross. section
respectively, to mest ventilation requirements, and are
‘about 500m in length. The Marden Street ventiation
tunnel will extract viiated ar from the eastbound
tunnel and the Pacific Highway exit ramp. The Sirius
Road ventilation tunnel off-take from the main
wastbound tunnel will be located at a distance of
approximately 1360m from the west porta, and the
tunnel will be about 500m in length with a low point
‘below the crossing of Stinaybark Creek. Al the end of
the Sirus Road ventlation tunnel, a 35m deep vertical
‘shaft wil provide access to the surface.
‘A sepatate ventilation exhaust tunnel Is provided
bbolow the westbound carriageway to remove vitiated
air from the east and westbound tunnels. The exhaust
‘ducts for these cariagenays are located upstream of
ai gona
‘The 3.6km long
twin-tube Lane
Cove Tunnel in
Sydney, New
South Wales is
scheduled to open
in 2007. Here, Jim
Rozek, project
design director for
Parsons
Brinckerhol,
describes the
current status of
the project and
details how the
local geology has
affected the tunnel
design
Bolow: Fig 1 - Plan
iogram of the Lane Cove
Tunnel project
NOVEMBER 2004 Tunnels & Tunnelling InternationalPROJECT REPORT - AUSTRALIA
Fights Fig 2 - Pan of the
‘tunnel systems with
roadeader excavation
sections marked up
Marden Stroot ventilation
‘oxhauet tunnel
owbeay Park work ta
‘Peacheader access)
&
astound
‘ne
Silus Road
Frodharitake
[i rocercadert IRE Poscheecor 2 WI Rascneacer 5 MEI Roecheacer 7
us poed| (MI | pu ecacreader2 EE Roscroecer + WE Roaceecors
the inlet vent tunnel at approximately the mic point of
the tunnels
“The exit and entrance ramps tothe Pacific Highway
require emergency egress provisions at 120m spacing
Capable of wheelchair egress, simier to the mainline
tunnels. Since the ramps are close to the surface than
the main lane tunnels, emergency egress is provided
between the ext and entrance ramps. by using
‘separate passages in the adjacent ventiation tunnels
to provide egress.
Driven tunnel and cut & cover
‘The Lane Cave tunnels are predominantly driven
tunnels, with cut and cover sections at each end of the
rain lane tunnels and the portals of the ramps. The
‘main lane tunnels have common cut and cover
‘structures at both the western and eastam ends. The
western cut and cover structure is located east of the
Mowbray Road intersaction in Epping Road. This
portal section will involve bored pile and top down
‘construction within a stagad excavation.
“The eastern cut and cover portal is Iocated in the
middle of the Gore Hill Freavy, immediataly west of
the Reserve Road fly-over. A short cut and cover box
is required to facilitate the transition from driven tunnel
to a deep cutting, The cut and cover box will be
‘approximately 76m long and 15m-20m deep. A secant
pile perimeter wall supported with up to four levels of
{ground anchors will be used to support the excavation
Until the tunnel roof and floor slab is constructed. The
fexcavation above the cut and cover tunnel wil then be
bbackillad end landscaped,
‘The westbound entry ramp from the Pacific
Highway joins the
two lane west
bound tunne! 200m
wost of the Pacitic
Highway, via a
portal and deciine
fn the eastern side
of the Pacific
Highway beneath
Ato piace,
‘The east bound
exit ramp to Paciic
Highway reaches
the Gore Hill
Freeway in a deep
cutting
Geotechnical conditions
‘The tunnels will be excavated in the upper
sedimentary formations of the Sydney Basin
stratigraphic sequence, which consists of sub
horizontal bads of middle to early Tassic aged rock
comprising Hawkesbury Sandstone, Mittagong
Formation and Ashfield Shale,
“The Hawkesbury Sandstone formation is. ill
known a8 a good tunnel medium, comprising
predominantly fine to medium grained quartzose
Sandstone deposited in 1m-m thick beds and lenses
that exhibit either massive structure or foreset cross
beds dipping at 20-30". Erosive contacts are common
between beds, and shale breccia channe! lag type
deposits are observed at the base of some beds.
‘Shale (sitstonenterbeds and lenses make up a minor
part of the sequence.
“The Mittagong Formation is typically 5m thick and
‘comprises interbedded sandstone, laminate, siltstone
‘and. claystone and is the tanstion ffom the
Hawkesbury Sandstone and the upper Ashfield Shale.
‘The Ashfield Shale comprises dark grey to black
laminated carbonaceous and calcareous siltstones
‘and mudstone with rare sandstone laminae:
Typically the bedding planes are subhrizontally
bedded, although steaper bedding canbe
encountered in the Ashfield Shale, The spacings
between bedding planes in the Hawkesbury
‘Sandstone is typically 0.5m-3m, Joints are typically
discrete and contained within. individual beds,
approximately 15% have a vertical continuity of about
'5m of more. The major joint sets in the Hawkesbury
Sandstone trend north-south and eastanest with a
‘subordinate northwest-southeast set
Design parameters vere developed on the basis of
geotechnical information available, supplementary
project specific exploration was cared out, and
(geological experiance in the Sydney Basin
environment was used to develop the design
parameters for the various goological strata and
defect types.
Driven tunnelling conditions
The majority of the tunnel in the western half will bo
Within Hawkesbury Sandstone. From the tunnels mid-
point to the eastern portal, the tunnel horizon
‘comprises the Mittagong Formation, and the lower
member of the Ashfield Shale. The tunnel traverses
‘through all the above formations and is expected to
Tunnels & Tunnelling International NOVEMBER 2004PROJECT REPORT
AUSTRALIA
Fight: An excavated
section of tree lane
tunnel plus breakdown bay
‘panning 16m. Note the
‘wo heading development
atthe far face
Acknowledgments:
“The author would ke
to thank P's Dr. Doug
‘Maconachio, who
‘managed and led the
tunnel design, and to
his staff of tunnel,
structural, geotechnical
engineers and
geologists. The tunnel
sign tear is
comprised of Parsons
Brinckerhof staf and
its subconsultants,
Coffey Geosciences
‘and Polls Sulivan &
Meynick. Grateful
‘acknowledgement is
‘also made to the stat
(of Thiess and John
Holland, for their
‘support and active
participation in the
osign process.
Bolow: Atypical section of
‘wo lane tunnel excavated
In sandstone with a fat
root
encounter zones of inferior rack associated with faults,
shale interbeds, volcanic dykes and joint swarms.
Heavier support will be required to these areas,
The fist 275m of tunnel from the eastern portal
postions the tunnel crown within about 4m ofthe floor
of a back filed brick pit. The quality of the rock
‘beneath the brick pit is assessed to be typicaly good,
‘put may be fractured as a result of blasting/excavation
‘ofthe shale during operation of the brick pit
Probe driling and grouting will be carried out forthe
200m section of the tuna in this aree. Appropriate
Contingency measures are being doveloped, with
{routing expected to be used if short-term dewatering
(ofthe backfiled brik pit would result in unaccoptable
surface settlements.
‘Where a tunnel crown is located in sandstone
possessing nearhorizontal bedding planes and
Characteristic joint sets and typically reguar joint
‘spacing of between 2m-Sm, the tunnel will have a fat
arch roof. The temporary and permanent support
consists of rockoolts, whose length is largely
dependent on the span, The tunnel sidewalls are
excavated as vertical walls thereby completing the
53.27? cross sectional area designed for two lane
stretches,
‘Where the crovin is located in the shale formation, a
higher arched tunnel crown will be constructed giving
a larger 58.49m? cross sectional area in the two lane
tunnel length. At the junction of the Pacific Highway
coxit and entry ramps with the main tunnels, the
‘excavation profile requires spans of up to 21m.
‘A rock pila of suficiont width is required to carry
the rock load without being over stressed. These
substantial spans requir significant support in the
form of rock anchors, steel fibre re-inforoed shotereta
and latice girders. Cablo bolts will bo installed forthe
reck support in the ramp junction areas. The tunnel
junctions are located in Mittagong Formation and
Ashfield Shale.
Low cover occurs in the eastern end of the tunnels
‘beneath the Artaman brick pit and in the entry ramp.
Depending on the characteristics of the rock mass
‘encountered at these critical sections, the support
selected will take one of the following forms:
«@ In areas of highly weathered rock mass (mainly in
the Ashfield Shale), passive support will be provided
sing techniques such as: canopy tubes, spiing
‘bars, sequential heading and bench methods,
lattice gilars and fibre reinforced shoterete (FRS),
steel sets
‘In areas of weathered rock mass or very shallow
cover, passive support wil be provided by lattice
dirders/stea sats and FAS. Active support trom pre-
tensioned rock bots is nt achievable; and
in areas of competent rock, rock bolts in
combination with FRS will be used. The exact
number of bolts and shotorete thickness will vary
depending on the class of the rock mass
‘encountered and the span
‘Tunnelling mathode similar to those used in soft
‘ground may be adapted to tunnel beneath the brick pit
fil at the eastern end of the tunnel. These methods.
‘may comprise sping bars or canopy tubes, sequential
heading and bench, lattice girders, stool sets, FRS,
‘ground treatment (grouting). Suppor requirements il
bbe derived based on detailed analyses of the ground
loading and settlement criteria
Design methodology
‘The design methodology that has been utlsed began
with the development of geotechnical long-sections
and cross-sections to assess the likely rock block
‘szes to be encountered. A study of precedent
practice of large-span caverns in Hawkesbury
Sandstone and simiar strata was performed to
establish precedents for roof support raquirements
‘and measured deformations. There was a comparison
fof empirical guidelines for large-span tunnels. in
horizontally bedded strata. Analysis was performed
Using Voussoir beam methods and bedding plane
hear reinforcement concepts.
Numerical modeling was performed to investigate
the rock mass response with the support levels
indicated by the analytical study. This modeling was
typically used for wide span junctions, jet fan
‘enlargements, intersections in typical and advoreo
rock conditions, and excavation and support
sequencing. Analytical and numerical studios wore
‘also performed for secondary openings, junctions and
passageways.
Inthe analysis ofthe flat bedded roofs, the stability
of the tunnel excavation within horizontally bedded
strata was analysed by considering the performance
‘of a single roof beam deflecting under its own weight
and an allowance for surcharge loading. ‘The
subsequent design of rock bolt support involved the
assessment of shear displacements along horizontal
bedding planes. The fundamental requirement of the
design process was to control the shear
displacements along bedding planes within the
required thickness ofthe ‘lineer arch’ assumed to form
inthestrata,
Tunnels & Tunneling International NOVEMBER 2004PROJECT REPORT - AUSTRALIA
‘The rock bolt reinforcoment thereby artificially
‘ensures that the thickness of the roof beam is
sufficient for the beam to become sof-supporting.
Numerical analysis was performed utilising either
Phase? or FLAC. The numerical analyses using Phase*
software was used to assess the tunneling-induced
‘round movernents and stesses.
Inthe arch roof, Phase’ modeling ofthe typical roof
‘construction was performed. It was important to
reflect the geotechnical concitions, and examine the
effects of the staging of excavation and installation of
supports. Te effects of shearing atthe haunch in the
arched roof sections in shale was examined in greater
etal. Considerable numerical modeling was
performed. Geotechnical sections for numerical
modeling were selected based on various
{geotechnical profes, overburden thickness, surface
structures and special ggological features. Models
‘were set up to represent possible tunnel config-
trations and geological conditions along the tunnel
alignment
General aspects of the analytical modelling
included parametric studies using generic models in
Phase®. Its aim was to assess the impact of various
‘geometric and geological features on the tunnel
designs and to identify critical design
parameters/conditions. Phase” was also used to
‘address specific design issues during the intial
‘modeling stage. In particular, the sensitivity of in situ
stress state and tunnel geometry on tunnel and
ground surface displacements was studied. Two
‘geological domains (typical and adverse concitions),
tunnel support systems, specific structures and
‘construction sequences were analysed as
appropriate.
Construction requirements
Construction access to the
eastern ond of the driven
tunnels is provided through
the excavation ofthe easter
ventilation tunnel and access
adit from Marden Street,
which joins the mainline
tual,
‘The adit may be used to
house equipment for the
permanent works and during
the tunnel operation phase it
may also be used as a
permanent access for emergency vehicles to gain Abo
‘access to an incident inthe tunnel
Construction staging
‘As can be gathered, the tunnels will be major
‘excavations in rock. The rock mass response to the
‘excavations willbe dependent toa large degree on the
‘excavation sequence adopted. It Is therefore a key
requirement that the tunnel design is progressed in
Close liaison with the construction planning team, anc
that construction sequencing forms an integral pat of
the design.
‘The excavation staging takes into account the plant
‘and equipment to be used by the contractor. For
‘example, all excavation stages must be dimensioned
to sult the requirements of the principal roadheader
‘excavation plant in terms of advance lengths and
reach, etc. Similarly, the rock support elemonts, in the
form of rock bolts and/or cable bots, will be installed
close to, or at specitiod cistances from, advancing
faces headings. we
one tuna in
sandetone with an AMIO5,
roadheader perked beside |
‘an ar serubber unit
NOVEMBER 2004 Tunnels ¢ Tunnelling International
What is most 2 fe As.
important when concreting tunnels!
is the right partner!
Putzmeister has just the right system solution for
your project. With powerful concrete pumps, reliable |
placing systems and of course a lot of know-how
from numerous tunnel projects.